CN204193927U - A kind of frame structure of electric arc preparation facilities - Google Patents

A kind of frame structure of electric arc preparation facilities Download PDF

Info

Publication number
CN204193927U
CN204193927U CN201420648397.0U CN201420648397U CN204193927U CN 204193927 U CN204193927 U CN 204193927U CN 201420648397 U CN201420648397 U CN 201420648397U CN 204193927 U CN204193927 U CN 204193927U
Authority
CN
China
Prior art keywords
frame
preparation facilities
outside framework
electric arc
inner frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201420648397.0U
Other languages
Chinese (zh)
Inventor
朱常锋
梁业明
李新德
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
XIAMEN FUNA NEW MATERIAL TECHNOLOGY Co Ltd
Original Assignee
XIAMEN FUNA NEW MATERIAL TECHNOLOGY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by XIAMEN FUNA NEW MATERIAL TECHNOLOGY Co Ltd filed Critical XIAMEN FUNA NEW MATERIAL TECHNOLOGY Co Ltd
Priority to CN201420648397.0U priority Critical patent/CN204193927U/en
Application granted granted Critical
Publication of CN204193927U publication Critical patent/CN204193927U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Furnace Details (AREA)

Abstract

The utility model relates to production equipment, particularly relates to electric arc preparation facilities.The utility model discloses a kind of frame structure of electric arc preparation facilities, comprising: a support frame, is around being connected into encapsulated coil by multiple supporter; Multiple support foundation, is fixedly installed on this support frame lower end respectively; An outside framework, is connected in the upper end of this support frame, thus this outside framework and this support frame form a ducted body frame body; Multiple inner frame, is connected in the side of this outside framework respectively; One vacuum arc furnace ignition gripper shoe, is fixedly installed on the centre position of this front end inner frame, and this vacuum arc furnace ignition gripper shoe is a panel, the support portion offering a fixing hole and have the left and right sides in the middle of this panel; And two arc power fixed parts, be arranged at two side positions of this front end inner frame respectively.The frame structure of the electric arc preparation facilities that the utility model proposes, can make each parts in electric arc preparation facilities be mounted thereon compactly.

Description

A kind of frame structure of electric arc preparation facilities
Technical field
The utility model relates to production equipment, particularly relates to electric arc preparation facilities.
Background technology
Electric arc preparation facilities is a kind of equipment utilizing arc process to prepare material, can be widely used in the materials such as manufacture fullerene, magnesia crystal, CNT.An electric arc preparation facilities generally comprises vacuum arc furnace ignition, arc power, vacuum mechanical pump, electrical control cabinet and the required each pipeline of water, electricity and gas etc., and each parts in existing electric arc preparation facilities (as publication number CN1721588, CN1800008, CN103194263A etc.) arbitrarily put to install to connect or installed by simple pedestal to arrange, this must cause the not easily mobile and transport easily of whole device, simultaneously many unfavorable for also existing when daily production operation, Maintenance and Repair, equipment replacement.
Utility model content
Therefore, the utility model proposes a kind of frame structure of electric arc preparation facilities, each parts in electric arc preparation facilities can be made to be mounted thereon compactly, thus whole device can be moved and transport very expediently.
The utility model adopts following technical scheme to realize:
A frame structure for electric arc preparation facilities, comprising:
One support frame is around being connected into encapsulated coil by multiple supporter;
Multiple support foundation, is fixedly installed on this support frame lower end respectively, is distributed in multiple interval location places of this encapsulated coil;
An outside framework, is connected in the upper end of this support frame, comprise the longeron of multiple upright setting and an end face framework of multiple body of rod formation respectively, thus this outside framework and this support frame forms a ducted body frame body;
Multiple inner frame, be connected in the side of this outside framework respectively, the front end inner frame being provided at this outside framework leading flank respectively, the left end inner frame being located at this outside framework left surface, be located at the right-hand member inner frame of this outside framework right flank and be located at the rear end inner frame of this outside framework trailing flank, wherein each inner frame is at least connected by 2 support rod body to arrange and form;
One vacuum arc furnace ignition gripper shoe, is fixedly installed on the centre position of this front end inner frame, and this vacuum arc furnace ignition gripper shoe is a panel, the support portion offering a fixing hole and have the left and right sides in the middle of this panel;
And two arc power fixed parts, be arranged at two side positions of this front end inner frame respectively.
Wherein, this support foundation is height-adjustable support foundation.
Wherein, this arc power fixed part is be made up of the rust steel bracing plate being arranged at above and below respectively.
Wherein, the side of this outside framework is respectively used to installation and repairing door, and the inside of this outside framework is respectively used to arrange trough.The upper end position of this rear end inner frame is used for installing water route, gas circuit valve concentratedly.The fixing hole of this vacuum arc furnace ignition gripper shoe is for fixedly mounting vacuum arc furnace ignition.This arc power fixed part is used for being fixedly installed arc power.The support portion of these vacuum arc furnace ignition gripper shoe both sides is used for being fixedly installed electrical control cabinet.
The utility model adopts as above technical scheme to realize, and each parts in electric arc preparation facilities can be made to be mounted thereon compactly, thus whole device can be moved and transport very expediently; And utilize limited space that all parts of whole electric arc preparation facilities are assembled into one by this frame structure, there is space layout reasonable, daily production operation, Maintenance and Repair, equipment replacement advantage all very easily.In addition, the water route needed for production, gas circuit arrange that standard operation is convenient, and take into full account the electromagnetic radiation of equipment, rational layout, reduces electromagnetism interference greatly, provides the system rejection to disturbance ability of equipment.
Accompanying drawing explanation
Fig. 1 is the structural representation () of the utility model one embodiment;
Fig. 2 is the structural representation (two) of this embodiment of the utility model.
Detailed description of the invention
Now with detailed description of the invention, the utility model is further illustrated by reference to the accompanying drawings.
Consult shown in Fig. 1 and Fig. 2, as the frame structure of the electric arc preparation facilities of the utility model one embodiment, comprising:
One support frame 20 is around being connected into encapsulated coil (this embodiment for square frame, not as limit) by multiple supporter; This support frame 20 bears the weight of whole appliance arrangement and frame body, and can be risen by whole device bottom skeleton with fork truck.
Multiple support foundation 10, is fixedly installed on this support frame 20 lower end respectively, is distributed in multiple interval location places of this encapsulated coil; Preferably, this support foundation 10 is height-adjustable support foundation, by regulating the level of base for supporting nut thread adjusting apparatus.
An outside framework 30, is connected in the upper end of this support frame 20, comprise the longeron 301 of multiple upright setting and an end face framework 302 of multiple body of rod formation respectively, thus this outside framework 30 forms a ducted body frame body with this support frame 20; This outside framework 30 is main frame part, and electric arc preparation facilities can according to the structure of this outside framework 30, and install in outside framework 30 4 sides and fan access door more, access door can easily be opened from framework or take off, convenient maintenance.In addition, at the internal placement trough of outside framework 30, each pipeline of aqueous vapor electricity arrives each device location in trough, makes internal water pneumoelectric pipeline very neat.
Multiple inner frame 40, be connected in the side of this outside framework 30 respectively, be provided at the front end inner frame 401 of this outside framework 30 leading flank respectively, be located at the left end inner frame 402 of this outside framework 30 left surface, be located at the right-hand member inner frame 403 of this outside framework 30 right flank and be located at the rear end inner frame 404 of this outside framework 30 trailing flank, wherein each inner frame 40 is at least connected by 2 support rod body to arrange and form; The plurality of inner frame 40 provides inner support, as can be used for fixing vacuum arc furnace ignition gripper shoe 50, arc power fixed part 60 etc.; And wherein the upper end position 404A of this rear end inner frame 404 is used for installing water route, gas circuit valve concentratedly, opens the rear access door of this outside framework 30 trailing flank, just can easily operate each water route, gas circuit valve.
One vacuum arc furnace ignition gripper shoe 50, is fixedly installed on the centre position of this front end inner frame 401, and this vacuum arc furnace ignition gripper shoe 50 is a panel, the support portion 502 offering a fixing hole 501 and have the left and right sides in the middle of this panel; This arc power fixed part 60 is for being fixedly installed arc power, and such vacuum arc furnace ignition is arranged on the forward position, center of framework, and vacuum arc furnace door can be opened from the front of framework; The support portion 502 of these vacuum arc furnace ignition gripper shoe 50 both sides is for being fixedly installed electrical control cabinet, and electrical control cabinet has two, is divided into power distribution cabinet and automatic control cabinet, position in the positive Middle face both sides of framework, also convenient operation.
And two arc power fixed parts 60, be arranged at two side positions of this front end inner frame 401 respectively; This arc power fixed part 60 is for being fixedly installed arc power; Wherein preferred, this arc power fixed part 60 is be made up of the rust steel bracing plate being arranged at above and below respectively, thus can effectively prevent the electromagnetic radiation of arc power from penetrating, and avoids having influence on whole change system.
In addition, vacuum mechanical pump can be arranged on framework position rearward, and vacuum mechanical pump is arranged on the base of band steamboat, can easily push and release from rear access door (preferably double door).
Utilize the frame structure of this embodiment each parts in whole electric arc preparation facilities can be mounted thereon compactly, when needing the movement of device with transport, whole device only need be pulled down the fast acting flange joint of two vacuum mechanical pumps and vacuum furnace body, vacuum mechanical pump is released from access door after framework, just can be risen by whole device from base of frame with fork lift truck, the movement of whole device is very convenient with transport.
As can be seen here, the frame structure of electric arc preparation facilities can utilize limited space all devices of whole equipment board to be assembled into one, and space layout is reasonable, and daily production operation, Maintenance and Repair, equipment replacement are all very convenient; Water route needed for production, gas circuit arrange that standard operation is convenient, and take into full account the electromagnetic radiation of equipment, rational layout, reduces electromagnetism interference greatly, provides the antijamming capability of system.
Although specifically show in conjunction with preferred embodiment and describe the utility model; but those skilled in the art should be understood that; not departing from the spirit and scope of the present utility model that appended claims limits; can make a variety of changes the utility model in the form and details, be protection domain of the present utility model.

