CN204188796U - A kind of single-phase electric energy meter inspection, the integrated termination of voltage-withstand test - Google Patents

A kind of single-phase electric energy meter inspection, the integrated termination of voltage-withstand test Download PDF

Info

Publication number
CN204188796U
CN204188796U CN201420556134.7U CN201420556134U CN204188796U CN 204188796 U CN204188796 U CN 204188796U CN 201420556134 U CN201420556134 U CN 201420556134U CN 204188796 U CN204188796 U CN 204188796U
Authority
CN
China
Prior art keywords
test
energy meter
terminal
electric energy
installation panel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201420556134.7U
Other languages
Chinese (zh)
Inventor
孙艳玲
翟晓卉
何毓函
孙晓斌
金在冬
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Electric Power Research Institute of State Grid Shandong Electric Power Co Ltd
Marketing Service Center of State Grid Shandong Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Electric Power Research Institute of State Grid Shandong Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Electric Power Research Institute of State Grid Shandong Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201420556134.7U priority Critical patent/CN204188796U/en
Application granted granted Critical
Publication of CN204188796U publication Critical patent/CN204188796U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model relates to the inspection of a kind of single-phase electric energy meter, the integrated termination of voltage-withstand test, comprise test installation panel, the compression joint mechanism of the control electric energy meter position that the front of this test installation panel is installed under upper successively, energy meter terminal terminal box, power test Wiring module and voltage-withstand test Wiring module that test installation panel is slidably connected; Described voltage-withstand test Wiring module has test connection terminal and contact point, and contact point protrudes from the front of test installation panel, and in the test installation panel of this module installation above power test Wiring module.Use this device to carry out electric energy detection and voltage detecting, and electric energy detection and voltage detecting are independent of each other in test process.

Description

A kind of single-phase electric energy meter inspection, the integrated termination of voltage-withstand test
Technical field
The utility model relates to field of electrical equipment, specifically, relates to the inspection of a kind of single-phase electric energy meter, the integrated termination of voltage-withstand test.
Background technology
Electric energy error accuracy test and the ac voltage withstanding safety test of electric energy meter are extremely important in electric energy meter calibration work, and the former is related to the accuracy of measuring of electric energy meter, and the latter is related to the safe handling of electric energy meter.
What current domestic voltage-withstand test part and electric energy calibrating part adopted is all relay isolation method, switch as required during test, but because the spacing of the relay break contact of isolation is little, safety creepage distance during voltage-withstand test can not be reached completely, relay is punctured because test voltage is high when carrying out 4kV voltage-withstand test through being everlasting, damage electric energy meter electric energy calibrating part, make testing apparatus cisco unity malfunction, in the urgent need to a kind of withstand voltage with spacer assembly during power test, when ensureing voltage-withstand test, electric energy meter electric energy calibrating part can not be damaged.
Meanwhile, when existing device detects electric energy meter, often because of misoperation or Equipment, the loose contact of stationary installation electric energy meter tie point can be caused, affects re-set target.
Therefore, how to design a kind of withstand voltage with spacer assembly during power test, can not damage electric energy meter electric energy calibrating part when ensureing voltage-withstand test, and can ensure that stationary installation and electric energy meter contact are stablized, be the problem that those skilled in the art's letter need solve.Utility model content
The technical matters that the utility model mainly solves is when testing electric energy meter, provides a kind of safe and reliable inspection, the integrated termination of voltage-withstand test.It is little that this device has guarantee connection resistance, and during voltage-withstand test, safe spacing is large, safe and reliable advantage.
The utility model adopts following technical scheme:
A kind of single-phase electric energy meter inspection, the integrated termination of voltage-withstand test, comprise test installation panel, the front of this test installation panel is provided with successively under upper:
Control the compression joint mechanism of electric energy meter position;
The energy meter terminal terminal box that test installation panel is slidably connected;
Power test Wiring module;
Voltage-withstand test Wiring module; Described voltage-withstand test Wiring module has test connection terminal and contact point, and contact point protrudes from the front of test installation panel, and in the test installation panel of this module installation above power test Wiring module.
Preferably, described power test Wiring module comprises electric energy mounting bracket, electric energy connection terminal and guidepost; Electric energy mounting bracket is installed on test installation panel by securing member.
Preferably, described energy meter terminal terminal box comprises terminal box mounting bracket, connecting terminal of junction box and guide runner; Energy meter terminal terminal box is arranged on test installation panel by guide runner.
Preferably, described energy meter terminal terminal box is also provided with the connecting hole suitable with described guidepost.
Preferably, described energy meter terminal terminal box has the first surface of contact and the second surface of contact, and the first surface of contact is positioned at the inner side of energy meter terminal terminal box, and the first surface of contact and contact point suitable.
Preferably, described second surface of contact is positioned at the bottom surface of energy meter terminal terminal box, the second surface of contact and electric energy connection terminal suitable.
Preferably, described test connection terminal is installed on the reverse side of test panel.
Preferably, described compression joint mechanism comprises the electric cylinder being installed on test installation panel reverse side and the sliding floor be arranged on test installation panel, and the screw mandrel of electric cylinder to be connected with sliding floor by a contiguous block and to drive sliding floor to move up and down.
Preferably, described guidepost is provided with spring.
The beneficial effects of the utility model are: can carry out voltage-withstand test and power test, and can not occur in test process that test voltage is high punctures relay, damage electric energy meter electric energy calibrating part; Meanwhile, this device is stablized with electric energy meter contact, effective safeguard work progress.
Accompanying drawing illustrates:
Fig. 1 is Facad structure schematic diagram of the present utility model;
Fig. 2 is inverse layer structure schematic diagram of the present utility model;
Fig. 3 is the structural representation of energy meter terminal terminal box in the utility model;
Fig. 4 is the bottom surface structure schematic diagram of energy meter terminal terminal box in the utility model;
Fig. 5 is the structural representation of power test Wiring module in the utility model;
Fig. 6 is the front wiring layout of voltage-withstand test Wiring module in the utility model;
Fig. 7 is the reverse side wiring layout of voltage-withstand test Wiring module in the utility model;
Fig. 8 is the energy meter terminal terminal box of the utility model when carrying out voltage-withstand test and the connection diagram of power test Wiring module;
Fig. 9 is the energy meter terminal terminal box of the utility model when carrying out voltage-withstand test and the connection diagram of voltage-withstand test Wiring module;
Figure 10 is the energy meter terminal terminal box of the utility model when carrying out power test and the connection diagram of power test Wiring module;
Figure 11 is the energy meter terminal terminal box of the utility model when carrying out power test and the connection diagram of voltage-withstand test Wiring module;
Figure 12 is the constitutional diagram of the utility model when carrying out voltage-withstand test;
Figure 13 is the constitutional diagram of the utility model when carrying out power test;
Wherein: 1, test installation panel, 2, compression joint mechanism, 2-1, electric cylinder, 2-2, contiguous block, 2-3, sliding floor, 3, energy meter terminal terminal box, 3-1, terminal box mounting bracket, 3-2, connecting terminal of junction box, 3-3, the first surface of contact, 3-4, the second surface of contact, 3-5 guide runner, 4, power test Wiring module, 4-1, electric energy mounting bracket, 4-2, electric energy connection terminal, 4-3, guidepost, 5, voltage-withstand test Wiring module, 5-1, test connection terminal, 5-2, contact point, 6, single-phase electric energy meter.
Embodiment:
Below in conjunction with the accompanying drawing in the utility model embodiment, be clearly and completely described the technical scheme in the utility model embodiment, obviously, described embodiment is only the utility model part embodiment, instead of whole embodiments.Based on the embodiment in the utility model, those of ordinary skill in the art are not making the every other embodiment obtained under creative work prerequisite, all belong to the scope of the utility model protection.
Embodiment 1: a kind of single-phase electric energy meter inspection, the integrated termination of voltage-withstand test, as shown in figs. 1-7, comprise test installation panel 1, the front of this test installation panel is provided with successively its structure under upper:
Control the compression joint mechanism 2 of electric energy meter 6 position;
The energy meter terminal terminal box 3 that test installation panel 1 is slidably connected;
Power test Wiring module 4;
Voltage-withstand test Wiring module 5; This voltage-withstand test Wiring module 5 has the front that test connection terminal 5-1 and contact point 5-2, contact point 5-2 protrude from test installation panel 1, and this voltage-withstand test Wiring module 5 is arranged in the test installation panel 1 above power test Wiring module 4.
Described power test Wiring module 4 comprises electric energy mounting bracket 4-1, electric energy connection terminal 4-2 and guidepost 4-3, and guidepost 4-3 overcoat has spring, can support preferably energy meter terminal terminal box 3; Electric energy mounting bracket 4-1 is installed on test installation panel 1 by screw.
Described energy meter terminal terminal box 3 comprises terminal box mounting bracket 3-1, connecting terminal of junction box 3-2 and guide runner 3-5; Energy meter terminal terminal box 3 is arranged on test installation panel 1 by guide runner 3-5.Accordingly, test on installation panel 1 and be provided with the guide chute suitable with described guide runner 3-5.
Described energy meter terminal terminal box 3 is also provided with the connecting hole suitable with described guidepost 4-3.
Described energy meter terminal terminal box 3 has the first surface of contact 3-3 and the second surface of contact 3-4, and the first surface of contact 3-3 is positioned at the inner side of energy meter terminal terminal box 3, and the first surface of contact 3-3 and contact point 5-2 is suitable.
Described second surface of contact 3-4 is positioned at the bottom surface of energy meter terminal terminal box 3, and the second surface of contact 3-4 and electric energy connection terminal 4-2 is suitable.
Described test connection terminal 5-1 is installed on the reverse side of test panel 1.
Described compression joint mechanism 2 comprises the electric cylinder 2-1 being installed on test installation panel 1 reverse side and the sliding floor 2-3 be arranged on test installation panel 1, and the screw mandrel of electric cylinder 2-1 to be connected with sliding floor 2-3 by contiguous block 2-2 and to drive sliding floor 2-3 to move up and down.
As shown in Figure 8, Figure 9, during voltage-withstand test, energy meter terminal terminal box 3 and power test Wiring module 4 are in and disconnect completely, the state that energy meter terminal terminal box 3 is connected with voltage-withstand test Wiring module 5.
As shown in figure 12, when this application of installation is in voltage-withstand test, first single-phase electric energy meter 6 is connected with sliding floor 2-3 by securing member, then crimping single-phase electric energy meter 6 is moved down by electric cylinder 2-1, the calibrating terminal of single-phase electric energy meter 6 is contacted with the connecting terminal of junction box 3-2 of energy meter terminal terminal box 3 connect, control crimp stroke makes energy meter terminal terminal box 3 be parked in voltage-withstand test position simultaneously, the first surface of contact 3-3 of energy meter terminal terminal box 3 is allowed to be connected conducting with the contact point 5-2 of voltage-withstand test Wiring module 5, p-wire is connected with test connection terminal 5-1, now withstand voltage properties test can be carried out.
When carrying out voltage-withstand test, the bottom surface of energy meter terminal terminal box 3 and the end face distance of power test Wiring module, at more than 8mm, can realize power test part and voltage-withstand test part is completely isolated.
As shown in Figure 10 and Figure 11, during power test, energy meter terminal terminal box 3 and voltage-withstand test Wiring module 5 are in and disconnect completely, the state that energy meter terminal terminal box 3 is connected with power test Wiring module 4.
As shown in figure 13: voltage-withstand test terminates, control electric cylinder 2-1 and continue crimping single-phase electric energy meter 6 downwards, the connecting terminal of junction box 3-2 of energy meter terminal terminal box 3 is connected with the electric energy connection terminal 4-2 of power test Wiring module 4 by the second surface of contact 3-4, then p-wire is communicated with power test Wiring module 4, electric energy performance is tested.
To the above-mentioned explanation of the disclosed embodiments, professional and technical personnel in the field are realized or uses the utility model.To be apparent for those skilled in the art to the multiple amendment of these embodiments, General Principle as defined herein when not departing from spirit or scope of the present utility model, can realize in other embodiments.Therefore, the utility model can not be restricted to these embodiments shown in this article, but will meet the widest scope consistent with principle disclosed herein and feature.

Claims (9)

1. single-phase electric energy meter inspection, the integrated termination of voltage-withstand test, it is characterized in that, comprise test installation panel, the front of this test installation panel is provided with successively under upper:
Control the compression joint mechanism of electric energy meter position;
The energy meter terminal terminal box that test installation panel is slidably connected;
Power test Wiring module;
Voltage-withstand test Wiring module; Described voltage-withstand test Wiring module has test connection terminal and contact point, and contact point protrudes from the front of test installation panel, and in the test installation panel of this module installation above power test Wiring module.
2. integrated termination according to claim 1, is characterized in that: described power test Wiring module comprises electric energy mounting bracket, electric energy connection terminal and guidepost; Electric energy mounting bracket is installed on test installation panel by securing member.
3. integrated termination according to claim 2, is characterized in that: described energy meter terminal terminal box comprises terminal box mounting bracket, connecting terminal of junction box and guide runner; Energy meter terminal terminal box is arranged on test installation panel by guide runner.
4. integrated termination according to claim 3, is characterized in that: described energy meter terminal terminal box is also provided with the connecting hole suitable with described guidepost.
5. integrated termination according to claim 3, it is characterized in that: described energy meter terminal terminal box has the first surface of contact and the second surface of contact, first surface of contact is positioned at the inner side of energy meter terminal terminal box, and the first surface of contact and contact point suitable.
6. integrated termination according to claim 5, is characterized in that: described second surface of contact is positioned at the bottom surface of energy meter terminal terminal box, the second surface of contact and electric energy connection terminal suitable.
7. the integrated termination according to any one of claim 3-6, is characterized in that: described test connection terminal is installed on the reverse side of test panel.
8. integrated termination according to claim 7, it is characterized in that: described compression joint mechanism comprises the electric cylinder being installed on test installation panel reverse side and the sliding floor be arranged on test installation panel, the screw mandrel of electric cylinder to be connected with sliding floor by a contiguous block and to drive sliding floor to move up and down.
9. integrated termination according to claim 7, is characterized in that: described guidepost is provided with spring.
CN201420556134.7U 2014-09-25 2014-09-25 A kind of single-phase electric energy meter inspection, the integrated termination of voltage-withstand test Active CN204188796U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420556134.7U CN204188796U (en) 2014-09-25 2014-09-25 A kind of single-phase electric energy meter inspection, the integrated termination of voltage-withstand test

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420556134.7U CN204188796U (en) 2014-09-25 2014-09-25 A kind of single-phase electric energy meter inspection, the integrated termination of voltage-withstand test

Publications (1)

Publication Number Publication Date
CN204188796U true CN204188796U (en) 2015-03-04

Family

ID=52620779

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420556134.7U Active CN204188796U (en) 2014-09-25 2014-09-25 A kind of single-phase electric energy meter inspection, the integrated termination of voltage-withstand test

Country Status (1)

Country Link
CN (1) CN204188796U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104237840A (en) * 2014-09-25 2014-12-24 国家电网公司 Integrated junction device for single-phase kilowatt-hour meter inspection and electric strength test

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104237840A (en) * 2014-09-25 2014-12-24 国家电网公司 Integrated junction device for single-phase kilowatt-hour meter inspection and electric strength test

Similar Documents

Publication Publication Date Title
CN203101563U (en) Polymer lithium-ion battery short-circuit detection apparatus
CN201788200U (en) Special test clamp for direct-current resistance test
CN104237840A (en) Integrated junction device for single-phase kilowatt-hour meter inspection and electric strength test
CN204595097U (en) A kind of Contact Resistance of Circuit Breaker proving installation
CN204188796U (en) A kind of single-phase electric energy meter inspection, the integrated termination of voltage-withstand test
CN204515052U (en) A kind of cable fault detect device
CN205212128U (en) Little generating line cross -over connection connecting cable line in screen top
CN203800224U (en) Shunt line 90 degree spiral clamping head
CN203365531U (en) Novel alternating-current and direct-current high-voltage electroscope
CN205003223U (en) Current transformer detection device
CN204945312U (en) Measure the servicing unit of insulating tool
CN218272675U (en) Withstand voltage detection device of ammeter
CN203813085U (en) 0 DEG screw-type clamp head of shunt wire
CN105490122A (en) Screen-top miniature bus bridging-connection cable
CN203216999U (en) Capacitive equipment dielectric loss live line measurement sampling device
CN202502136U (en) Measuring device for induced voltage and induced current of AC line
CN204255981U (en) Special fixing-line device changed by a kind of ammeter
CN203982926U (en) A kind of low-voltage circuit insulating blanked clamper
CN203519652U (en) Insulation rod for switch equipment loop resistance test
CN202196146U (en) On-line detecting device for electric power circuit insulator
CN202041568U (en) Inserting type contact resistor measurement clamper
CN201892721U (en) High voltage resistant testing device
CN201449420U (en) Device for measuring dielectric loss of insulating material for transformer
CN204142854U (en) A kind of lightning arrester live line measurement servicing unit
CN204719181U (en) The pressure resistant testing device of insulating paper

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CP01 Change in the name or title of a patent holder

Address after: 100031 Xicheng District West Chang'an Avenue, No. 86, Beijing

Patentee after: STATE GRID CORPORATION OF CHINA

Patentee after: ELECTRIC POWER RESEARCH INSTITUTE OF STATE GRID SHANDONG ELECTRIC POWER Co.

Address before: 100031 Xicheng District West Chang'an Avenue, No. 86, Beijing

Patentee before: State Grid Corporation of China

Patentee before: ELECTRIC POWER RESEARCH INSTITUTE OF STATE GRID SHANDONG ELECTRIC POWER Co.

CP01 Change in the name or title of a patent holder
TR01 Transfer of patent right

Effective date of registration: 20210423

Address after: No. 150, Jinger Road, Daguanyuan, Shizhong District, Jinan City, Shandong Province

Patentee after: Shandong Electric Power Marketing Center

Patentee after: STATE GRID CORPORATION OF CHINA

Patentee after: ELECTRIC POWER RESEARCH INSTITUTE OF STATE GRID SHANDONG ELECTRIC POWER Co.

Address before: 100031 Xicheng District West Chang'an Avenue, No. 86, Beijing

Patentee before: STATE GRID CORPORATION OF CHINA

Patentee before: ELECTRIC POWER RESEARCH INSTITUTE OF STATE GRID SHANDONG ELECTRIC POWER Co.

TR01 Transfer of patent right