Prior art keywords
wall
pipeline
sleeve pipe
sound
insulating structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201420577305.4U
Other languages
Chinese (zh)
Inventor
郑凯华
姚华伟
薛红飞
金嘉玮
张铭
周晓莉
黄轶
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Construction No 4 Group Co Ltd
Original Assignee
Shanghai Construction No 4 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Construction No 4 Group Co Ltd filed Critical Shanghai Construction No 4 Group Co Ltd
Priority to CN201420577305.4U priority Critical patent/CN204164508U/en
Application granted granted Critical
Publication of CN204164508U publication Critical patent/CN204164508U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Pipe Accessories (AREA)

Abstract

The utility model discloses a kind of pipeline and wear double wall sound insulating structure, belong to wall feed-through pipeline technical field of construction, for solving the sound insulation and noise reduction problem of pipeline through-wall.Double wall sound insulating structure worn by pipeline, comprise and be sheathed on the first sleeve pipe outside pipeline and the second thimble assembly successively, the second thimble assembly is respectively independently sleeve pipe one and sleeve pipe two, and sleeve pipe one is fixed on fixing wall, sleeve pipe two is fixed on floating wall, sleeve pipe two and floating wall synchronizing moving; Establish the first sound-absorbing material layer between pipeline outer wall and first set inner tube wall, pipeline establishes metal hose joint near the one end of the wall that floats.The distortion that double wall sound insulating structure can prevent floating pipeline within the walls worn by this pipeline, meets the sound insulation and noise reduction effect of pipeline through-wall.

Description

Double wall sound insulating structure worn by a kind of pipeline
Technical field
The utility model belongs to wall feed-through pipeline technical field of construction, particularly relates to a kind of pipeline and wears double wall sound insulating structure.
Background technique
Usually, some ventilation ducts and water pipe can be arranged in building masonry wall.When pipeline works, sound of the wind or the underwater sound can form noise, thus affect the defening effect of building.Therefore, in the building masonry wall higher to sound isolation requirement, pipeline through-wall structure all will do sound insulation process, to prevent the solid-borne sound transmission between pipeline and body of wall.Traditional way is, sound insulation by filling material between pipeline and body of wall, to reduce noise pollution.But, when building masonry wall is for floating wall, move because floating wall has vertical direction, adopt traditional pipeline through-wall structure cause the distortion of pipeline body because floating floating of wall, destroying.Therefore, the sound insulating structure how providing a kind of pipeline to wear double wall and method of construction are those skilled in the art's technical problems urgently to be resolved hurrily to meet the sound insulation and noise reduction of the double wall pipeline through-wall of fixing wall and floating wall composition.
Model utility content
The purpose of this utility model is to provide a kind of pipeline to wear double wall sound insulating structure, to solve the sound insulation and noise reduction problem of the double wall pipeline through-wall of fixing wall and floating wall composition.
To achieve these goals, the technical solution of the utility model is:
Double wall sound insulating structure worn by a kind of pipeline, described double wall comprises the fixing wall and floating wall that are set up in parallel successively, described floating wall moves at vertical direction, described pipeline is successively horizontal through described fixing wall and described floating wall, double wall sound insulating structure worn by described pipeline, comprise and be sheathed on the first sleeve pipe outside described pipeline and the second thimble assembly successively, described second thimble assembly is respectively separate sleeve pipe one and sleeve pipe two, described sleeve pipe one is fixedly installed on described fixing wall, described sleeve pipe two is fixedly installed on described floating wall, and described sleeve pipe two and described floating wall synchronizing moving, lay the first sound-absorbing material layer between described pipeline outer wall and described first set inner tube wall, described pipeline is provided with metal hose joint near one end of described floating wall.
Further, between described first sleeve outer wall and described sleeve pipe one inwall, be provided with grey mud layer, between described first sleeve outer wall and described sleeve pipe two inwall, lay the second sound-absorbing material layer.
Further, the length of described metal hose joint is 50mm-150mm.
Further, described pipeline is water pipe or airduct.
Further, described airduct outer wall is also pasted with warming plate.
Further, described first sound-absorbing material layer is rock wool layer.
Further, the thickness of described sleeve pipe one and described sleeve pipe two is 1.1mm-1.3mm.
Further, described first sound-absorbing material layer in described water pipe and the two ends of described second sound-absorbing material layer arrange the first clay layer shutoff respectively.
The utility model compared with prior art, tool has the following advantages and beneficial effect: double wall sound insulating structure worn by pipeline of the present utility model, double wall comprises the fixing wall and floating wall that are set up in parallel successively, the wall that floats moves at vertical direction, pipeline is successively horizontal through fixing wall and floating wall, double wall sound insulating structure worn by described pipeline, comprise and be sheathed on the first sleeve pipe outside pipeline and the second thimble assembly successively, second thimble assembly is respectively separate sleeve pipe one and sleeve pipe two, sleeve pipe one is fixedly installed on fixing wall, sleeve pipe two is fixedly installed on floating wall, and sleeve pipe two and floating wall synchronizing moving, lay the first sound-absorbing material layer between pipeline outer wall and first set inner tube wall, pipeline is provided with metal hose joint near the one end of the wall that floats.By arranging metal hose joint on pipeline, playing buffer function, when can prevent floating wall vertical direction from moving, being positioned at distortion or even the damage of the segment pipe floated within the walls.In addition, by laying sound-absorbing material between pipeline outer wall and the second thimble assembly inwall, noise when pipe ventilated or water flowing can be reduced.Therefore, the sound insulation and noise reduction effect that double wall sound insulating structure can meet the wall feed-through pipeline of the double wall be made up of fixing wall and floating wall worn by pipeline of the present utility model.Meanwhile, because metal hose joint can be installed on pipeline in advance, do not affect the working procedure of original Pipe installing, can the reduction of erection time.
Accompanying drawing explanation
Pipeline of the present utility model is worn double wall sound insulating structure and is provided by following embodiment and accompanying drawing.
Fig. 1 is the structural representation that double wall sound insulating structure worn by the utility model one embodiment pipeline;
Fig. 2 is the structural representation that double wall sound insulating structure worn by another embodiment's pipeline of the utility model.
Embodiment
Wear double wall sound insulating structure below in conjunction with the drawings and specific embodiments to pipeline of the present utility model to be described in further detail.According to the following describes and claims, advantage of the present utility model and feature will be clearer.It should be noted that, accompanying drawing all adopts the form that simplifies very much and all uses non-ratio accurately, only in order to object that is convenient, aid illustration the utility model embodiment lucidly.
Describe pipeline of the present utility model in detail below in conjunction with Fig. 1 and Fig. 2 and wear double wall sound insulating structure composition.
As shown in Figure 1, double wall sound insulating structure worn by a kind of pipeline, double wall comprises the fixing wall 1 and floating wall 2 that are set up in parallel successively, the wall 2 that floats moves at vertical direction, pipeline 3 is successively horizontal through fixing wall 1 and floating wall 2, double wall sound insulating structure worn by described pipeline, comprise the first sleeve pipe 40 and the second thimble assembly (not shown) be sheathed on successively outside pipeline, second thimble assembly is respectively separate sleeve pipe 1 and sleeve pipe 2 42, sleeve pipe 1 is fixedly installed on fixing wall 1, sleeve pipe 2 42 is fixedly installed on floating wall 2, and sleeve pipe 2 42 and floating wall 2 synchronizing moving, lay the first sound-absorbing material layer 51 between pipeline 3 outer wall and the first sleeve pipe 40 inwall, pipeline 3 is provided with metal hose joint 31 near the one end of the wall 2 that floats.Consider the convenience and Economy of drawing materials, usually select rock wool layer to select thickness to be the metal sleeve of 1.1mm-1.3mm as the first sound-absorbing material layer 51, first sleeve pipe 40.By laying the first sound-absorbing material layer 51 between pipeline outer wall and first set inner tube wall, cotton-shaped rock wool can be fixed on specified position, better sqouynd absorption lowering noise effect can be reached while saving rock wool material.
Specifically, be provided with at concert hall etc. in the building of floating wall (removable body of wall), lay the impact on pipeline when pipeline will take into full account that floating wall vertical direction moves.Therefore, adopt the pipeline of special setting in the present embodiment, on the body of wall side of floating, metal hose joint is set, the destruction to pipeline when moving to prevent floating wall vertical direction at pipeline.Because floating wall is little in the amplitude of vertical direction movement, normally positive and negative 50mm, by arranging metal hose joint, when floating wall vertical direction moves, metal hose joint can flexibility move and play buffer function in the certain limit of vertical direction, thus prevents the pipe deforming through floating wall part from even damaging.Level interval between metal hose joint and floating wall can be designed as 280mm-320mm, such as, can be designed as 300mm.In addition, establishing sound-absorbing material by filling out, the sound insulation and noise reduction effect that double wall sound insulating structure worn by pipeline can be improved.
Continue with reference to figure 1, consider that double wall is the fixing wall 1 and floating wall 2 that are set up in parallel, when floating wall 2 vertical direction moves, by arranging the protection that metal hose joint 31 can realize the segment pipe being positioned at floating wall 2 inside in pipeline 3 body.But the second thimble assembly is made by steel plate materials, be rigid construction, if double wall shares a sleeve pipe, will because floating wall 2 be at mobile destruction second thimble assembly of vertical direction.In order to address this problem, the present embodiment is provided with separate sleeve pipe 1 and sleeve pipe 2 42 respectively in fixing wall 1 and floating wall 2, wherein fix in wall 1 and bury sleeve pipe 1 underground, bury sleeve pipe 2 42 underground in the wall 2 that floats, do not connect between sleeve pipe 1 and sleeve pipe 2 42.Certainly, in order to reach good soundproof effect, the gap of sleeve pipe 1 and sleeve pipe 2 42 substantially horizontal is also provided with the first sound-absorbing material layer 51.Head (shutoff) is received with the first clay layer 61 in the two ends of the first sound-absorbing material layer 51, to close the first sound-absorbing material layer 51.
Continue with reference to figure 1, especially, between sleeve pipe 2 42 and floating wall 2, be provided with the second sound-absorbing material layer 52.Usual second sound-absorbing material layer 52 selects rock wool layer, draws materials to facilitate and constructs.When the object arranging the second sound-absorbing material layer 52 being to make floating wall 2 move, contacting for soft between sleeve pipe 2 42 with floating wall 2, playing certain buffer function, thus prevent the solid-borne sound transmission between sleeve pipe 2 42 and floating wall 2, reach the effect of sound insulation and noise reduction.In addition, the two ends of the second sound-absorbing material layer 52 all adopt the second clay layer 62 to receive head.Certainly, fixing wall 1 and floating wall 2 body of wall outermost are equipped with decorative layer 7.
Continue with reference to figure 1, further, in order to reach good cushioning effect, and do not affect the function of pipeline 3, the length of metal hose joint 31 is 50mm-150mm.
Continue with reference to figure 1, especially, in order to fill the space between fixing wall 1 and sleeve pipe 1, and playing buffer action, making directly not contact therebetween, between fixing wall 1 and sleeve pipe 1, be also provided with plaster 63.
Continue with reference to figure 1, the pipeline 3 of the present embodiment is water pipe.In order to increase the water output of pipeline 3 per unit volume, usual water pipe is circular.
As shown in Figure 2, in another embodiment of the present utility model, pipeline 3 is airduct, for indoor air-supply.In order to reduce energy ezpenditure, airduct outer wall is also pasted with warming plate 8.Such as, thickness can be adopted to be the reinforcement aluminium foil of 30mm, and unit weight is 48kg/m 3centrifugally glass-wool plate makes warming plate 8.Airduct can be chosen as circular or square, is good to facilitate installation and to reduce energy consumption.Certainly, in order to reduce noise during duct ventilation further, fixing wall 1 and sleeve pipe 1 and the joint between floating wall 2 and sleeve pipe 2 42 are also filled out and are provided with damping sound-insulating felt 9.Damping sound-insulating felt 9 can select thickness to be 2mm, and face quality is 4kg/m 2b1 level nonflammable material make.
Continue below to describe with reference to figure 1 and Fig. 2 the method for construction that double wall sound insulating structure worn by the utility model pipeline in detail.
The method of construction of double wall sound insulating structure worn by pipeline, comprises the steps:
Step one: construct described fixing wall 1 and floating wall 2, and in fixing wall 1 and floating wall 2 reserved opening, and bury sleeve pipe 1 underground in fixing wall 1, in floating wall 2, bury sleeve pipe 2 42 underground, and sleeve pipe 1 and sleeve pipe 2 42 separate.
In order to not affect the mutual performance of fixing wall 1 and floating wall 2, and ensure wall 2 vertically movement in certain amplitude range of floating, fixing not connection between wall 1 and floating wall 2, but leave certain gap.Correspondingly, be sheathed on the sleeve pipe 1 of fixing wall 1 outer wall and be sheathed on the separate setting of sleeve pipe 2 42 of floating wall 2 outer wall, thus meeting sleeve pipe 2 42 and move with the synchronous vertical direction of floating wall 2.Usually, in order to save material and meet the second thimble assembly to the protection of pipeline 3, sleeve pipe 1 and sleeve pipe 2 42 all select thickness to be the metal sleeve of 1.1mm-1.3mm.Certainly, when casing thickness is 1.2mm, effect is better.
Step 2: by the first sleeve pipe 40 successively through sleeve pipe 1 and sleeve pipe 2 42, pipeline 3 is sheathed in the first sleeve pipe 40, and make metal hose joint 31 be positioned at one end of the close wall 2 that floats.
Usually; metal hose joint 31 is fixedly connected with the pipeline 3 of rigidity is airtight; when not only satisfied wall 2 vertical direction that floats moves; buffer protection function is played to the pipeline 3 being positioned at floating wall 2; and when meeting ventilation or water flowing in pipeline 3; can not seepage, thus ensure good ventilation or water flowing effect.
Step 3: respectively the first sound-absorbing material layer 51 is set between sleeve pipe 1 and the first sleeve pipe 40 and between sleeve pipe 2 42 and the first sleeve pipe 40.
By arranging the first sound-absorbing material layer 51, reducing noise when ventilation or water flowing in pipeline 3, thus meeting the noise reduction defening effect of building.
Continue with reference to figure 1, especially, when pipeline 3 is water pipes, the two ends of the first sound-absorbing material layer 51 and the second sound-absorbing material layer 52 arrange the first clay layer 61 shutoff respectively.By arranging the first clay layer 61, the first sound-absorbing material layer 51 can be separately fixed at the special position between sleeve pipe 1 and the first sleeve pipe 40 and between sleeve pipe 2 42 and the first sleeve pipe 40, thus reach good defening effect.In like manner, the second sound-absorbing material layer 52 is also fixed on specified position, thus reaches good defening effect.
In sum, double wall sound insulating structure worn by pipeline of the present utility model, double wall comprises the fixing wall and floating wall that are set up in parallel successively, the wall that floats moves at vertical direction, pipeline is successively horizontal through fixing wall and floating wall, double wall sound insulating structure worn by described pipeline, comprise and be sheathed on the first sleeve pipe outside pipeline and the second thimble assembly successively, second thimble assembly is respectively separate sleeve pipe one and sleeve pipe two, sleeve pipe one is fixedly installed on fixing wall, sleeve pipe two is fixedly installed on floating wall, and sleeve pipe two and floating wall synchronizing moving; Lay the first sound-absorbing material layer between pipeline outer wall and first set inner tube wall, pipeline is provided with metal hose joint near the one end of the wall that floats.By arranging metal hose joint on pipeline, playing buffer function, when can prevent floating wall vertical direction from moving, being positioned at distortion or even the damage of the segment pipe floated within the walls.In addition, by laying sound-absorbing material between pipeline outer wall and the second thimble assembly inwall, noise when pipe ventilated or water flowing can be reduced.Further, by arranging the second sound-absorbing material layer between sleeve pipe two and floating wall, when floating wall can be made to move, contact for soft between sleeve pipe two with floating wall, thus it is fixing transaudient to stop between sleeve pipe two and floating wall, thus reduction noise.The method of construction of double wall sound insulating structure worn by pipeline, first the fixing wall of construction and floating wall, and at fixing wall and the reserved opening within the walls that floats, and buries sleeve pipe one within the walls underground fixing, buries sleeve pipe two within the walls underground floating, and sleeve pipe one and sleeve pipe two separate; Then by the first sleeve pipe successively horizontal through sleeve pipe one and sleeve pipe two, pipeline is sheathed in the first sleeve pipe, and makes metal hose joint be positioned near the one end of wall of floating; Finally between sleeve pipe one and the first sleeve pipe and between sleeve pipe two and the first sleeve pipe, fill the first sound-absorbing material layer respectively.Meanwhile, because metal hose joint can be installed on pipeline in advance, do not affect the working procedure of original Pipe installing, can the reduction of erection time.
Foregoing description is only the description to the utility model preferred embodiment, any restriction not to the utility model scope.Any change that those skilled in the art does according to above-mentioned disclosure, modification, all belong to the protection domain of claim.

Claims (8)

1. double wall sound insulating structure worn by a pipeline, described double wall comprises the fixing wall and floating wall that are set up in parallel successively, described floating wall moves at vertical direction, described pipeline is successively horizontal through described fixing wall and described floating wall, it is characterized in that, double wall sound insulating structure worn by described pipeline, comprise and be sheathed on the first sleeve pipe outside described pipeline and the second thimble assembly successively, described second thimble assembly is respectively separate sleeve pipe one and sleeve pipe two, described sleeve pipe one is fixedly installed on described fixing wall, described sleeve pipe two is fixedly installed on described floating wall, and described sleeve pipe two and described floating wall synchronizing moving, lay the first sound-absorbing material layer between described pipeline outer wall and described first set inner tube wall, described pipeline is provided with metal hose joint near one end of described floating wall.
2. double wall sound insulating structure worn by pipeline as claimed in claim 1, it is characterized in that, is provided with grey mud layer between described first sleeve outer wall and described sleeve pipe one inwall, lay the second sound-absorbing material layer between described first sleeve outer wall and described sleeve pipe two inwall.
3. double wall sound insulating structure worn by pipeline as claimed in claim 1, and it is characterized in that, the length of described metal hose joint is 50mm-150mm.
4. double wall sound insulating structure worn by the pipeline as described in any one of claims 1 to 3, it is characterized in that, described pipeline is water pipe or airduct.
5. double wall sound insulating structure worn by pipeline as claimed in claim 4, and it is characterized in that, described airduct outer wall is also pasted with warming plate.
6. double wall sound insulating structure worn by pipeline as claimed in claim 5, and it is characterized in that, described first sound-absorbing material layer is rock wool layer.
7. double wall sound insulating structure worn by pipeline as claimed in claim 6, and it is characterized in that, the thickness of described sleeve pipe one and described sleeve pipe two is 1.1mm-1.3mm.
8. double wall sound insulating structure worn by pipeline as claimed in claim 7, and it is characterized in that, described first sound-absorbing material layer in described water pipe and the two ends of described second sound-absorbing material layer arrange the first clay layer shutoff respectively.
CN201420577305.4U 2014-10-08 2014-10-08 Double wall sound insulating structure worn by a kind of pipeline Expired - Fee Related CN204164508U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420577305.4U CN204164508U (en) 2014-10-08 2014-10-08 Double wall sound insulating structure worn by a kind of pipeline

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420577305.4U CN204164508U (en) 2014-10-08 2014-10-08 Double wall sound insulating structure worn by a kind of pipeline

Publications (1)

Publication Number Publication Date
CN204164508U true CN204164508U (en) 2015-02-18

Family

ID=52538195

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420577305.4U Expired - Fee Related CN204164508U (en) 2014-10-08 2014-10-08 Double wall sound insulating structure worn by a kind of pipeline

Country Status (1)

Country Link
CN (1) CN204164508U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104455753A (en) * 2014-10-08 2015-03-25 上海建工四建集团有限公司 Pipeline through-double-layer-wall sound insulation structure for pipeline penetrating through two layers of walls and construction method
CN105135065A (en) * 2015-06-24 2015-12-09 中国建筑第八工程局有限公司 Fireproof structure allowing pipeline to penetrate lightgage steel joist gypsum board partition wall and construction method of fireproof structure
CN109882947A (en) * 2019-03-30 2019-06-14 彭青珍 A kind of house air-conditioning
CN117947889A (en) * 2024-03-26 2024-04-30 安徽省建筑材料科学技术研究所有限公司 Assembled building wall

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104455753A (en) * 2014-10-08 2015-03-25 上海建工四建集团有限公司 Pipeline through-double-layer-wall sound insulation structure for pipeline penetrating through two layers of walls and construction method
CN104455753B (en) * 2014-10-08 2017-02-15 上海建工四建集团有限公司 Pipeline through-double-layer-wall sound insulation structure for pipeline penetrating through two layers of walls and construction method
CN105135065A (en) * 2015-06-24 2015-12-09 中国建筑第八工程局有限公司 Fireproof structure allowing pipeline to penetrate lightgage steel joist gypsum board partition wall and construction method of fireproof structure
CN109882947A (en) * 2019-03-30 2019-06-14 彭青珍 A kind of house air-conditioning
CN117947889A (en) * 2024-03-26 2024-04-30 安徽省建筑材料科学技术研究所有限公司 Assembled building wall
CN117947889B (en) * 2024-03-26 2024-06-11 安徽省建筑材料科学技术研究所有限公司 Assembled building wall

Similar Documents

Publication Publication Date Title
CN204164508U (en) Double wall sound insulating structure worn by a kind of pipeline
CN205116435U (en) Waterproof structure of vertical connected node of prefabricated concrete structure wall body
CN104455753B (en) Pipeline through-double-layer-wall sound insulation structure for pipeline penetrating through two layers of walls and construction method
CN211850327U (en) Novel heat-insulation building energy-saving wallboard
CN204040300U (en) A kind of prefabricated wall feed-through pipeline structure of masonry wall
CN202227514U (en) High sound-insulation wall
CN204826318U (en) Outdoor main room sound -proof wall that becomes
CN104908893A (en) Cabin used for deep-water semi-submersible drilling platform
CN203175571U (en) Subway station independent-of-wall type partition wall
CN212772972U (en) Grooving-free cloth pipe structure of air-entraining block wall
CN205822514U (en) Indoor grouting partition wall
CN215110995U (en) Fireproof sound insulation honeycomb steel beam
CN204986039U (en) Buried sleeve organizes subassembly
CN206736961U (en) A kind of Novel steel-plastic composite pipe corridor
CN221461526U (en) Novel assembled heat preservation wall
CN205777043U (en) The fireproof heat insulating compound floor of noise elimination
CN204785111U (en) Waterproof construction of shaft is connected to outdoor tuber pipe
CN204531169U (en) A kind of rain proof type compound sound absorption wall body module
CN203334323U (en) Basement waterproof layer
CN202483142U (en) Noise-proof floor
CN107178672A (en) Toilet pipeline sound partiting system
CN104018616B (en) Wall plate structure
CN208056439U (en) A kind of building block exterior wall air louver prefabricated section
CN212672686U (en) Prefabricated electric tracing thermal insulation pipe
CN210177785U (en) Noise reduction brick beneficial to installation

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150218

Termination date: 20171008

CF01 Termination of patent right due to non-payment of annual fee