CN204081574U CN201420399282.2U CN201420399282U CN204081574U CN 204081574 U CN204081574 U CN 204081574U CN 201420399282 U CN201420399282 U CN 201420399282U CN 204081574 U CN204081574 U CN 204081574U
Authority
CN
China
Prior art keywords
girder steel
clamp
steel
steel clamp
sheet metal
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201420399282.2U
Other languages
Chinese (zh)
Inventor
盛晓云
张媛
滕文
陈冬
叶金根
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui Huadian Engineering Consulting and Design Co Ltd
Original Assignee
Anhui Huadian Engineering Consulting and Design Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Anhui Huadian Engineering Consulting and Design Co Ltd filed Critical Anhui Huadian Engineering Consulting and Design Co Ltd
Priority to CN201420399282.2U priority Critical patent/CN204081574U/en
Application granted granted Critical
Publication of CN204081574U publication Critical patent/CN204081574U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

A kind of steel work transformer station, it comprises main body, in described main body, roofing top girder steel adopts U-steel, described girder steel is provided with multiple girder steel clamp, described girder steel clamp can with being intended to reversing of position and handling on girder steel, girder steel clamp has hung wire casing and lighting by suspension rod in below, and described girder steel clamp is made up of C shape sheet metal and bolt, and arbitrary horizontal edge of C shape sheet metal is provided with screw.The time that the utility model does not put forward money by electric specialty preheating embedding line restricts, improve efficiency of construction, accelerate engineering construction progress, and decrease the link of the pre-buried illumination pipeline of engineering, remain the integrality of profiled sheet, girder steel clamp can be installed according to light fixture and wire casing to be needed to carry out position adjustment, thus makes in-site installation more convenient, faster.

Description

A kind of steel work transformer station
Technical field:
The utility model relates to transformation facility technical field, particularly relates to a kind of steel work transformer station.
Background technology:
In present stage national grid construction, gradually occurred that a kind of standard dispensing formula substation project builds form, namely prefabricated assembled steel work is adopted to carry out building constructions thing, to reaching minimizing resource consumption, the object of increasing work efficiency and preserving the ecological environment, but in the practical set process of steel-structure factory building, need the link of carrying out the pre-buried illumination pipeline of engineering, so just there will be civil engineering and be subject to the restriction that money put forward by electric lighting light fixture pipeline, and profiled sheet also becomes imperfect after pre-buried illumination pipeline, have impact on the integrally-built fastness of transformer station and stability, and because pre-buried illumination pipeline is fixed, therefore often there will be in illumination in-site installation and inconvenient situation is installed, thus have impact on efficiency of construction, slowed down engineering construction progress.
Utility model content:
In order to solve Problems existing in background technology, the utility model is by the following technical solutions: it comprises main body, in described main body, roofing top girder steel adopts U-steel, described girder steel is provided with multiple girder steel clamp, described girder steel clamp can with being intended to reversing of position and handling on girder steel, girder steel clamp has hung wire casing and lighting by suspension rod in below, and described girder steel clamp is made up of C shape sheet metal and bolt, and arbitrary horizontal edge of C shape sheet metal is provided with screw.
Described U-steel is C-type steel or i iron.
The time that the utility model does not put forward money by electric specialty preheating embedding line when lighting installation is installed in civil engineering restricts, operation can be carried out according to the construction period of civil engineering building and node, improve efficiency of construction, accelerate engineering construction progress, and decrease the link of the pre-buried illumination pipeline of engineering, remain the integrality of profiled sheet, girder steel clamp can be installed according to light fixture and wire casing to be needed to carry out position adjustment, thus makes in-site installation more convenient, faster.
Accompanying drawing illustrates:
Fig. 1 is structural representation of the present utility model;
Fig. 2 is the enlarged drawing of the utility model girder steel clamp.
Detailed description of the invention:
With reference to Fig. 1-2, the utility model it comprise main body 1, in described main body 1, roofing top girder steel adopts the U-steel 2 of C-type steel or i iron, described girder steel is provided with multiple girder steel clamp 3, described girder steel clamp 3 is made up of C shape sheet metal 7 and bolt 8, first be set on the base of U-steel 2 with the groove part of C shape sheet metal 7 during installation, then to penetrate from the screw arbitrary horizontal edge of C shape sheet metal 7 with bolt 8 and tighten to direction, U-steel 2 base, thus girder steel clamp 3 is fixed on the base of C-type steel or i iron, when needs carry out reversing of position, only need unclamp bolt 8 moves C shape sheet metal 7 to relevant position, again bolt 8 is tightened again, therefore girder steel clamp 3 can with being intended to reversing of position and handling on girder steel, thus avoid pre-buried illumination pipeline on profiled sheet, remain the integrality of profiled sheet, do not need the time putting forward money by electric specialty preheating embedding line to restrict when lighting installation is installed in civil engineering simultaneously yet, thus improve efficiency of construction, accelerate engineering construction progress, suspension rod 4 is connected with below described girder steel clamp 3, and thereunder hung wire casing 5 and lighting 6 by suspension rod 4, when mounted lamp 6 and wire casing 5, the position adjusting girder steel clamp 3 can be needed according to the position of light fixture 6 and wire casing 5, thus make in-site installation more convenient, faster.

Claims (2)

1. a steel work transformer station, it is characterized in that, it comprises main body, in described main body, roofing top girder steel adopts U-steel, described girder steel is provided with multiple girder steel clamp, described girder steel clamp can with being intended to reversing of position and handling on girder steel, and girder steel clamp has hung wire casing and lighting by suspension rod in below, described girder steel clamp is made up of C shape sheet metal and bolt, and arbitrary horizontal edge of C shape sheet metal is provided with screw.
2. transformer station according to claim 1, is characterized in that, described U-steel is C-type steel or i iron.
CN201420399282.2U 2014-07-21 2014-07-21 A kind of steel work transformer station Active CN204081574U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420399282.2U CN204081574U (en) 2014-07-21 2014-07-21 A kind of steel work transformer station

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420399282.2U CN204081574U (en) 2014-07-21 2014-07-21 A kind of steel work transformer station

Publications (1)

Publication Number Publication Date
CN204081574U true CN204081574U (en) 2015-01-07

Family

ID=52174307

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420399282.2U Active CN204081574U (en) 2014-07-21 2014-07-21 A kind of steel work transformer station

Country Status (1)

Country Link
CN (1) CN204081574U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113718629A (en) * 2021-08-24 2021-11-30 山西中煤担水沟煤业有限公司 Pedestrian bridge-crossing device suitable for belt conveyor in mine

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113718629A (en) * 2021-08-24 2021-11-30 山西中煤担水沟煤业有限公司 Pedestrian bridge-crossing device suitable for belt conveyor in mine
CN113718629B (en) * 2021-08-24 2023-08-15 山西中煤担水沟煤业有限公司 Pedestrian bridge crossing device applicable to belt conveyor in mine

Similar Documents

Publication Publication Date Title
CN204629289U (en) The street lamp of automatically replaceable bulb
CN202299465U (en) Quick adjustment device for steel beam hoisting
CN204081574U (en) A kind of steel work transformer station
CN104210758A (en) Pipe fitting placing frame for building
CN201420317Y (en) Three-dimensional adjustable curtain wall installation connecting piece
CN204387992U (en) A kind of light weight steel structure spool lays and lamp installation hanger
CN204000868U (en) The device of sand concrete free pipe is transferred in a kind of pipe well well-points dewatering
CN203370942U (en) Bending die for multifunctional hydraulic angle steel processing machine
CN203571610U (en) Multifunctional vertical rod for construction
CN105442868A (en) Adjustable steel-structure reticulated shell spliced scaffold
CN204137550U (en) A kind of pipe fitting rack for building
CN205104147U (en) Simulation building sand table
CN204569139U (en) Facilitate the lifting appliance that object is laid
CN204186081U (en) Wallboard riser erecting device
CN204345208U (en) A kind of spherical camera mounting bracket
CN203409762U (en) Cross-shaped petroleum pipeline cutting identification strip
CN204171698U (en) The short material clamping seat of a kind of copper pipe
CN204420513U (en) Electronic information management building device
CN203892726U (en) Prefabricated hanging piece supporting plate
CN203067933U (en) Supporting plate for hoisting pieces
CN203769210U (en) Lightning strip fixing piece special for tile roofs
CN204879048U (en) Novel pipeline support
CN203924504U (en) A kind of building roof steel work
CN204456427U (en) High-altitude long-span wire rope pipe arrangement support
CN205070331U (en) Novel electrician's sleeve pipe

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant