CN204240325U - Boiler final reheater outlet transition pipe - Google Patents

Boiler final reheater outlet transition pipe Download PDF

Info

Publication number
CN204240325U
CN204240325U CN201420624782.1U CN201420624782U CN204240325U CN 204240325 U CN204240325 U CN 204240325U CN 201420624782 U CN201420624782 U CN 201420624782U CN 204240325 U CN204240325 U CN 204240325U
Authority
CN
China
Prior art keywords
internal diameter
transition
transition portion
boiler
reheater outlet
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201420624782.1U
Other languages
Chinese (zh)
Inventor
蔡鹏远
刘进峰
王力强
蒙殿武
刘炜
陈捷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
International Lv Si Of Jiangsu Datang Port Power Generation Corp Ltd
Original Assignee
International Lv Si Of Jiangsu Datang Port Power Generation Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by International Lv Si Of Jiangsu Datang Port Power Generation Corp Ltd filed Critical International Lv Si Of Jiangsu Datang Port Power Generation Corp Ltd
Priority to CN201420624782.1U priority Critical patent/CN204240325U/en
Application granted granted Critical
Publication of CN204240325U publication Critical patent/CN204240325U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Rigid Pipes And Flexible Pipes (AREA)

Abstract

The utility model discloses a kind of boiler final reheater outlet transition pipe, and this transition conduit comprises body, is provided with the pipeline of this body through in body; Body comprises along its pipeline axial and connects successively and the Part I be interconnected, transition portion and Part II; The internal diameter of Part I is greater than the internal diameter of Part II; Transition portion is equal with the internal diameter of Part I with one end internal diameter that Part I connects, the internal diameter of transition portion is reduced to the one end connecting Part II gradually by the one end connecting Part I, and transition portion is equal with the internal diameter of Part II with one end internal diameter that Part II connects.The utility model lengthens the length of transition conduit transition portion, reduce the excessive angle of transition portion, improve cutter groove, wedge angle, round-corner transition radius, increase the fineness of transition conduit inwall simultaneously, thus the boiler leakage blowing out accident avoided transition conduit that fracture occurs and cause, ensure the normal work of boiler.

Description

Boiler final reheater outlet transition pipe
Technical field
The utility model relates to a kind of boiler pipe part, is specifically related to a kind of boiler final reheater outlet transition pipe.
Background technology
At present, the situations such as the final reheater outlet transition pipe of apparatus of thermo-electric power boiler exists cutter groove, wedge angle, round-corner transition radius is inadequate, fineness inadequate, wall unevenness.Cause stove final reheater outlet transition short tube easily to rupture, cause boiler leakage blowing out accident.
Utility model content
The utility model provides a kind of boiler final reheater outlet transition pipe, improves transition portion length, reduces excessive angle, avoid transition conduit to rupture.
For achieving the above object, the utility model provides a kind of boiler final reheater outlet transition pipe, and this transition conduit comprises body, is provided with the pipeline of this body through in body; Be characterized in,
Above-mentioned tubular body comprises along its pipeline axial and connects successively and the Part I be interconnected, transition portion and Part II;
The internal diameter of above-mentioned Part I is greater than the internal diameter of Part II;
Above-mentioned transition portion is equal with the internal diameter of Part I with one end internal diameter that Part I connects, the internal diameter of transition portion is reduced to the one end connecting Part II gradually by the one end connecting Part I, and transition portion is equal with the internal diameter of Part II with one end internal diameter that Part II connects.
The internal diameter of above-mentioned transition portion is reduced with linear relationship to the one end connecting Part II by the one end connecting Part I.
Corner dimension between the madial wall of above-mentioned transition portion and the madial wall of Part I is 166 degree.
Above-mentioned transition portion is set to 820 millimeters along the length of its axis.
The external diameter size of the Part I of above-mentioned tubular body, transition portion and Part II is constant along pipeline axial.
The outer end of above-mentioned Part II and the junction of Part II lateral wall are provided with inclined-plane.
Above-mentioned Part II length is vertically greater than Part I length vertically.
The utility model boiler final reheater outlet transition pipe is compared with the transition conduit of prior art, its advantage is, the utility model lengthens the length of transition conduit transition portion, reduce the excessive angle of transition portion, improve cutter groove, wedge angle, round-corner transition radius, increase the fineness of transition conduit inwall simultaneously, thus the boiler leakage blowing out accident avoided transition conduit that fracture occurs and cause, ensure the normal work of boiler.
Accompanying drawing explanation
Fig. 1 is the structural representation of the utility model boiler final reheater outlet transition pipe.
Detailed description of the invention
Below in conjunction with accompanying drawing, further illustrate specific embodiment of the utility model.
As shown in Figure 1, disclose a kind of embodiment of boiler final reheater outlet transition pipe, this transition conduit includes the columniform body that external diameter is 60 millimeters, the pipeline of this body through is provided with in body, inner-walls of duct fineness can be arranged by technological requirement, in routine use, inner-walls of duct fineness can the technological ability of prior art be set to the highest.
Body comprises along its pipeline axial and connects successively and the Part I 1 be interconnected, transition portion 3 and Part II 2.
The external diameter size of the Part I of body, transition portion and Part II is constant along pipeline axial.
Part II length is vertically greater than Part I and transition portion length vertically.Wherein transition portion is set to 820 millimeters along the length of its axis.
Wherein, the internal diameter of Part I 1 is greater than the internal diameter of Part II 2, and wherein the internal diameter of Part II 2 is evenly set to 31 millimeters, and the internal diameter of Part I 1 is evenly set to 52.2 millimeters.One end that transition portion 3 is connected with Part I 1, its internal diameter is equal with the internal diameter of Part I 1.And one end that transition portion 3 is connected with Part II 2, its internal diameter is equal with the internal diameter of Part II 2.The internal diameter of this transition portion 3 is reduced to the one end connecting Part II 2 gradually by the one end connecting Part I 1, the changeover portion that before forming Part I 1 and Part II 2, internal diameter changes.
Preferably, the internal diameter of transition portion 3 is reduced with linear relationship, to ensure transition portion 3 inwall fineness to the one end connecting Part II 2 by the one end connecting Part I 1.
Further, the madial wall of transition portion 3 and the madial wall of Part I towards Part II 2 extended line between angle be 14 degree, the corner dimension namely between the madial wall of transition portion 3 and the madial wall of Part I 1 is 166 degree.
As shown in Figure 1, along the outer end of Part II and the junction of Part II lateral wall, be also provided with the inclined-plane around Part II end edge, this inclined-plane is used for groove during transition conduit welding.
Although content of the present utility model has done detailed introduction by above preferred embodiment, will be appreciated that above-mentioned description should not be considered to restriction of the present utility model.After those skilled in the art have read foregoing, for multiple amendment of the present utility model and substitute will be all apparent.Therefore, protection domain of the present utility model should be limited to the appended claims.

Claims (7)

1. a boiler final reheater outlet transition pipe, this transition conduit comprises body, is provided with the pipeline of this body through in body; It is characterized in that,
Described body comprises along its pipeline axial and connects successively and the Part I be interconnected, transition portion and Part II;
The internal diameter of described Part I is greater than the internal diameter of Part II;
Described transition portion is equal with the internal diameter of Part I with one end internal diameter that Part I connects, the internal diameter of transition portion is reduced to the one end connecting Part II gradually by the one end connecting Part I, and transition portion is equal with the internal diameter of Part II with one end internal diameter that Part II connects.
2. boiler final reheater outlet transition pipe as claimed in claim 1, is characterized in that, the internal diameter of described transition portion is reduced with linear relationship to the one end connecting Part II by the one end connecting Part I.
3. boiler final reheater outlet transition pipe as claimed in claim 1 or 2, it is characterized in that, the corner dimension between the madial wall of described transition portion and the madial wall of Part I is 166 degree.
4. boiler final reheater outlet transition pipe as claimed in claim 1, it is characterized in that, described transition portion is set to 820 millimeters along the length of its axis.
5. boiler final reheater outlet transition pipe as claimed in claim 1, is characterized in that, the external diameter size of the Part I of described body, transition portion and Part II is constant along pipeline axial.
6. boiler final reheater outlet transition pipe as claimed in claim 1, it is characterized in that, the outer end of described Part II and the junction of Part II lateral wall are provided with inclined-plane.
7. boiler final reheater outlet transition pipe as claimed in claim 1, it is characterized in that, described Part II length is vertically greater than Part I length vertically.
CN201420624782.1U 2014-10-27 2014-10-27 Boiler final reheater outlet transition pipe Expired - Fee Related CN204240325U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420624782.1U CN204240325U (en) 2014-10-27 2014-10-27 Boiler final reheater outlet transition pipe

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420624782.1U CN204240325U (en) 2014-10-27 2014-10-27 Boiler final reheater outlet transition pipe

Publications (1)

Publication Number Publication Date
CN204240325U true CN204240325U (en) 2015-04-01

Family

ID=52769815

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420624782.1U Expired - Fee Related CN204240325U (en) 2014-10-27 2014-10-27 Boiler final reheater outlet transition pipe

Country Status (1)

Country Link
CN (1) CN204240325U (en)

Similar Documents

Publication Publication Date Title
CN205363142U (en) Pipe positioning core axle
CN204240325U (en) Boiler final reheater outlet transition pipe
CN204254022U (en) A kind of valve cutting ferrule linkage structure
CN216768686U (en) Metal corrugated hose end connecting structure capable of avoiding torsion and metal corrugated hose
CN206159700U (en) Hydraulic hose connecting device
CN210266319U (en) Easily-adjusted connecting pipe
CN204083582U (en) Jacket pipe with in press adpting flange
CN203671087U (en) Sampling tube base and sampling assembly
CN103075590B (en) A kind of connecting tube and reducer union device
CN204921030U (en) Plug -hole stopper
CN103411079A (en) Street elbow
CN205618879U (en) Anti -blocking pipe says cross
CN204099772U (en) Be applied to the joiner of valve
CN204879216U (en) Tee bend of elbow type
CN203585669U (en) Internal and external tooth-shaped elbow
CN204127512U (en) Force-feed lubrication system and Welded fitting device thereof
CN204657492U (en) A kind of digital control lathe chuck is top
CN204060883U (en) Engine exhaust helical bellows
CN204365768U (en) The shaping plug of one side's rectangular bend
CN203979696U (en) Pipe joint in a kind of air conditioner condensation water system
CN202561300U (en) Combined overflow pipe
CN102588686A (en) Chucking type pipe joint fitting
CN107763354A (en) A kind of adjustable elbow
CN104235534A (en) Connector applied to valve
CN202803843U (en) Pipe correcting device

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150401

Termination date: 20211027