CN204224077U - A kind of steel construction piece mounting hanger - Google Patents

A kind of steel construction piece mounting hanger Download PDF

Info

Publication number
CN204224077U
CN204224077U CN201420675391.2U CN201420675391U CN204224077U CN 204224077 U CN204224077 U CN 204224077U CN 201420675391 U CN201420675391 U CN 201420675391U CN 204224077 U CN204224077 U CN 204224077U
Authority
CN
China
Prior art keywords
crossbeam
vertical rod
hanger
steel construction
construction piece
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201420675391.2U
Other languages
Chinese (zh)
Inventor
刘建国
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MCC Tiangong Group Corp Ltd
Original Assignee
MCC Tiangong Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MCC Tiangong Group Corp Ltd filed Critical MCC Tiangong Group Corp Ltd
Priority to CN201420675391.2U priority Critical patent/CN204224077U/en
Application granted granted Critical
Publication of CN204224077U publication Critical patent/CN204224077U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Load-Engaging Elements For Cranes (AREA)

Abstract

The utility model provides a kind of steel construction piece mounting hanger, comprises the hole for hoist arranged on the upside of crossbeam and crossbeam two ends; A vertical rod is respectively established on the downside of described crossbeam two ends; Each described vertical rod is provided with several vertical rod hangers of differing heights; Each described vertical rod hanger is all provided with snap ring, described snap ring is all provided with lifting rope.Wherein, each described vertical rod upper end by hinge on crossbeam.The utility model can realize less steel construction piece and install upper air installing operation function, and safety of operation is reliable.Can realize " a hook more than one piece " simultaneously, substantially increase installation effectiveness, accelerate installation rate, improve work efficiency.In addition, manufacture craft is simple, and draw materials extensively, productive costs is lower.

Description

A kind of steel construction piece mounting hanger
Technical field
The utility model belongs to construction steel structure installation Technology field, especially relates to a kind of steel construction piece mounting hanger.
Background technology
Current construction steel structure installation field at home, more small-sized lightweight construction part high altitude mounting method for enormous amount is all adopt " one, a hook ", the problem that its efficiency is low, cost is high is obvious, only have the special hanger of employing " a hook more than one piece ", just greatly can improve lifting efficiency and reduce mechanical one-shift cost.
Utility model content
Problem to be solved in the utility model is to provide a kind of steel construction piece mounting hanger, and structure is simple, and design science is reasonable, and productive costs is lower, easy to use, can effective guarantee fast, stable, safety carries out the installation of small members high-altitude.
For solving the problems of the technologies described above, the technical solution adopted in the utility model is: a kind of steel construction piece mounting hanger, comprises the hole for hoist arranged on the upside of crossbeam and crossbeam two ends; A vertical rod is respectively established on the downside of described crossbeam two ends; Each described vertical rod is provided with several vertical rod hangers of differing heights; Each described vertical rod hanger is all provided with snap ring, described snap ring is all provided with lifting rope.
Further, each described vertical rod upper end all by hinge on crossbeam.
Further, the vertical rod that described crossbeam two ends are arranged is arranged relative to the Central Symmetry of crossbeam.
Further, the downside at described crossbeam two ends is provided with hanger under crossbeam, and described vertical rod to be all hinged under crossbeam on hanger.
Further, under described crossbeam, hanger is welded on crossbeam.
Further, be respectively equipped with hanger on crossbeam on the upside of described crossbeam two ends, described hole for hoist to be arranged on crossbeam on hanger.
Further, on described crossbeam, hanger is welded on crossbeam.
Further, the hole for hoist at described crossbeam two ends is arranged relative to the Central Symmetry of crossbeam.
Further, each described lifting rope is equipped with sling.
The advantage that the utility model has and good effect are:
1) realize less steel construction piece and install upper air installing operation function, safety of operation is reliable.
2) achieve " a hook more than one piece ", substantially increase installation effectiveness, accelerate installation rate, improve work efficiency.
3) manufacture craft is simple, and draw materials extensively, productive costs is lower.
Accompanying drawing explanation
Fig. 1 is structural representation of the present utility model;
Schematic diagram when Fig. 2 is the utility model use.
In figure: 1-crossbeam; 2-vertical rod; 3-bearing pin; 4-vertical rod hanger; 5-snap ring; 6-lifting rope; Hanger on 7-crossbeam; Hanger under 8-crossbeam; 9-sling; 10-hole for hoist.
Detailed description of the invention
Below in conjunction with accompanying drawing, specific embodiment of the utility model is elaborated.
A kind of steel construction piece mounting hanger, as shown in Figure 1, comprises the hole for hoist 10 arranged on the upside of crossbeam 1 and crossbeam 1 two ends; A vertical rod 2 is respectively established on the downside of described crossbeam 1 two ends; Each described vertical rod 2 is provided with several vertical rod hangers 4 of differing heights; Each described vertical rod hanger 4 is all provided with snap ring 5, described snap ring 5 is all provided with lifting rope 6.
Wherein, each described vertical rod 2 upper end is all hinged on crossbeam 1 by bearing pin 3, stabilized structure, and vertical rod 2 and crossbeam 1 can relatively rotate, like this, flexibly more convenient when steel construction piece is installed, and not by the restriction of structure, is easy to install.
Wherein, the vertical rod 2 that described crossbeam 1 two ends are arranged is arranged relative to the Central Symmetry of crossbeam 1, and whole machine balancing is good, it should be noted that, on the ground during binding structure part, also make the framing member weight equity in two vertical rods 2 as far as possible, in order to avoid run-off the straight after lifting, be unfavorable for installing.
Wherein, the downside at described crossbeam 1 two ends is provided with hanger 8 under crossbeam, and described vertical rod 2 is all hinged under crossbeam on hanger 8, and under described crossbeam, hanger 8 is welded on the upside of crossbeam 1 two ends.
Wherein, be respectively equipped with hanger 7 on crossbeam on the upside of described crossbeam 1 two ends, described hole for hoist 10 is arranged on crossbeam on hanger 7, and on described crossbeam, hanger 7 is welded on the downside of crossbeam 1 two ends.
Wherein, the hole for hoist 10 at described crossbeam 1 two ends is arranged relative to crossbeam 1 Central Symmetry, and stabilized structure, whole machine balancing is good, is easy to lifting operation.
Crossbeam 1 adopts square steel tube or round steel pipe to make, and on crossbeam, under hanger 7 and crossbeam, hanger 8 is all welded on crossbeam 1, is easier to processing, structural strength complete guaranteed while, also save tooling cost.
Wherein, each described lifting rope 6 is equipped with sling 9.It should be noted that, lifting rope 6 one end Joining clasp 5, the other end arranges sling 9, and the colligation of framing member of being more convenient for like this, efficiency is high.Snap ring 5 hook steel construction piece, lifting rope 6 plays colligation fixation, and steel construction piece colligation is firm, solid firm, and lifting safety, each trade union college is convenient.
It should be noted that, crossbeam 1 and vertical rod 2 all adopt steel pipe material to be processed into, and bearing pin 3 adopts No. 45 steel to be processed into, and on crossbeam, under hanger 7, crossbeam, hanger 8 and vertical rod hanger 4 all adopt steel plate material to be processed into.Draw materials extensively, productive costs is lower.
Separately it should be noted that, be the clear of structure representation in accompanying drawing 1 and accompanying drawing 2, concealed the lifting rope 6 on part snap ring 5.
The length size of each lifting rope 6 can be different, and its phase difference is by the n multiple of lifting components cross dimensions height, is easier to each framing member of slinging, and can not interferes between each framing member.
During use, as shown in Figure 2, first use rope (as suspender belt, steel rope etc.) through hanger on crossbeam 7, to sling this suspender with hanging device (as overhead traveling crane, hoisting crane etc.), vertical rod 2 is hung down.
Then, multiple small members is hooked on different snap rings 5 by operating personal on the ground respectively, and live with lifting rope 6 colligation that each snap ring 5 is arranged, after confirming each steel construction piece colligation firmly, with hanging device, this suspender is sling, like this, just achieve " a hook more than one piece ", substantially increase installation effectiveness, accelerate installation rate, improve work efficiency.
Above an embodiment of the present utility model has been described in detail, but described content being only preferred embodiment of the present utility model, can not being considered to for limiting practical range of the present utility model.All equalizations done according to the utility model application range change and improve, and all should still belong within patent covering scope of the present utility model.

