CN204074355U - Mist cooling dust guard pollution abatement equipment - Google Patents

Mist cooling dust guard pollution abatement equipment Download PDF

Info

Publication number
CN204074355U
CN204074355U CN201420496286.2U CN201420496286U CN204074355U CN 204074355 U CN204074355 U CN 204074355U CN 201420496286 U CN201420496286 U CN 201420496286U CN 204074355 U CN204074355 U CN 204074355U
Authority
CN
China
Prior art keywords
water pipe
tower crane
longitudinal
dust guard
pollution abatement
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201420496286.2U
Other languages
Chinese (zh)
Inventor
关奇
洪德军
张旭东
杨士杰
于科
张爱军
李超
李蕾
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
First Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
China Construction Industrial and Energy Engineering Group Co Ltd
Original Assignee
First Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by First Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd filed Critical First Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Priority to CN201420496286.2U priority Critical patent/CN204074355U/en
Application granted granted Critical
Publication of CN204074355U publication Critical patent/CN204074355U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a kind of mist cooling dust guard pollution abatement equipment, comprise tower crane, tower crane tower body is provided with longitudinal water pipe, and tower crane arm is provided with horizontal water pipe, and horizontal water pipe arranges an atomizer every 2m; Tower body and arm junction are provided with swivel joint, and swivel joint connects longitudinal water pipe and horizontal water pipe respectively, and the length of longitudinal every section, water pipe is installed using the single-unit height of tower crane tower body as modulus, and longitudinal water pipe top is provided with buffering knuckle; Longitudinal water pipe lower end is connected with booster water pump, and booster water pump is connected with precipitation gathering-device.The beneficial effect of this programme can be learnt according to describing of such scheme, and structure is simple, reasonable in design, utilize the height of tower crane arm, water smoke can be made to cover the space of whole job site, temperature is reduced and is removed with airborne dust, reach the requirement of green construction.<b/>

Description

Mist cooling dust guard pollution abatement equipment
Technical field
The utility model relates to a kind of cooling, dust preventing equipment, particularly relates to a kind of mist cooling dust guard pollution abatement equipment.
Background technology
In summer, construction site is not only hot abnormal, and stirs up a cloud of dust.In order to job site cooling and control airborne dust, often need to sprinkle water to job site.But no matter current job site watering is giant jetting, or spraying apparatus spraying, and be mostly to carry out on ground, water droplet and water smoke do not reach higher position, cannot to the cooling of building higher position, and the airborne dust of higher spatial be fallen.
Utility model content
The utility model is for the deficiency existing for prior art, and it is simple, reasonable in design to provide a kind of structure, and water smoke can be made to cover the space of whole job site, makes temperature be reduced the mist cooling dust guard pollution abatement equipment obtaining removing with airborne dust.
To achieve these goals, the utility model provides a kind of mist cooling dust guard pollution abatement equipment, comprises tower crane, described tower crane tower body is provided with longitudinal water pipe, described tower crane arm is provided with horizontal water pipe, and described horizontal water pipe is provided with some shower nozzles, and described shower nozzle is atomizer;
Described tower body and arm junction are provided with swivel joint, and described swivel joint connects described longitudinal water pipe and horizontal water pipe respectively;
Described longitudinal water pipe lower end is connected with booster water pump;
Described booster water pump is electrically connected with switch combination, and described switch combination comprises time switch in parallel and hand switch, and described hand switch and time switch are in series with master switch;
Described booster water pump is connected with water storage device.
Wherein, the length of described longitudinal every section, water pipe is installed with the multiple of tower crane single-unit height.
Described longitudinal water pipe top is provided with buffering knuckle.
Described water storage device is precipitation gathering-device.
The beneficial effect of this programme can be learnt according to describing of such scheme, and structure is simple, reasonable in design, utilize the height of tower crane arm, water smoke can be made to cover the space of whole job site, temperature is reduced and is removed with airborne dust, reach the requirement of green construction.In order to coordinate the rotation of arm, so horizontal water pipe and longitudinal water pipe head adopt swivel joint.In order to ensure the pressure of the shower nozzle on arm, so adopt booster water pump.Time switch is set, at set intervals, will lowers the temperature by auto spraying, alleviate hand labor.Arrange hand switch, in order to airborne dust between is accidentally excessive or temperature enterprise is high, and the time switch time is not used then.Longitudinal length of pipe is installed with the multiple of tower crane single-unit height, and the height of spraying water pipe can be adjusted along with the height of tower crane.Longitudinal water pipe top is provided with buffering knuckle, with reduce booster water pump open send water time impact to swivel joint place.Water storage device is precipitation gathering-device, reaches water-saving object, reaches the requirement of green construction further.
Accompanying drawing explanation
Fig. 1 is the structural representation of the utility model detailed description of the invention;
Fig. 2 is the I position enlarged drawing of Fig. 1;
In figure, 1, tower body; 2, longitudinal water pipe; 3, arm; 4, horizontal water pipe; 5, atomizer; 6, swivel joint; 7, knuckle; 8, booster water pump; 9, precipitation gathering-device; 10, time switch; 11, hand switch; 12, master switch.
Detailed description of the invention
For the technical characterstic of this programme can be clearly demonstrated, below by detailed description of the invention, this programme is set forth.
As shown in Figure 1-2, the utility model is a kind of mist cooling dust guard pollution abatement equipment, comprises tower crane, and tower crane tower body 1 is provided with longitudinal water pipe 2, and tower crane arm 3 is provided with horizontal water pipe 4, and horizontal water pipe 4 arranges an atomizer 5 every 2m.
Tower body 1 and arm 3 junction are provided with swivel joint 6, and swivel joint 6 connects longitudinal water pipe 2 and horizontal water pipe 4 respectively, and longitudinal water pipe 2 length of every section is installed with the multiple of the single-unit height of tower crane tower body 1, and longitudinal water pipe 2 top is provided with buffering knuckle 7.
Longitudinal water pipe 2 lower end is connected with booster water pump 8, and booster water pump 8 is connected with precipitation gathering-device 9; Booster water pump 8 is electrically connected with switch combination, and switch combination comprises time switch 10 in parallel and hand switch 11, and hand switch 11 and time switch 10 are in series with master switch 12.
The utility model can pass through without the technical characteristic described or adopt existing techniques in realizing; do not repeat them here; certainly; above-mentioned explanation is not to restriction of the present utility model; the utility model is also not limited in above-mentioned citing; the change that those skilled in the art make in essential scope of the present utility model, remodeling, interpolation or replacement, also should belong to protection domain of the present utility model.

Claims (4)

1. a mist cooling dust guard pollution abatement equipment, is characterized in that, comprises tower crane, and described tower crane tower body is provided with longitudinal water pipe, and described tower crane arm is provided with horizontal water pipe, and described horizontal water pipe is provided with some shower nozzles, and described shower nozzle is atomizer;
Described tower body and arm junction are provided with swivel joint, and described swivel joint connects described longitudinal water pipe and horizontal water pipe respectively;
Described longitudinal water pipe lower end is connected with booster water pump;
Described booster water pump is electrically connected with switch combination, and described switch combination comprises time switch in parallel and hand switch, and described hand switch and time switch are in series with master switch;
Described booster water pump is connected with water storage device.
2. mist cooling dust guard pollution abatement equipment according to claim 1, is characterized in that, the length of described longitudinal every section, water pipe is installed with the multiple of tower crane single-unit height.
3. mist cooling dust guard pollution abatement equipment according to claim 1 and 2, is characterized in that, described longitudinal water pipe top is provided with buffering knuckle.
4. mist cooling dust guard pollution abatement equipment according to claim 1 and 2, is characterized in that, described water storage device is precipitation gathering-device.
CN201420496286.2U 2014-09-01 2014-09-01 Mist cooling dust guard pollution abatement equipment Active CN204074355U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420496286.2U CN204074355U (en) 2014-09-01 2014-09-01 Mist cooling dust guard pollution abatement equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420496286.2U CN204074355U (en) 2014-09-01 2014-09-01 Mist cooling dust guard pollution abatement equipment

Publications (1)

Publication Number Publication Date
CN204074355U true CN204074355U (en) 2015-01-07

Family

ID=52167121

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420496286.2U Active CN204074355U (en) 2014-09-01 2014-09-01 Mist cooling dust guard pollution abatement equipment

Country Status (1)

Country Link
CN (1) CN204074355U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105561709A (en) * 2016-02-22 2016-05-11 福建省闽南建筑工程有限公司 Spraying type dust removal device and method for indoor stirring of construction site
CN108037666A (en) * 2017-12-14 2018-05-15 中建三局第建设工程有限责任公司 A kind of dust from construction sites automatically controls Threshold Analysis and dynamic control method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105561709A (en) * 2016-02-22 2016-05-11 福建省闽南建筑工程有限公司 Spraying type dust removal device and method for indoor stirring of construction site
CN105561709B (en) * 2016-02-22 2017-10-20 福建省闽南建筑工程有限公司 For the atomizing dust arrester and its dust removal method stirred in the room of construction site
CN108037666A (en) * 2017-12-14 2018-05-15 中建三局第建设工程有限责任公司 A kind of dust from construction sites automatically controls Threshold Analysis and dynamic control method

Similar Documents

Publication Publication Date Title
CN203944254U (en) A kind of tower crane water injection system
CN204238146U (en) A kind of environmental protection guardrail with spray equipment
CN204842067U (en) Automobile frame priming paint intelligence paint spraying apparatus
CN202962972U (en) Device for clearing insulator at multiple angles
CN204074355U (en) Mist cooling dust guard pollution abatement equipment
CN103609392B (en) The sprinkler spray gun that a kind of pitch angle is adjustable
CN202512049U (en) Rainfall device
CN106594916A (en) Urban comprehensive dust removing, haze reducing and air conditioning system
CN204018108U (en) A kind of swing type fountain system
CN204018092U (en) The spraying application car of low regular facade metope in photocatalyst outdoor
CN203961231U (en) Photocatalyst basket-hanging spray equipment
CN203705292U (en) Portable insulator dirty loss coefficient researching device
CN204429547U (en) A kind of water wax sprayer
CN204027566U (en) A kind of solar assembly junction box laser locating apparatus
CN204426209U (en) Prevent the forestry spray equipment effectively utilizing rainwater of splash pedestrian
CN203570413U (en) Spraying cooling device for air-cooled diesel engine
CN204283480U (en) A kind of automatic control device for mine underground dustproof water screen
CN204356720U (en) A kind of guardrail with spraying function
CN204247443U (en) A kind of device removing the aerosol that spray paint produces
CN205206332U (en) Cooling dust fall sprays system for superelevation layer construction top mould
CN203420243U (en) Environment-protecting guard bar
CN204266149U (en) Novel isolation strip
CN204148074U (en) A kind of spray-painting plant of electric three-wheel
CN204543868U (en) Red infrared self-control device for reducing dust
CN204837678U (en) Ear of grain is drawn to high efficiency, fruit shower nozzle of expanding

Legal Events

Date Code Title Description
C14 Grant of patent or utility model