CN204212190U - building pile load detection device - Google Patents

building pile load detection device Download PDF

Info

Publication number
CN204212190U
CN204212190U CN201420699424.7U CN201420699424U CN204212190U CN 204212190 U CN204212190 U CN 204212190U CN 201420699424 U CN201420699424 U CN 201420699424U CN 204212190 U CN204212190 U CN 204212190U
Authority
CN
China
Prior art keywords
base
vertical beam
crossbeam
wire rope
hook
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201420699424.7U
Other languages
Chinese (zh)
Inventor
魏瑞琼
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201420699424.7U priority Critical patent/CN204212190U/en
Application granted granted Critical
Publication of CN204212190U publication Critical patent/CN204212190U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The open a kind of building pile load detection device of the utility model, comprise crossbeam and this crossbeam two ends vertical beam for supporting of a level, the bottom of described vertical beam is provided with movable pulley, the below of vertical beam is provided with base, this base is provided with the wheel chamber embedding coupling for described movable pulley, base lower surface is the base plate with bolt hole, described crossbeam is provided with a wire rope, this crossbeam is provided with multiple fixing hole, wire rope runs through above-mentioned fixing hole successively, the two ends of this wire rope are provided with fixed hook, wire rope between adjacent two fixing holes is provided with Removable hook, described vertical beam with base is provided with the link mated with above-mentioned fixed hook and Removable hook.By movable pulley this checkout gear mobile easily, without the need to using large-scale lifting machine to lift, time saving and energy saving; And can be fixed on vertical beam, base or ground by the hook of wire rope, increase the stability maintenance of crossbeam further, larger reaction force is provided, improve the structural strength of key position.

Description

Building pile load detection device
Technical field
The utility model belongs to constructional engineering machinery field, is specifically related to a kind of building pile load detection device.
Background technology
In building construction process, in order to ensure the quality of building, load-carrying ability detection must be carried out to building stake, common detection method is above stake, fix a crossbeam, jack is set between crossbeam and stake, applies pressure with jack to stake, and detect its pressure-bearing situation.The crossbeam of this detection of pier foundation is all huge i iron usually, bulky, from great, be not easy to transport, need during use to utilize large-scale lifting machine to be lifted to precalculated position, waste time and energy.
Summary of the invention
Technical problem to be solved in the utility model is for above-mentioned the deficiencies in the prior art, and provide a kind of building pile load detection device, it is convenient transport and use not only, and also can provide larger load, structure is more stable simultaneously.
The technical scheme that the utility model adopts is: a kind of building pile load detection device, comprise crossbeam and this crossbeam two ends vertical beam for supporting of a level, the bottom of described vertical beam is provided with movable pulley, the below of described vertical beam is provided with the base removably connected with it, this base is provided with the wheel chamber embedding coupling for described movable pulley, described base lower surface is the base plate with bolt hole, described crossbeam is provided with a wire rope, this crossbeam is provided with multiple fixing hole along its length, described wire rope runs through above-mentioned fixing hole successively, the two ends of this wire rope are provided with fixed hook, wire rope between adjacent two fixing holes is provided with Removable hook, described vertical beam with base is provided with the link mated with above-mentioned fixed hook and Removable hook.
As preferably, described vertical beam is connected with described bolt of lower base.
As preferably, the length of described wire rope is greater than three times of described crossbeam length.
As preferably, described vertical beam is evenly distributed with multiple link along its short transverse.
The beneficial effects of the utility model are: because vertical beam bottom of the present utility model is provided with movable pulley, therefore installing and using by movable pulley this checkout gear mobile easily in process, without the need to using large-scale lifting machine to lift, time saving and energy saving; And wire rope is provided with on crossbeam, and this wire rope runs through the multiple fixing holes on crossbeam successively, can be fixed on vertical beam, base or ground by the fixed hook on wire rope and Removable hook, the stability maintenance of further increase crossbeam, larger reaction force is provided, improves the structural strength of key position.
Accompanying drawing explanation
Fig. 1 is structural representation of the present utility model.
In figure: 1, crossbeam; 2, vertical beam; 3, movable pulley; 4, base; 5, fixing hole; 6, wire rope; 7, fixed hook; 8, link; 9, chamber is taken turns; 10, Removable hook.
Detailed description of the invention
Below in conjunction with the accompanying drawings and the specific embodiments the utility model is described in further detail.
As shown in Figure 1, a kind of building pile load detection device, comprise crossbeam 1 and this crossbeam 1 two ends vertical beam 2 for supporting of a level, the bottom of described vertical beam 2 is provided with movable pulley 3, the below of described vertical beam 2 is provided with the base 4 removably connected with it, vertical beam 2 is connected with described base 4 bolt, certainly it also can be other connected mode, this base 4 is provided with the wheel chamber 9 embedding coupling for described movable pulley 3, described base 4 lower surface is the base plate with bolt hole, described crossbeam 1 is provided with a wire rope 6, the length of wire rope 6 is greater than three times of described crossbeam 1 length, this crossbeam 1 is provided with multiple fixing hole 5 along its length, described wire rope 6 runs through above-mentioned fixing hole 5 successively, the two ends of this wire rope 6 are provided with fixed hook 7, wire rope 6 between adjacent two fixing holes 5 is provided with Removable hook 10, described vertical beam 2 with base 4 is provided with the link 8 mated with above-mentioned fixed hook 7 and Removable hook 10, vertical beam 2 is evenly distributed with multiple link 8 along its short transverse.
Use procedure of the present utility model is as follows: first left and right two base 4 is arranged on correct position near pre-peg by bolt, then after utilizing movable pulley 3 to promote this checkout gear arrival relevant position, for ease of movable pulley 3 being embedded the wheel chamber 9 of base 4, can base 4 be fixed on below ground, position, wheel chamber 9 is not above the ground level movable pulley 3, then gently movable pulley 3 is pushed wheel chamber 9, vertical beam 2 is fixed on base 4, then the fixed hook 7 on wire rope 6 and Removable hook 10 are fixed on vertical beam 2, base 4 or ground.More flexible how just wire rope 6 of the present utility model and Removable hook 10 design for changable moving, make fixed form, can adapt to varying environment.
Because vertical beam 2 bottom of the present utility model is provided with movable pulley 3, therefore installing and using by movable pulley 3 this checkout gear mobile easily in process, without the need to using large-scale lifting machine to lift, time saving and energy saving; And wire rope 6 is provided with on crossbeam 1, and this wire rope 6 runs through the multiple fixing holes 5 on crossbeam 1 successively, can be fixed on vertical beam 2, base 4 or ground by the fixed hook 7 on wire rope 6 and Removable hook 10, the stability maintenance of further increase crossbeam 1, larger reaction force is provided, improves the structural strength of key position.
The above, be only the utility model preferred embodiment, therefore can not limit with this scope that the utility model implements, the equivalence namely done according to the utility model claim and description change with modify, all should still belong in scope that the utility model patent contains.

Claims (4)

1. a building pile load detection device, it is characterized in that: crossbeam (1) and this crossbeam (1) the two ends vertical beam (2) for supporting comprising a level, the bottom of described vertical beam (2) is provided with movable pulley (3), the below of described vertical beam (2) is provided with the base (4) removably connected with it, this base (4) is provided with the wheel chamber (9) embedding coupling for described movable pulley (3), described base (4) lower surface is the base plate with bolt hole, described crossbeam (1) is provided with a wire rope (6), this crossbeam (1) is provided with along its length multiple fixing hole (5), described wire rope (6) runs through above-mentioned fixing hole (5) successively, the two ends of this wire rope (6) are provided with fixed hook (7), wire rope (6) between adjacent two fixing holes (5) is provided with Removable hook (10), described vertical beam (2) with base (4) is provided with the link (8) mated with above-mentioned fixed hook (7) and Removable hook (10).
2. building pile load detection device according to claim 1, is characterized in that: described vertical beam (2) is connected with described base (4) bolt.
3. building pile load detection device according to claim 1, is characterized in that: the length of described wire rope (6) is greater than three times of described crossbeam (1) length.
4. building pile load detection device according to claim 1, is characterized in that: described vertical beam (2) is evenly distributed with multiple link (8) along its short transverse.
CN201420699424.7U 2014-11-20 2014-11-20 building pile load detection device Expired - Fee Related CN204212190U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420699424.7U CN204212190U (en) 2014-11-20 2014-11-20 building pile load detection device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420699424.7U CN204212190U (en) 2014-11-20 2014-11-20 building pile load detection device

Publications (1)

Publication Number Publication Date
CN204212190U true CN204212190U (en) 2015-03-18

Family

ID=52980876

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420699424.7U Expired - Fee Related CN204212190U (en) 2014-11-20 2014-11-20 building pile load detection device

Country Status (1)

Country Link
CN (1) CN204212190U (en)

Similar Documents

Publication Publication Date Title
CN201864516U (en) Lifting appliance special for overhauling isolating switch
CN202299574U (en) Plug-in type communication base station lifting tower
CN204401395U (en) A kind of subgrade case
CN206034479U (en) Tower crane relay handling supporter device
CN204212190U (en) building pile load detection device
CN202754704U (en) Hoisting device for heating surface module of heat recovery boiler
CN202164037U (en) Adjustable plate hook
CN202369321U (en) Vibration isolating support hoist
CN204434174U (en) Self-control electric hoisting device
CN203781713U (en) High slope support material transport device
CN203361662U (en) Large net rack short-distance lifting device
CN202988576U (en) Simple and easy chain hoist lifting support
CN208948679U (en) Assembled hanger
CN204078997U (en) A kind of paper placing machine put paper platform structure
CN203754232U (en) Simple steel rail lifting tool
CN203545446U (en) Tire lifting device
CN202644416U (en) A simple lifting device for dismounting a bailey beam
CN202379616U (en) Movable simple hoisting device
CN206502559U (en) The jack lifting platform of ship's space unit
CN205804429U (en) A kind of building pile load detection device
CN204282920U (en) A kind of communication tower being furnished with spliced pedestal
CN202193551U (en) Wheel type lifting and conveying device for curtain wall plates
CN204456164U (en) A kind of spliced pedestal of communication tower
CN202400545U (en) Quick conveying device for installation of large-scale pipeline on pipe gallery
CN202880727U (en) Lifting device for large lifting platform

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150318

Termination date: 20151120

EXPY Termination of patent right or utility model