Claims (8)

1. a frame structure for electric arc preparation facilities, is characterized in that, comprising:
One support frame (20) is around being connected into encapsulated coil by multiple supporter;
Multiple support foundation (10), is fixedly installed on this support frame (20) lower end respectively, is distributed in multiple interval location places of this encapsulated coil;
An outside framework (30), be connected in the upper end of this support frame (20), comprise the longeron (301) of multiple upright setting and an end face framework (302) of multiple body of rod formation respectively, thus this outside framework (30) and this support frame (20) form a ducted body frame body;
Multiple inner frame (40), be connected in the side of this outside framework (30) respectively, the front end inner frame (401) being provided at this outside framework (30) leading flank respectively, the left end inner frame (402) being located at this outside framework (30) left surface, be located at the right-hand member inner frame (403) of this outside framework (30) right flank and be located at the rear end inner frame (404) of this outside framework (30) trailing flank, wherein each inner frame (40) is at least connected by 2 support rod body to arrange and form;
One vacuum arc furnace ignition gripper shoe (50), be fixedly installed on the centre position of this front end inner frame (401), this vacuum arc furnace ignition gripper shoe (50) is a panel, the support portion (502) offering a fixing hole (501) and have the left and right sides in the middle of this panel;
And two arc power fixed parts (60), be arranged at two side positions of this front end inner frame (401) respectively.
2. the frame structure of electric arc preparation facilities according to claim 1, is characterized in that: this support foundation (10) is height-adjustable support foundation.
3. the frame structure of electric arc preparation facilities according to claim 1, is characterized in that: this arc power fixed part (60) is be made up of the rust steel bracing plate being arranged at above and below respectively.
4. the frame structure of the electric arc preparation facilities according to claim 1 or 2 or 3, is characterized in that: the side of this outside framework (30) is respectively used to installation and repairing door, and the inside of this outside framework (30) is respectively used to arrange trough.
5. the frame structure of the electric arc preparation facilities according to claim 1 or 2 or 3, is characterized in that: the upper end position (404A) of this rear end inner frame (404) is for installing water route, gas circuit valve concentratedly.
6. the frame structure of the electric arc preparation facilities according to claim 1 or 2 or 3, is characterized in that: the fixing hole (501) of this vacuum arc furnace ignition gripper shoe (50) is for fixedly mounting vacuum arc furnace ignition.
7. the frame structure of the electric arc preparation facilities according to claim 1 or 2 or 3, is characterized in that: this arc power fixed part (60) is for being fixedly installed arc power.
8. the frame structure of the electric arc preparation facilities according to claim 1 or 2 or 3, is characterized in that: the support portion (502) of these vacuum arc furnace ignition gripper shoe (50) both sides is for being fixedly installed electrical control cabinet.
CN201420648397.0U 2014-11-04 2014-11-04 A kind of frame structure of electric arc preparation facilities Active CN204193927U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420648397.0U CN204193927U (en) 2014-11-04 2014-11-04 A kind of frame structure of electric arc preparation facilities

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420648397.0U CN204193927U (en) 2014-11-04 2014-11-04 A kind of frame structure of electric arc preparation facilities

Publications (1)

Publication Number Publication Date
CN204193927U true CN204193927U (en) 2015-03-11

Family

ID=52651928

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420648397.0U Active CN204193927U (en) 2014-11-04 2014-11-04 A kind of frame structure of electric arc preparation facilities

Country Status (1)

Country Link
CN (1) CN204193927U (en)

Similar Documents

Publication Publication Date Title
CN204193927U (en) A kind of frame structure of electric arc preparation facilities
CN203645927U (en) Novel flexibly-assembled engineering control cabinet
CN202091743U (en) Front maintaining spliced display screen support for panel display device
CN103874366A (en) Electrical cabinet
CN203562334U (en) Multifunctional electric operating mechanism suitable for small space
CN205249656U (en) Embedded components of a whole that can function independently touch -sensitive screen fixing device
CN204517170U (en) Outdoor vacuum switch insulating support
CN206958744U (en) A kind of Liftable type Landscape Lamp
CN205051240U (en) Modular installation aerify cabinet
CN103151714A (en) Power distribution cabinet
CN204577869U (en) Easy installation power distribution cabinet
CN204167691U (en) Cable stable type floatless switch case
CN205388954U (en) Vacuum circuit breaker procedure lock support
CN203871726U (en) Preassembled transformer substation
CN204577874U (en) Exempt from power distribution cabinet is installed
CN202957463U (en) Cable chamber for high-voltage cabinet
CN201918731U (en) Arrangement structure of low-voltage compensation cabinet
CN202340061U (en) Double-door power distributing cabinet
CN202088477U (en) Corona treatment device of plastic board
CN205319543U (en) High bearing capacity's of high protection level switch board cabinet body
CN207045275U (en) A kind of electric appliance mounting support of pure electric automobile
CN204651681U (en) Be convenient to the power distribution cabinet case of inlet wire
CN204014305U (en) Lathe electric cabinet
CN203983746U (en) A kind of DC240V power distribution panel
CN204497592U (en) A kind of cabinet type insulation closed box base

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant