CN204075186U - A kind of split type air brick core - Google Patents

A kind of split type air brick core Download PDF

Info

Publication number
CN204075186U
CN204075186U CN201420533635.3U CN201420533635U CN204075186U CN 204075186 U CN204075186 U CN 204075186U CN 201420533635 U CN201420533635 U CN 201420533635U CN 204075186 U CN204075186 U CN 204075186U
Authority
CN
China
Prior art keywords
air brick
cover board
metal
brick core
metal cover
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201420533635.3U
Other languages
Chinese (zh)
Inventor
崔庆阳
寇志奇
赵继增
李有奇
毛晓刚
徐兵
黄鹏
张春杰
肖娅红
孔祥魁
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Luoyang Lier Refractory Materials Co Ltd
Original Assignee
Luoyang Lier Refractory Materials Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Luoyang Lier Refractory Materials Co Ltd filed Critical Luoyang Lier Refractory Materials Co Ltd
Priority to CN201420533635.3U priority Critical patent/CN204075186U/en
Application granted granted Critical
Publication of CN204075186U publication Critical patent/CN204075186U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Carbon Steel Or Casting Steel Manufacturing (AREA)

Abstract

A kind of split type air brick core, the steel bushing comprising bottom opening and the metal cover board be fixedly installed on bottom steel bushing, air brick core body is arranged in the cavity that steel bushing and metal cover board form, and and seal with fire clay between steel bushing, between air brick core body and metal cover board, air chamber is set, the metal tracheae of metal cover board side welding is communicated with air chamber through metal cover board, multiple metalwork is welded on the opposite side of metal cover board, and be upward through the inside that air chamber inserts air brick core body, air brick core body and metal cover board are connected as one, sheathed metal nuts on described metal tracheae, and weld with the inner edge of metal nuts, one end of metal nuts is welded on metal cover board.The utility model, by the improvement to air brick core body and metal cover board structure, strengthens the bonding strength between air brick core body and metal cover board and between metal cover board and metal tracheae, thus facilitates the dismounting of air brick.

Description

A kind of split type air brick core
Technical field
The utility model relates to a kind of iron and steel metallurgical industry ladle bottom blowing air brick, especially relates to a kind of split type air brick core.
Background technology
In iron and steel metallurgical industry, by being blown into argon gas in molten steel, reaching and stirring the object of molten steel, can the evenly temperature of molten steel and chemical composition, promoting inclusion removal or control inclusion morphology, is the liquid steel refining mode that modern metallurgy industry generally adopts.
Air brick is the important functional element of ladle bottom blowing gas, and its service condition directly can affect the quality of steel.Air brick is roughly divided into two kinds of structures, and one is that air brick core and brick cup are prefabricated into an entirety, is integral air brick; Another kind is that air brick core and brick cup are separate, is combined in brick cup during use by air brick core, is split type air brick.Air brick core comprises steel bushing around air brick core body that refractory material makes, air brick core body, fill the parts such as the metal cover board that the fire clay in gap between air brick core body and steel bushing and steel bushing weld together and the metal tracheae be connected with metal cover board, between metal cover board and air brick core body, be provided with air chamber.During air brick work, gas enters air brick core from metal tracheae, is being blown in molten steel through air brick core.
Split air brick can carry out hot replacing, and use flexible, use cost is relatively low, can not be forced to roll off the production line because of air brick reason, can realize the maximization of ladle life, thus be widely used by iron and steel enterprise in use procedure.But its shortcoming easily smears uneven or quality problems because of air brick surface fire clay to make bleed-out probability increase; When the residual height of air brick is lower, after residual brick need being pulled down, then install new air brick, labor strength is larger; Require higher to workman's technical merit, when installing air brick, require that air brick core must be vertical with Ladle Bottom, air brick core center line must overlap with bellmouth center line in brick cup, to ensure being uniformly distributed of air brick wicking surface refractory wass.
During the air brick more renewed, usually following three kinds of sides can be adopted except remaining air brick core: (1) uses bale breaker, by air brick from immediate roof inside ladle out, this method is the method that current domestic contrast is conventional, and be characterized in convenient and swift, labor strength is low, shortcoming is that steel mill must have bale breaker, costly, and space hold position is large, and a lot of steel mill does not satisfy the requirements; (2) use beche or long rod to be up in bag by air brick, this substitute mode equipment investment is few, but operating process is complicated, and labor strength is large, and efficiency is low; (3) mechanical pullers is used, pulled out in ladle by air brick core, this method equipment is little and simple, and expense is low, the position that takes up room is little, thus remaining brick core used by some steel mills, but being pulled out of air brick core 100% can not be ensured, once can not pull out smoothly, manpower is then needed to dismantle brick core, meeting elapsed time is long, and labour intensity, loses the advantage of split air brick.
Utility model content
The purpose of this utility model is to provide a kind of split type air brick core, by the improvement to air brick core body construction and metal cover board structure, strengthen the connection between air brick core body and metal cover board and between metal cover board and metal tracheae, thus facilitate the dismounting of air brick.
For solving the problems of the technologies described above, the technical solution adopted in the utility model is: a kind of split type air brick core, its air brick core body is arranged in the cavity that is made up of steel bushing and metal cover board, seal with fire clay between air brick core body and steel bushing, metal cover board is fixedly installed on the bottom of steel bushing, and and between air brick core body, air chamber is set, metal tracheae is fixedly installed on the side of metal cover board, and be communicated with air chamber through metal cover board, metal cover board opposite side is welded with multiple metalwork, the bottom of described air brick core body arranges the connecting hole matched with described metalwork, metalwork is upward through air chamber and is plugged in connecting hole, air brick core body and metal cover board are connected as one, a sheathed metal nuts on described metal tracheae, and weld with the inner edge of metal nuts, one end of metal nuts is welded on metal cover board.
Described metalwork surface smear has fire clay.
Preferably, described metalwork is column, is set to 3 ~ 6, and it is highly 10 ~ 50mm.
Preferably, the height of described metal nuts is 10 ~ 30mm.
Compared with prior art, the utility model has following beneficial effect:
First, the metal nuts of the utility model by rotating metallic cover plate is fixedly installed, air brick core is made to occur to loosen in brick cup, thus be convenient to the dismounting of air brick, and set metal nuts strengthens the connection between metal tracheae and metal cover board, avoid causing between metal tracheae and metal cover board when rotating metallic nut rupturing, the metalwork simultaneously metal cover board arranged inserts air brick core body interior, air brick core body and metal cover board are held together, thus ensure that when rotating metal nuts, the steel bushing of air brick core body and outside is together with metal cover board synchronous axial system, avoid the disengaging of metal cover board and steel bushing and air brick core body,
The second, the metalwork in the utility model is non-rectilinear setting on metal cover board, and arranges around the center of metal cover board, can strengthen the firmness combined between air brick core body and metalwork further.
Therefore, the utility model is very easy to the dismounting of air brick, has both reduced the labour intensity of workman, again without the need to the input of professional equipment, reduces the production cost of enterprise.
Accompanying drawing explanation
Fig. 1 is structural representation of the present utility model.
Mark in figure: 1, air brick core body, 2, steel bushing, 3, air chamber, 4, alarming sign, 5, fire clay, 6, metalwork, 7, metal cover board, 8, metal nuts, 9, metal tracheae.
Detailed description of the invention
Below in conjunction with accompanying drawing, by detailed description of the invention, the utility model is further described.
As shown in the figure, a kind of split type air brick core, comprise air brick core body 1, be welded on the steel bushing 2 around air brick core body 1, metal cover board 7 bottom air brick core body 1, multiple metalwork 6 be welded on metal cover board 7, the metal tracheae 9 welded with metal cover board 7, wherein, seal with fire clay 5 between described steel bushing 2 and air brick core body 1, the bottom sides of steel bushing 2 is along being welded together by argon arc welding with metal base plate 7 edge, and air chamber 3 is set bottom metal cover board 7 with air brick core body 1, described metal tracheae 9 is communicated with air chamber 3 through metal cover board 7, bottom air brick core body 1, multiple connecting hole is set, described metalwork 6 surface smear fire clay 5 is also upward through air chamber 3 and inserts in corresponding connecting hole, air brick core body 1 and metal cover board 7 are connected as a single entity, a sheathed metal nuts 8 on metal tracheae 9, and weld with the inner edge of metal nuts 8, one end of metal nuts 8 is welded on metal cover board 7.
Described metalwork 6 is set to 5 stainless steel columns, and that to be arranged on metal cover board 7 center be the center of circle is circumferentially same, and it is highly 50mm, and the height of described metal nuts 8 is 30mm.
Described air brick core is also provided with alarming sign 4.
When air brick core needs to change, after needing the residual steel of air brick core working face, residue to clean out, clamp metal nuts 8 with instrument pincers to be rotated, air brick core is made to occur to loosen in brick cup, step up metal tracheae 9 drawing outward at use instrument, the object of removing air brick core can be reached.
In the process of removing air brick core, due to the effect on metalwork 6 and air brick core body 1 between connecting hole, air brick core body 1, steel bushing 2, metal cover board 7 are connected, thus avoid air brick core body 1 in the process of rotating metallic nut 8 and depart from metal cover board 7 because of twisting force, cause dismounting not thorough, simultaneously, the metal nuts 8 of welding with metal base plate 7 strengthens the connection between metal tracheae 9 and metal cover board 7, ensure that and can not disconnect between metal tracheae 9 and metal cover board 7.

Claims (4)

1. a split type air brick core, its air brick core body (1) is arranged on by the cavity that steel bushing (2) and metal cover board (7) are formed, seal with fire clay (5) between air brick core body (1) and steel bushing (2), metal cover board (7) is fixedly installed on the bottom of steel bushing (2), and and between air brick core body (1), air chamber (3) is set, metal tracheae (9) is fixedly installed on the side of metal cover board (7), and be communicated with air chamber (3) through metal cover board (7), metal cover board (7) opposite side is welded with multiple metalwork (6), it is characterized in that: the bottom of described air brick core body (1) arranges the connecting hole (61) matched with described metalwork (6), metalwork (6) is upward through air chamber (3) and is plugged in connecting hole (61), air brick core body (1) and metal cover board (7) are connected as one, the upper sheathed metal nuts (8) of described metal tracheae (9), and weld with the inner edge of metal nuts (8), one end of metal nuts (8) is welded on metal cover board (7).
2. the split type air brick core of one according to claim 1, is characterized in that: described metalwork (6) surface smear has fire clay (5).
3. the split type air brick core of one according to claim 1, is characterized in that: described metalwork (6), in column, is set to 3 ~ 6, and it is highly 10 ~ 50mm.
4. the split type air brick core of one according to claim 1, is characterized in that: the height of described metal nuts (8) is 10 ~ 30mm.
CN201420533635.3U 2014-09-17 2014-09-17 A kind of split type air brick core Expired - Fee Related CN204075186U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420533635.3U CN204075186U (en) 2014-09-17 2014-09-17 A kind of split type air brick core

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420533635.3U CN204075186U (en) 2014-09-17 2014-09-17 A kind of split type air brick core

Publications (1)

Publication Number Publication Date
CN204075186U true CN204075186U (en) 2015-01-07

Family

ID=52167951

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420533635.3U Expired - Fee Related CN204075186U (en) 2014-09-17 2014-09-17 A kind of split type air brick core

Country Status (1)

Country Link
CN (1) CN204075186U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104819645A (en) * 2015-04-21 2015-08-05 梧州市海邦科技有限公司 Split-type ventilating brick and installation method thereof
CN106893803A (en) * 2017-04-05 2017-06-27 海城市方宏耐火材料有限公司 A kind of air brick and preparation method with two-way inclination angle slit and safety early warning device
CN114908211A (en) * 2022-05-20 2022-08-16 山东钢铁股份有限公司 Electric furnace bottom blowing air brick and use method thereof

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104819645A (en) * 2015-04-21 2015-08-05 梧州市海邦科技有限公司 Split-type ventilating brick and installation method thereof
CN104819645B (en) * 2015-04-21 2016-08-24 陕西阳光雨生态科技有限公司 A kind of split type air brick and installation method thereof
CN106893803A (en) * 2017-04-05 2017-06-27 海城市方宏耐火材料有限公司 A kind of air brick and preparation method with two-way inclination angle slit and safety early warning device
CN106893803B (en) * 2017-04-05 2018-09-14 海城市方宏耐火材料有限公司 A kind of air brick and preparation method of band two-way inclination angle slit and safety early warning device
CN114908211A (en) * 2022-05-20 2022-08-16 山东钢铁股份有限公司 Electric furnace bottom blowing air brick and use method thereof

Similar Documents

Publication Publication Date Title
CN204075186U (en) A kind of split type air brick core
CN103540767A (en) Molten aluminum refining degassing and slag-removing device
KR20140001115U (en) Combined Furnace System for Fire Refining Red Impure Copper
CN103736985A (en) Steel ladle working lining and method for building slag line part of steel ladle working lining
CN102443685A (en) Method for building middle groove lining of vacuum chamber of vacuum circulating degassing furnace
CN208592256U (en) A kind of inner circle aligning tool of dip pipe steel gallbladder
CN103978197A (en) Device for cleaning aluminum slag in deep well
CN213537984U (en) Steelmaking electric furnace cover
CN202199767U (en) Tundish quick-changing tool of middle and large-scale continuous casting blanks
CN203778755U (en) Air brick capable of conducting heat transfer
CN201289301Y (en) Copple for medium-frequency induction furnace and mold for manufacturing the same
CN204770587U (en) Low pressure heat preservation stove
CN201008962Y (en) Combined anode copper casting mold
CN201205598Y (en) Air brick capable of drawing
CN211233948U (en) Argon blowing type electric furnace cover
CN207525265U (en) Tuyere medium jacket of blast furnace protectiveness provision for disengagement
CN203947123U (en) A kind of converter tap hole tube of being convenient to carry out guide-localization
CN204981943U (en) Dismantle device of anode furnace air brick
JP2013129863A (en) Tuyere structure in refining furnace and method for cooling tuyere brick in copper refining furnace
CN217290383U (en) Conical bottom blowing quick dismounting device for silicon-on-metal bag
CN204944168U (en) Casting smelting intermediate frequency furnace
CN204944169U (en) Casting smelting intermediate frequency furnace increase part
CN206956072U (en) The detachable collecting hood of blast furnace dedusting
CN203470889U (en) Special durable steel ladle
CN206986226U (en) One kind dismantles easy converter taphole assembly

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150107