CN204079224U CN201420433336.2U CN201420433336U CN204079224U CN 204079224 U CN204079224 U CN 204079224U CN 201420433336 U CN201420433336 U CN 201420433336U CN 204079224 U CN204079224 U CN 204079224U
Authority
CN
China
Prior art keywords
steel pipe
suspension ring
circle
handling
lifting tool
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201420433336.2U
Other languages
Chinese (zh)
Inventor
刘茂柏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
TIANJIN JINLI STEEL PIPE CO Ltd
Original Assignee
TIANJIN JINLI STEEL PIPE CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by TIANJIN JINLI STEEL PIPE CO Ltd filed Critical TIANJIN JINLI STEEL PIPE CO Ltd
Priority to CN201420433336.2U priority Critical patent/CN204079224U/en
Application granted granted Critical
Publication of CN204079224U publication Critical patent/CN204079224U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Load-Engaging Elements For Cranes (AREA)

Abstract

The utility model provide a kind of can the steel pipe lifting tool of handling different-diameter steel pipe, comprise crossbeam, iron hoop, two steel ropes, suspension ring, on the upside of crossbeam, two ends are respectively equipped with an iron hoop, two iron hoops are connected with suspension ring respectively by steel rope, on the downside of crossbeam, two ends are respectively equipped with and hang circle, hang circle and are provided with the catch gear regulating and hang circle size.The utility model catch gear be arranged on handling steel pipe time can regulate the size of suspension ring according to the diameter of steel pipe, the landing of steel pipe during handling can be avoided; The setting of catch gear middle slide plate firmly can fix the size of suspension ring, prevents the movement of steel pipe in handling process, avoids the landing of steel pipe; The utility model has that safety is good, handling efficiency advantages of higher.

Description

A kind of can the steel pipe lifting tool of handling different-diameter steel pipe
Technical field
The utility model belongs to steel pipe transporting field, especially relate to a kind of can the steel pipe lifting tool of handling different-diameter steel pipe.
Background technology
Along with the development of the modernization of industry, the mechanical equipment of processing and carrier mostly has high safety and reliability requirement for equipment and materials.In the field of each large use steel pipe, often need handling steel tubes and storage, and the steel pipe sizes used in general each field has multiple, if the steel pipe of handling different size uses same suspender, easily cause potential safety hazard on the one hand, also easily make handling efficiency lower on the other hand.Application number is that just to devise a kind of handling efficiency in the patent application of 200920234600 higher and can not affect the steel pipe lifting tool of tube quality, but this suspender easily produces the landing of steel pipe when handling steel pipe, have larger potential safety hazard; During the steel pipe that especially carrying diameter is less, because the size of hanging circle is certain, the therefore easier landing of steel pipe.
Summary of the invention
Problem to be solved in the utility model is to provide that a kind of safety is high, handling efficiency is high and can the steel pipe lifting tool of handling different-diameter steel pipe.
For solving the problems of the technologies described above, the technical solution adopted in the utility model is: a kind of can the steel pipe lifting tool of handling different-diameter steel pipe, comprise crossbeam (1), iron hoop (5), two steel ropes (3), suspension ring (2), it is characterized in that: two ends, described crossbeam (1) upside are respectively equipped with an iron hoop (5), two described iron hoops (5) are connected with described suspension ring (2) respectively by described steel rope (3), two ends, described crossbeam (1) downside are respectively equipped with hangs circle (4), the described circle (4) that hangs is provided with the catch gear (6) that circle (4) size is hung in adjustment, described catch gear (6) comprises cube framework (61) penetrating up and down, can along the slide plate (62) of a cube framework (61) front-rear side walls movement and binding bolt (63), described binding bolt (63) runs through the right side wall of described cube framework (61), the described circle (4) that hangs runs through the described space formed between cube framework (61) left side wall and described slide plate (62).
Further, the number of described binding bolt (63) is 1-2.
Further, two described steel rope (3) length are consistent, and described suspension ring (2) are positioned at described crossbeam (1) overcentre.
Further, described slide plate (62) both sides, top are provided with draw-in groove (62), and described draw-in groove (62) is stuck in the top of described cube framework (61) forward and backward sidewall.
Further, described suspension ring (2), described iron hoop (5) and described in hang circle (4) outside parcel one deck canvas.
The advantage that the utility model has and good effect are: owing to adopting technique scheme, catch gear (6) be arranged on handling steel pipe time can regulate the size of suspension ring (4) according to the diameter of steel pipe, the landing of steel pipe during handling can be avoided; The setting of catch gear (6) middle slide plate (62) firmly can fix the size of suspension ring (4), prevents the movement of steel pipe in handling process, avoids the landing of steel pipe; The utility model has that safety is good, handling efficiency advantages of higher.
Accompanying drawing explanation
Fig. 1 is the structural representation of the utility model embodiment;
Fig. 2 is the structure for amplifying schematic diagram of catch gear in the utility model embodiment;
Fig. 3 is another structure enlarged diagram of catch gear in the utility model embodiment;
In figure:
1, crossbeam 2, suspension ring 3, steel rope
4, circle 5, iron hoop 6, catch gear is hung
61 cubes of frameworks 62, slide plate 63, binding bolts
Detailed description of the invention
In order to better understand the utility model, below in conjunction with specific embodiments and the drawings, the utility model is conducted further description.
The utility model provide a kind of can the steel pipe lifting tool of handling different-diameter steel pipe, as shown in Figure 1, comprise crossbeam 1, iron hoop 5, two steel ropes 3, suspension ring 2, on the upside of crossbeam 1, two ends are respectively equipped with an iron hoop 5, two iron hoops 5 are connected with suspension ring 2 respectively by steel rope 3, on the downside of crossbeam 1, two ends are respectively equipped with and hang circle 4, hang circle 4 and are provided with the catch gear 6 regulating and hang circle 4 size.
Further, two steel rope 3 length are consistent, and suspension ring 2 are positioned at crossbeam 1 overcentre.
Further, please refer to Fig. 2, catch gear 6 comprise cube framework 61 penetrating up and down, can along the slide plate 62 of cube framework 61 front-rear side walls movement and binding bolt 63, binding bolt 63 runs through the right side wall of cube framework 61, hangs circle 4 and runs through the space formed between cube framework 61 left side wall and slide plate 62.In catch gear 6, binding bolt 63 can also be two, as shown in Figure 3.The catch gear 6 that the utility model provides is very good for the fastening effect hanging circle 4, effectively can improve the safety in handling process, prevents the size of hanging circle 4 in handling process from changing, avoids steel pipe landing in handling process.
Further, both sides, slide plate 62 top are provided with draw-in groove 62, and draw-in groove 62 is stuck in the top of the forward and backward sidewall of cube framework 61.
Further, suspension ring 2, iron hoop 5 and hang outside circle 4 and wrap up one deck canvas.
The working process of this example: the utility model has following two kinds of occupation modes.Occupation mode one, before handling, according to the size adjustment catch gear 6 needing handling diameter of steel tube, rotational fastener bolt 63, moving slide board 62, moves up and down the position of catch gear 6, make the ratio diameter of steel tube hanging circle 4 slightly large, directly the two ends of steel pipe are set in respectively during handling and hang in circle 4.Occupation mode two, binding bolt 63 of outwarding winding when handling steel pipe, steel pipe two ends are put into and are hung circle 4, moving slide board 62, screw binding bolt 63, then carry out handling by moving slide board 62 respectively, and this kind of mode safety is higher, can ensure steel pipe not landing.
Above embodiment of the present utility model has been described in detail, but described content can not be considered to for limiting practical range of the present utility model.All equalizations done according to the utility model application range change and improve, and all should still belong within patent covering scope of the present utility model.

Claims (5)

1. one kind can the steel pipe lifting tool of handling different-diameter steel pipe, comprise crossbeam (1), iron hoop (5), two steel ropes (3), suspension ring (2), it is characterized in that: two ends, described crossbeam (1) upside are respectively equipped with an iron hoop (5), two described iron hoops (5) are connected with described suspension ring (2) respectively by described steel rope (3), two ends, described crossbeam (1) downside are respectively equipped with hangs circle (4), the described circle (4) that hangs is provided with the catch gear (6) that circle (4) size is hung in adjustment, described catch gear (6) comprises cube framework (61) penetrating up and down, can along the slide plate (62) of a cube framework (61) front-rear side walls movement and binding bolt (63), described binding bolt (63) runs through the right side wall of described cube framework (61), the described circle (4) that hangs runs through the described space formed between cube framework (61) left side wall and described slide plate (62).
2. according to claim 1 can the steel pipe lifting tool of handling different-diameter steel pipe, it is characterized in that: the number of described binding bolt (63) is 1-2.
3. according to claim 1 can the steel pipe lifting tool of handling different-diameter steel pipe, it is characterized in that: two described steel rope (3) length are consistent, and described suspension ring (2) are positioned at described crossbeam (1) overcentre.
4. according to claim 3 can the steel pipe lifting tool of handling different-diameter steel pipe, it is characterized in that: described slide plate (62) both sides, top are provided with draw-in groove (62), described draw-in groove (62) is stuck in the top of described cube framework (61) forward and backward sidewall.
5. according to any one of claim 1,2,3 or 4 can the steel pipe lifting tool of handling different-diameter steel pipe, it is characterized in that: described suspension ring (2), described iron hoop (5) and described in hang circle (4) outside parcel one deck canvas.
CN201420433336.2U 2014-07-30 2014-07-30 A kind of can the steel pipe lifting tool of handling different-diameter steel pipe Expired - Fee Related CN204079224U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420433336.2U CN204079224U (en) 2014-07-30 2014-07-30 A kind of can the steel pipe lifting tool of handling different-diameter steel pipe

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420433336.2U CN204079224U (en) 2014-07-30 2014-07-30 A kind of can the steel pipe lifting tool of handling different-diameter steel pipe

Publications (1)

Publication Number Publication Date
CN204079224U true CN204079224U (en) 2015-01-07

Family

ID=52171962

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420433336.2U Expired - Fee Related CN204079224U (en) 2014-07-30 2014-07-30 A kind of can the steel pipe lifting tool of handling different-diameter steel pipe

Country Status (1)

Country Link
CN (1) CN204079224U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107381334A (en) * 2017-08-10 2017-11-24 江苏京龙工程机械有限公司 A kind of security grabhook of derrick crane
CN107601256A (en) * 2017-10-19 2018-01-19 成都科盛石油科技有限公司 Suitable for the clamping device of petroleum pipeline movement

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107381334A (en) * 2017-08-10 2017-11-24 江苏京龙工程机械有限公司 A kind of security grabhook of derrick crane
CN107601256A (en) * 2017-10-19 2018-01-19 成都科盛石油科技有限公司 Suitable for the clamping device of petroleum pipeline movement

Similar Documents

Publication Publication Date Title
CN202245809U (en) Electromagnetic gantry crane
CN204079224U (en) A kind of can the steel pipe lifting tool of handling different-diameter steel pipe
CN104909277A (en) Container inner gantry crane
CN203922509U (en) A kind of overhead hoist of hull plate
CN204022133U (en) Hanging apparatus fixed by a kind of belt
CN204162273U (en) The lifting appliance of cylindrical component
CN203903772U (en) Multi-functional balance hoisting beam of crane
CN205397548U (en) Board feeding device
CN202089701U (en) External copper loading mechanism of copper-clad plate production equipment
CN204173797U (en) A kind of door-plate transhipment overhead traveling crane
CN204778669U (en) Fork truck davit that stretches out and draws back
CN208182184U (en) A kind of segmentation lifting device
CN204237411U (en) Baggage elevator
CN202864674U (en) Hoisting device for drummed raw materials
CN203728129U (en) Turning-over and feeding device for rod members
CN203306913U (en) Lifting hook for steel pipe
CN203781399U (en) Buffer transport unit used after pipe preparation
CN206580218U (en) A kind of belt collet roll change tools
CN204079247U (en) New steel plate transporter
CN204310687U (en) Change the suspender of bucket type belt
CN106181946B (en) Pneumatic cucurbit shelf tooling
CN203845202U (en) Material rest convenient to move
CN203582276U (en) Lifting bracket
CN203079520U (en) Steel tube hoisting conveying device
CN204714332U (en) Can enclosed hook during a kind of handling

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant