CN204283450U - A kind of anchor bar of waterproof plate in tunnels and sweating welder thereof - Google Patents

A kind of anchor bar of waterproof plate in tunnels and sweating welder thereof Download PDF

Info

Publication number
CN204283450U
CN204283450U CN201420613545.5U CN201420613545U CN204283450U CN 204283450 U CN204283450 U CN 204283450U CN 201420613545 U CN201420613545 U CN 201420613545U CN 204283450 U CN204283450 U CN 204283450U
Authority
CN
China
Prior art keywords
splash guard
tape splicing
seal weld
welding
interannular
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201420613545.5U
Other languages
Chinese (zh)
Inventor
郑杭蓉
邓卫东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Changshu Jiafa Chemical Co ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201420613545.5U priority Critical patent/CN204283450U/en
Application granted granted Critical
Publication of CN204283450U publication Critical patent/CN204283450U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a kind of anchor bar of waterproof plate in tunnels and sweating welder thereof, at splash guard interannular overlap, splash guard front and/or reverse side arrange and merge seal weld tape splicing, the distribution arrangement merging seal weld tape splicing is identical with the bead direction of interannular overlap, merges the fusing point of fusing point lower than splash guard material of seal welding carrying material, during welding, bonding machine increases by one group of squeezing roller, to while splash guard sweat soldering or after sweat soldering, the heating arrangements of bonding machine heats fusion seal welding band, fusion seal weld tape splicing is made to melt to liquid-plastic state on splash guard, the fusion seal weld tape splicing of the squeezing roller extruding liquid-plastic state of the increase of bonding machine, it is made to diffuse to welded seam area, butt welded seam carries out mending-leakage reinforcement, the seal weld of continuous uniform is formed at former fusion seal weld tape splicing place, the utility model makes up climbs the defect of welding technology in constructing tunnel, improve waterproof construction technology and equipment, improve waterproof construction quality.

Description

A kind of anchor bar of waterproof plate in tunnels and sweating welder thereof
Technical field
The utility model relates to the tunnel splash guards such as a kind of railway, highway, water conservancy, and this splash guard effectively can realize welded seal, ensures welding quality.The utility model also relates to the sweating welder adopted in welding method between this splash guard and this welding method.
Background technology
Railway tunnel, highway tunnel, water conservancy anchor bar of waterproof plate in tunnels interannular adopt hot melt portable welding machine of creeping to weld two adjacent splash guards mostly, by splash guard according to function zoning, the region of adjacent two width splash guard overlaps is called interannular overlap or superimposed district, and the width in superimposed district is generally 10-15 centimetre.In current welding procedure, superimposed district center forms the parallel heat smelting crimp connection weld seam of twice, and this weld width is generally 1.5-2 centimetre.
Above-mentioned sweat soldering main technique principle is: adopt heating plate or hot blast, be heated to molten condition, roll through mechanical rollers splash guard superimposed district inner surface material, the crimping of superimposed splash guard is made up.Climb welder in forward plane-welding field as refuse landfill, pond waterproofing course, in water works, effect is reliable, but be applied to anchor bar of waterproof plate in tunnels when oppositely welding, because tunnel contour is arcuate structure, for keep splash guard and Tunnel layer closely connected, need reserved sag, splash guard thus be in relaxed state, adding in heat welding process to anchor bar of waterproof plate in tunnels, because collection location is inaccurate, water is also had in tunnel, dust, the factor impacts such as Mechanical Moving traveling speed, affect the uniformity that plate surface, weld zone is heated, be difficult to the uniformity synchronously reaching melt temperature, over-heating then can cause splash guard excessive melting, destroy material body intensity, be difficult to effectively to form firm continuous print and make weld zone up, welding effect is subject to the restriction of execution conditions, it is one of Major Diseases source of current tunnel leak.
Utility model content
Technical problem to be solved in the utility model is to provide one effectively can realize welded seal, ensures the splash guard of welding quality; In addition, the utility model also provides the sweating welder adopted in welding method between above-mentioned splash guard and this welding method.
For solving the problems of the technologies described above, the utility model has done further improvement to traditional splash guard: both sides are interannular overlap, adjacent two width splash guards are by being welded together at interannular overlap, it is characterized in that: at the interannular overlap of splash guard, the front of splash guard and/or reverse side are provided with and merge sealing fusion seal weld tape splicing, the distribution arrangement of described fusion seal weld tape splicing is identical with the bead direction of interannular overlap, and the fusing point of described fusion seal welding carrying material is lower than the fusing point of splash guard material.The front of splash guard and/or reverse side are provided with and merge seal weld tape splicing and represent: the front of splash guard, reverse side or obverse and reverse are provided with and merge seal weld tape splicing.
The utility model makes full use of climbs soldering equipment and cardinal principle at present, hot melt can be still adopted to creep welding, according to the process of current railway tunnel construction, utilize and climb the gap that weld seam adjacent region is merged in Welding welding at present, preset at splash guard interannular overlap and merge seal weld tape splicing, the material fusing point of this fusion seal weld tape splicing lower than splash guard mother metal fusing point, positioning molding synchronous with splash guard in splash guard manufacture process.When adding thermal weld to splash guard interannular overlap, merge seal weld tape splicing because fusing point is lower than the fusing point of mother metal, liquid-plastic state can be melted to, weld zone band is incorporated through climbing the extruding of welding machine roller, it is forced to diffuse to the weld metal zone of both sides, to strengthen the mending-leakage reinforcement to original weld seam, form the seal weld of continuous uniform, close simultaneously and merge the bad leakage point stayed of seal welding welding.
Merge the fusing point of fusing point lower than splash guard material of seal weld tape splicing, when ensureing weld heating, merge seal weld tape splicing and fully melt, usually, the fusing point 50-100 DEG C lower than the fusing point of splash guard material of described fusion seal welding carrying material.
Bottom line realizes technical purpose of the present utility model only to be needed: described fusion seal weld tape splicing is arranged on the interannular overlap of splash guard body side, described fusion seal weld tape splicing is arranged on the one side of splash guard body, namely splash guard is only provided with a fusion seal weld tape splicing.
If be welded with twice weld seam between splash guard, described fusion seal weld tape splicing is between twice weld seam, and this is the scheme optimized.Optimized scheme merges seal weld tape splicing to be in the middle of twice weld seam.
Described fusion seal weld tape splicing is greater than weld width apart from the distance at splash guard edge, and the object of this scheme avoids weld seam to exceed interannular overlap.
Described fusion seal weld tape splicing is made up of some tapes, some refers to one or more herein.Preferred fusion seal weld tape splicing is made up of a tape, and general interannular overlap width is 15 centimetres, and this tape is in the middle of interannular overlap, and the width of tape is 15-20mm, and thickness is 0.3-0.6mm, and during welding, weld seam is positioned at the both sides of this tape.
In order to form air pressure method sense channel, in described fusion seal weld tape splicing, arrange isolating bar, the fusing point of described isolating bar material is higher than the fusing point of splash guard material.The heating-up temperature of bonding machine is lower than the fusing point merging seal weld tape splicing, and when the heating arrangements of bonding machine heats fusion seal welding region, isolating bar maintains the original state, around isolating bar, form gap, this gap and air pressure method sense channel.The material of isolating bar can be poromeric material, may be used for like this making up forming the problems such as little or local, gap is not clear and coherent around above-mentioned isolating bar, guarantees that the entirety of air pressure method sense channel is unimpeded.
Welding method between above-mentioned anchor bar of waterproof plate in tunnels, comprises the steps:
(1) splash guard is installed, the interannular overlap of adjacent two width splash guards is superimposed;
(2) adopt bonding machine to carry out sweat soldering, bonding machine carries out sweat soldering along distribution arrangement splash guard merging seal weld tape splicing, and the weld seam of welding is positioned at the both sides of merging seal weld tape splicing;
(3) bonding machine is to while splash guard sweat soldering or after sweat soldering, and the heating arrangements of bonding machine heats fusion seal welding band, makes fusion seal weld tape splicing melt to liquid-plastic state on splash guard;
(4) welded seam area of the roller extruding splash guard of bonding machine forms weld seam;
(5) the fusion seal welding region of the roller extruding liquid-plastic state of bonding machine, make it diffuse to bonding welded seam area, butt welded seam carries out mending-leakage reinforcement, forms the seal weld of continuous uniform at former fusion seal weld tape splicing place; When merge in seal weld tape splicing be provided with the isolating bar of fusing point higher than splash guard material melting point time, the heating-up temperature of bonding machine is lower than the fusing point merging seal weld tape splicing, when the heating arrangements of bonding machine heats fusion seal welding region, isolating bar maintains the original state, and forms gap around isolating bar.
In addition, described splash guard merges seal welding carrying material and different colours is arranged to by splash guard material, when fusion seal welding band on splash guard is heated, merge seal weld tape splicing and melt to liquid-plastic state on splash guard, the fusion seal weld tape splicing of extruding liquid-plastic state, it is made to diffuse to welded seam area, if weld seam is leaky, then the fusion seal welding carrying material of different colours liquid-plastic state diffuses in weld seam leak, after cooling, to leak reinforcement while on weld seam, the fusion seal welding carrying material of different colours shows leak position.
Anchor bar of waterproof plate in tunnels welding sweating welder, comprise the first squeezing roller and heating arrangements that extruding forms weld seam, characterized by further comprising the second squeezing roller for merging seal weld tape splicing, described second squeezing roller and the first squeezing roller arranged side by side, or second after squeezing roller is positioned at the first squeezing roller, the air outlet of described heating arrangements is covered to and merges seal welding region.
The utility model is according to constructing tunnel produced problem such as railways, JP sends out the utility model splash guard and correlation technique thereof, make up and climb the defect of welding technology in constructing tunnel, eliminate the defect of mainly leaking of tunnel waterproofing layer construction, improve waterproof construction technology and equipment, improve waterproof construction quality.
The advantage of the utility model splash guard and welding method:
1, climb in weldering process at anchor bar of waterproof plate in tunnels, form the seal weld that strengthening melting together connects, fundamentally realize the welded seal of two width splash guards, ensure welding quality; Meanwhile, merge band and realize secondary and make up, effective reinforcement being carried out to normal twice weld seam and supplements sealing, thus improve the reliability of the welding water blockoff of weld seam, also omit the step as adopted air pressure to stop leakage in the roof.
2, not changing the main technique technology of current anchor bar of waterproof plate in tunnels welding, only carrying out local improvement to climbing welding machine extrusion structure, be adapted at the constructing tunnel technology field that application is wider at present.
3, do not change material, the manufacturing process equipment of current splash guard, save existing social resources.
4, can apply in the welding in the various superimposed district of splash guard hoop, applicability is strong.
5, excellent to the security function of anchor bar of waterproof plate in tunnels hoop superimposed district's sweat soldering airtight quality, to guarantee workmanship, extend engineering application life, economic worth and social effect are all more great.
Accompanying drawing explanation
Below in conjunction with the drawings and specific embodiments, the utility model is described in further detail.
Fig. 1 is the utility model splash guard schematic diagram.
Fig. 2 is that the utility model splash guard is at welding schematic diagram.
Fig. 3 is that the utility model splash guard is at welding sectional view.
Fig. 4 arranges isolating bar schematic diagram for merging in seal weld tape splicing.
Fig. 5 welds the position view of rear isolating bar.
Fig. 6 is the squeezing roller position view of sweating welder.
Detailed description of the invention
(1) install anchor bar of waterproof plate in tunnels, as shown in Figure 1, its both sides are defined as interannular overlap 2 according to function to anchor bar of waterproof plate in tunnels, and the interannular overlap 2 of adjacent two width splash guards 1 is superimposed together.At the interannular overlap 2 of splash guard 1, the front of splash guard 1 and/or reverse side are provided with and merge seal weld tape splicing 3, namely merge seal weld tape splicing 3 and can be arranged on either side interannular overlap 2, or be arranged on both sides interannular overlap 2 simultaneously, merge any surface (i.e. front or reverse side) that seal weld tape splicing 3 can be arranged on interannular overlap 2, or be arranged on the positive and negative of interannular overlap 2 simultaneously.
Merge seal weld tape splicing 3 and select the redness obstructed with splash guard 1 color, the distribution arrangement merging seal weld tape splicing 3 is identical with weld seam 4 (as shown in Figure 2) direction of interannular overlap 2, and merging seal weld tape splicing 3 can be made up of one or more tape.Merging seal weld tape splicing 3 with the mother metal of splash guard 1 can be the materials such as PE, EVA or PE+EVA, but merges the fusing point of fusing point lower than splash guard 1 material of seal weld tape splicing 3 material, as selected the low 50-100 DEG C of fusing point.
As shown in Figure 4, isolating bar 5 is provided with in fusion seal weld tape splicing 3, the fusing point of described isolating bar 5 material is higher than the fusing point of splash guard 1 material, bonding machine welding temperature is selected to be greater than splash guard 1 body melting temperature and is less than isolating bar 6 material melting point temperature when heating splash guard 1 body, isolating bar 5 can not change, here change refers to can not melting, even melts to liquid-plastic state.When the heating arrangements of bonding machine heats fusion seal weld tape splicing 3 region, isolating bar 5 maintains the original state, and around isolating bar 5, form gap, this gap is as air pressure method sense channel.
Isolating bar 5 can select the high temperature resistant poromeric materials such as high temperature film band, glass fabric, and here high temperature resistant does not limit higher temperature, and the fusing point of high temperature resistant poromeric material here is only greater than splash guard 1 body melting temperature.Certainly, the material of isolating bar 5 can not be poromeric material, selects poromeric material to may be used for making up above-mentioned isolating bar 5 surrounding and forms the problems such as little or local, gap is not clear and coherent, guarantee that the entirety of air pressure method sense channel is unimpeded.
The present embodiment, the interannular overlap 2 of splash guard 1 selects 150mm, and merging seal weld tape splicing 3 is an overall tape 5, and it is positioned at interannular overlap 2 center, and wide 3 degree of tape is 30mm, and thickness is 0.3mm.Isolating bar 5 width is 10mm, and thickness is 0.2mm, and it is arranged on and merges middle part in seal weld tape splicing 3, is positioned on splash guard 1, the fusion seal weld tape splicing 3 that isolating bar 5 top also has 0.1mm thick bottom isolating bar.
The position of merging seal weld tape splicing 3 does not limit the center being positioned at interannular overlap 2, can be amesiality, when amesiality, under double slit climbs weldering situation, needs the position stopping weld seam 4 at interannular overlap 2.
(2) adopt automatic crawling bonding machine to carry out double slit and climb weldering, automatic crawling bonding machine carries out sweat soldering along distribution arrangement splash guard 1 merging seal weld tape splicing, as shown in Figure 2,3, the twice weld seam 4 of welding is positioned at and merges seal weld tape splicing 3 both sides, twice weld seam 4 is close to the wide tape of 30mm, and per pass weld seam 4 width is 20mm.
The automatic crawling bonding machine adopted needs to improve, main improvement is in heating arrangements and squeezing roller part, former automatic crawling bonding machine comprises the first squeezing roller 6 and heating arrangements that extruding forms weld seam, as shown in Figure 6, bonding machine after improvement also comprises the second squeezing roller 7 for merging seal weld tape splicing, described second squeezing roller 7 and the first squeezing roller 6 arranged side by side, or after the second squeezing roller 7 is positioned at the first squeezing roller 6 as shown in Figure 5, and the air outlet of heating arrangements is improved, the air outlet of heating arrangements is covered to and merges seal weld tape splicing 3 region, thus can fusion seal weld tape splicing 3 region between twice weld seam be heated.
(3) bonding machine is to while splash guard 1 sweat soldering or after sweat soldering, and the heating arrangements of bonding machine 1 heats fusion seal weld tape splicing 3, makes fusion seal weld tape splicing 3 melt to liquid-plastic state on splash guard 1.
The present embodiment is selected while sweat soldering, and the heating arrangements of bonding machine heats fusion seal weld tape splicing 3, like this, when adding thermal weld to splash guard 1 interannular overlap 2, merge seal weld tape splicing 3 because fusing point is lower than the fusing point of mother metal, can liquid-plastic state be melted to
(4) welded seam area of roller (i.e. the first squeezing roller 6 in Fig. 6) the extruding splash guard 1 of bonding machine forms weld seam 4.
(5) fusion seal weld tape splicing 3 region of the roller extruding liquid-plastic state of bonding machine, it is made to diffuse to bonding weld seam 4 region, butt welded seam 4 carries out mending-leakage reinforcement, form the seal weld of continuous uniform at former fusion seal weld tape splicing 3 place while, the leakage point that closed failure welding stays, as shown in Figure 3.
If weld seam 4 is leaky, then fusion seal weld tape splicing 3 material of red liquid-plastic state diffuses in weld seam leak, after cooling, weld seam will occur the leak position of red fusion seal weld tape splicing 3 material display, and now red fusion seal weld tape splicing 3 material carries out reinforcement to leak.If weld seam 4 does not have leak, red fusion seal weld tape splicing 3 material of liquid-plastic state forms the seal weld of continuous uniform between twice weld seam 4.
When the heating arrangements of bonding machine heats fusion seal weld tape splicing 3 region, isolating bar maintains the original state, and as shown in Figure 5, forms gap around isolating bar, forms air pressure method sense channel, is convenient to later stage butt welded seam and detects.
Above-described embodiment limits the utility model never in any form, and the technical scheme that the mode that every employing is equal to replacement or equivalent transformation obtains all drops in protection domain of the present utility model.

Claims (8)

1. an anchor bar of waterproof plate in tunnels, its both sides are interannular overlap, adjacent two width splash guards are by being welded together at interannular overlap, it is characterized in that: at the interannular overlap of splash guard, the front of splash guard and/or reverse side are provided with and merge seal weld tape splicing, the distribution arrangement of described fusion seal weld tape splicing is identical with the bead direction of interannular overlap, and the fusing point of described fusion seal welding carrying material is lower than the fusing point of splash guard material.
2. anchor bar of waterproof plate in tunnels according to claim 1, is characterized in that: described fusion seal weld tape splicing is arranged on the interannular overlap of splash guard body side.
3. anchor bar of waterproof plate in tunnels according to claim 2, is characterized in that: described fusion seal weld tape splicing is arranged on the one side of splash guard body.
4. the anchor bar of waterproof plate in tunnels according to claim 1,2 or 3, is characterized in that: described fusion seal weld tape splicing is made up of some tapes.
5. anchor bar of waterproof plate in tunnels according to claim 4, is characterized in that: described fusion seal weld tape splicing is made up of a tape.
6. anchor bar of waterproof plate in tunnels according to claim 1, is characterized in that: be provided with isolating bar in described fusion seal weld tape splicing, and the fusing point of described isolating bar material is higher than the fusing point of splash guard material.
7. anchor bar of waterproof plate in tunnels according to claim 6, is characterized in that: described isolating bar material is poromeric material.
8. an anchor bar of waterproof plate in tunnels welding sweating welder, comprise the first squeezing roller and heating arrangements that extruding forms weld seam, characterized by further comprising the second squeezing roller for merging seal weld tape splicing, described second squeezing roller and the first squeezing roller arranged side by side, or second after squeezing roller is positioned at the first squeezing roller, the air outlet of described heating arrangements is covered to and merges seal welding region.
CN201420613545.5U 2014-10-22 2014-10-22 A kind of anchor bar of waterproof plate in tunnels and sweating welder thereof Expired - Fee Related CN204283450U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420613545.5U CN204283450U (en) 2014-10-22 2014-10-22 A kind of anchor bar of waterproof plate in tunnels and sweating welder thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420613545.5U CN204283450U (en) 2014-10-22 2014-10-22 A kind of anchor bar of waterproof plate in tunnels and sweating welder thereof

Publications (1)

Publication Number Publication Date
CN204283450U true CN204283450U (en) 2015-04-22

Family

ID=52866623

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420613545.5U Expired - Fee Related CN204283450U (en) 2014-10-22 2014-10-22 A kind of anchor bar of waterproof plate in tunnels and sweating welder thereof

Country Status (1)

Country Link
CN (1) CN204283450U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104476765A (en) * 2014-10-22 2015-04-01 邓卫东 A tunnel waterproof board, a waterproof board welding method and a hot-melt welding machine
CN113123372A (en) * 2021-04-09 2021-07-16 中船第九设计研究院工程有限公司 Vertical HDPE film construction method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104476765A (en) * 2014-10-22 2015-04-01 邓卫东 A tunnel waterproof board, a waterproof board welding method and a hot-melt welding machine
CN113123372A (en) * 2021-04-09 2021-07-16 中船第九设计研究院工程有限公司 Vertical HDPE film construction method

Similar Documents

Publication Publication Date Title
CN104476765B (en) A tunnel waterproof board, a waterproof board welding method and a hot-melt welding machine
CN105195860B (en) Welding method is tiltedly found in back docking
CN204283450U (en) A kind of anchor bar of waterproof plate in tunnels and sweating welder thereof
CN111516268A (en) Welding and detection process for HDPE (high-density polyethylene) geomembrane of refuse landfill
CN108581257A (en) A kind of ship fore body narrow zone welding method
CN107262889A (en) A kind of band steel welding method
IT8948539A1 (en) ADHESIVE SHEET WITH INCORPORATED METALLIC RETICLE FOR WELDED AND GLUED COMBINED JOINTS.
ATE279318T1 (en) LAYER COMPOSITE WITH WELDED METAL INSERT
CN104607783A (en) Welding Device for Welding a Connecting Portion and Method for Welding the Connecting Portion with the Welding Assembly
CN101148314A (en) Seal method for vacuum glass periphery and edge sealing strip
CN108856971A (en) Penstock combines steel sleeve single side butt weld technologies for steel
CN101585232A (en) Composite welding method used for steel belt to reinforce pipe joint of polyethylene drainpipe
CN208281646U (en) A kind of outer protective polyethylene layer polyurethane foam heat-insulation pipe road
CN205420600U (en) Leak protection silicon device of ingot furnace
US2182796A (en) Welding process
CN204739354U (en) No coped joint electrothermal welding area
CN103604026A (en) Novel construction method for heat insulation of heat-insulating pipeline joints
CN204588972U (en) The closure works system of high temperature solution in a kind of kiln material road
JP2007085057A (en) Snow-melting panel
Cui et al. The morphology and mechanical property of hot gas implant welding joint of polypropylene
CN216479380U (en) High-density polyethylene seamless electric hot melting sleeve
CN206157927U (en) Drain bar is prevented to self -adhesion overlap joint formula
CN207394203U (en) High sealing is seamless, and hot melt covers
CN207331778U (en) A kind of novel high-strength waterproof roll
CN110374638A (en) A kind of anchor bar of waterproof plate in tunnels zip mode connection system and its construction method

Legal Events

Date Code Title Description
GR01 Patent grant
C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20160725

Address after: 215500 the Fuchun River Road, Southeast Development Zone, Jiangsu, Changshou City

Patentee after: CHANGSHU JIAFA CHEMICAL Co.,Ltd.

Address before: Changshou City Yushan Town Suzhou city Jiangsu province 215500 zhaomwen road Shannon Garden

Patentee before: Deng Weidong

CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150422

Termination date: 20211022

CF01 Termination of patent right due to non-payment of annual fee