Claims (9)

1. a steel construction piece mounting hanger, is characterized in that: comprise the hole for hoist arranged on the upside of crossbeam and crossbeam two ends; A vertical rod is respectively established on the downside of described crossbeam two ends; Each described vertical rod is provided with several vertical rod hangers of differing heights; Each described vertical rod hanger is all provided with snap ring, described snap ring is all provided with lifting rope.
2. a kind of steel construction piece mounting hanger according to claim 1, is characterized in that: each described vertical rod upper end all by hinge on crossbeam.
3. a kind of steel construction piece mounting hanger according to claim 1 and 2, is characterized in that: the vertical rod that described crossbeam two ends are arranged is arranged relative to the Central Symmetry of crossbeam.
4. a kind of steel construction piece mounting hanger according to claim 1, is characterized in that: the downside at described crossbeam two ends is provided with hanger under crossbeam, and described vertical rod to be all hinged under crossbeam on hanger.
5. a kind of steel construction piece mounting hanger according to claim 4, is characterized in that: under described crossbeam, hanger is welded on crossbeam.
6. a kind of steel construction piece mounting hanger according to claim 1, is characterized in that: be respectively equipped with hanger on crossbeam on the upside of described crossbeam two ends, and described hole for hoist to be arranged on crossbeam on hanger.
7. a kind of steel construction piece mounting hanger according to claim 6, is characterized in that: on described crossbeam, hanger is welded on crossbeam.
8. a kind of steel construction piece mounting hanger according to claim 1, is characterized in that: the hole for hoist at described crossbeam two ends is arranged relative to the Central Symmetry of crossbeam.
9. a kind of steel construction piece mounting hanger according to claim 1, is characterized in that: each described lifting rope is equipped with sling.
CN201420675391.2U 2014-11-13 2014-11-13 A kind of steel construction piece mounting hanger Active CN204224077U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420675391.2U CN204224077U (en) 2014-11-13 2014-11-13 A kind of steel construction piece mounting hanger

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420675391.2U CN204224077U (en) 2014-11-13 2014-11-13 A kind of steel construction piece mounting hanger

Publications (1)

Publication Number Publication Date
CN204224077U true CN204224077U (en) 2015-03-25

Family

ID=52922195

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420675391.2U Active CN204224077U (en) 2014-11-13 2014-11-13 A kind of steel construction piece mounting hanger

Country Status (1)

Country Link
CN (1) CN204224077U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109368485A (en) * 2018-11-29 2019-02-22 岑加昌 A kind of environmental project trees balance type lifting device

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109368485A (en) * 2018-11-29 2019-02-22 岑加昌 A kind of environmental project trees balance type lifting device

Similar Documents

Publication Publication Date Title
CN203269335U (en) Clamping structure of adjustable self-locking clamp
CN202296842U (en) Hanger special for universal shaft of vertical rolling mill
CN204823647U (en) Pipe hoist
CN204224077U (en) A kind of steel construction piece mounting hanger
CN202671002U (en) Lifting appliance for oil cylinder of excavator
CN205275004U (en) Automatic balanced type hanging beam
CN201665484U (en) Net rack bulk part suspending device
CN202029999U (en) Helicopter hanger
CN203186981U (en) Suspension device with self-adjustment balancing function
CN203612823U (en) Spherical substance lifting tool
CN204324685U (en) Interim hanger is used in a kind of novel short range lifting
CN204939932U (en) A kind of safety clothes drying rod
CN202936082U (en) Assembly line hanger for spiral spring clutch
CN203319501U (en) Lifting device for charging chinlon slices
CN204079223U (en) A kind of steel pipe lifting tool
CN103640962A (en) Spherical object lifting tool
CN202754702U (en) Motor lifting device
CN204784442U (en) Hoist cable go -between
CN203295055U (en) Guide wheel structure
CN203998712U (en) A kind of annealing furnace roller way conveying roller mounting hanger
CN203439907U (en) Hook
CN203392717U (en) Special lifting appliance for universal shaft of vertical mill
CN205419498U (en) Circular tubulose section bar hoist
CN209259489U (en) Wind-driven generator brake processing transport hook
CN201703967U (en) Adjustable suspending support frame

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant