CN204023486U - Structure for providing downward discharge ecological flow for initial reservoir storage - Google Patents

Structure for providing downward discharge ecological flow for initial reservoir storage Download PDF

Info

Publication number
CN204023486U
CN204023486U CN201420411841.7U CN201420411841U CN204023486U CN 204023486 U CN204023486 U CN 204023486U CN 201420411841 U CN201420411841 U CN 201420411841U CN 204023486 U CN204023486 U CN 204023486U
Authority
CN
China
Prior art keywords
water
permanent
retaining structure
reservoir
ecological flow
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN201420411841.7U
Other languages
Chinese (zh)
Inventor
夏豪
魏浪
陈凡
张虎成
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Guiyang Engineering Corp Ltd
Original Assignee
PowerChina Guiyang Engineering Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Guiyang Engineering Corp Ltd filed Critical PowerChina Guiyang Engineering Corp Ltd
Priority to CN201420411841.7U priority Critical patent/CN204023486U/en
Application granted granted Critical
Publication of CN204023486U publication Critical patent/CN204023486U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Sewage (AREA)

Abstract

The utility model discloses a structure that is used for reservoir initial stage retaining to provide ecological flow of letting out down, including permanent retaining structure and set up in the water conservancy diversion outlet structure of permanent retaining structure top, be provided with permanent retaining structure in the permanent retaining structure, be provided with the temporary water and wave in storehouse district upstream at permanent retaining structure, the temporary water and wave in storehouse district below is provided with the conduit that supplies water to permanent retaining structure low reaches, pumping equipment is the suction pump, the temporary water and wave in storehouse district is built before the floodgate is let off to hold full water. The utility model builds a temporary water stage in the reservoir area before the diversion and water release building is braked, utilizes water conservancy to temporarily store water, and excess water overflows from the top of the water stage and lays a diversion pipeline from the water stage to the downstream of the dam to supply water to the downstream; the utility model discloses the technical risk is little, and is simple and easy, convenient and practical, low cost can extensively popularize and apply in hydraulic structure water conservancy diversion sluicing technical field.

Description

A kind ofly provide down the structure of letting out ecological flow for reservoir initial filling
Technical field
The utility model belongs to hydraulic structure water conservancy diversion sluicing technical field, and specifically relating to a kind ofly provides down the structure of letting out ecological flow for reservoir initial filling.
Background technology
In recent years along with China's improving constantly Hydraulic and Hydro-Power Engineering environmental protection requirement, letting out ecological flow problem under during reservoir engineering first filling is the emphasis that environmental protection authorities pay close attention to.Method conventional at present has following several:
(1) hole and electric butterfly valve are set on water conservancy diversion outlet structure escape works steel-slag sand, or open regulating gate aperture to let out the object of ecological flow under reaching by import steel-slag sand local.In view of electric butterfly valve does not have successful engineering experience, plate steel gate is opened and is easily made gate produce vibration under river channels, and technical risk is large, is difficult to the requirement meeting downstream ecology flow;
(2) during retaining, some water pumps are set before dam, from the dewatering orifice of drawing water before dam to the certain elevation of dam body.This scheme uses more in small reservoir, but some engineering dam height are large, exceeded the water lift lift of water pump, adopts the method to be difficult to meet downstream water demand requirement.
Utility model content
For solving the problem, the utility model provides a kind of and provides down the structure of letting out ecological flow for reservoir initial filling.Just can meet downstream water supply requirement without the need to local starting gate during making lower lock, implement convenient and easy.
The utility model is achieved by following technical solution.
A kind ofly provide down the structure of letting out ecological flow for reservoir initial filling, comprise permanent water retaining structure and be arranged at the water conservancy diversion outlet structure escape works above permanent water retaining structure, be provided with permanent outlet structure escape works in described permanent water retaining structure, be provided with interim water pond, reservoir area in permanent water retaining structure upstream.
Further, the aqueduct to permanent water retaining structure downstream water supply is provided with below the interim water in described reservoir area pond.
Further, interim Shui Po top, described reservoir area is provided with pumping equipment.
Further, described pumping equipment is suction pump.
Further, interim water pond, described reservoir area is built up before lock under water conservancy diversion outlet structure escape works, and stores full water.
Further, the interim water in described reservoir area pond is positioned at permanent water retaining structure upstream 100 ~ 500m scope.
The beneficial effects of the utility model are:
Have employed described in the utility model under let out ecological flow structure, when before lock under diversion structure, utilize the retaining of water pond.When after lock under water conservancy diversion outlet structure escape works, the a little aquaporins being from upstream to downstream are blocked by gate, when needs are to downstream water supply, lift gate is not needed again to discharge water, and only need to utilize conduit pipe to flow automatically or with pumping for water pump, by conduit pipe to downstream water supply, diversion or the flow that draws water determine according to downstream ecology uninterrupted.Adopt the utility model, the startup repeatedly avoiding gate is closed, and can reduce gate running cost, improves gate application life, guarantees that engineering is at the security and stability building period simultaneously.When permanent water retaining structure is retained to permanent outlet structure escape works elevation, change and provide downstream ecology flow by permanent outlet structure escape works.Realize artesian diversion owing to utilizing reservoir area interim water pond retaining or draw water to permanent water retaining structure downstream, avoiding that cause when adopting water pump not enough from pumping head before permanent water retaining structure dam cannot to the problem of downstream water supply.The utility model technical risk is little, simple for structure, convenient and practical, with low cost, can play the effect arrived very much, and can not leave over lower defect to permanent building self, can in hydraulic structure water conservancy diversion sluicing technical field wide popularization and application.
Accompanying drawing explanation
Fig. 1 is layout schematic diagram of the present utility model;
Fig. 2 is that structural profile of the present utility model arranges schematic diagram.
In figure: 1-water conservancy diversion outlet structure escape works, interim water pond, 2-reservoir area, the permanent water retaining structure of 3-, the permanent outlet structure escape works of 4-, 5-suction pump, 6-aqueduct.
Detailed description of the invention
The technical solution of the utility model is further described below in conjunction with accompanying drawing, but described in claimed scope is not limited to.
As shown in Figure 1 and Figure 2, described in the utility model 1, a kind ofly provide down the structure of letting out ecological flow for reservoir initial filling, the water conservancy diversion outlet structure escape works 1 comprising permanent water retaining structure 3 and be arranged at above permanent water retaining structure 3, described permanent water retaining structure 3 is provided with permanent outlet structure escape works 4, permanent water retaining structure 3 upstream is provided with interim water pond 2, reservoir area.
The aqueduct 6 to permanent water retaining structure 3 downstream water supply is provided with below interim water pond, described reservoir area 2.Aqueduct 6 for from reservoir area interim water pond 2 artesian diversion to permanent water retaining structure 3 downstream.
Top, interim water pond 2, described reservoir area is provided with pumping equipment.
Described pumping equipment is suction pump 5.Drawn water to permanent water retaining structure 3 downstream by suction pump 5.
Interim water pond 2, described reservoir area is built up before water conservancy diversion outlet structure escape works 1 time lock, and stores full water.
Interim water pond, described reservoir area 2 is positioned at upstream, permanent water retaining structure 3 upstream 100 ~ 500m scope.Make to flow automatically by aqueduct 6 or utilize water pump 5 to draw water to permanent water retaining structure 3 downstream.
Interim for reservoir area water pond 2 in use, before water conservancy diversion outlet structure escape works 1 time lock, is stored full water by the utility model in advance, and unnecessary interim water pond 2, Shui Zecong district top overflow, to meet reservoir filling requirement.After water conservancy diversion outlet structure escape works 1 time lock, utilize suction pump 5 to draw water interim water pond 2 from reservoir area, and cause permanent water retaining structure 3 downstream by aqueduct 6, realize to downstream water supply.
As can be seen from Figure 1, permanent outlet structure escape works 4 to be arranged within permanent water retaining structure 3 or outside, when permanent water retaining structure 3 is Rigid Dam, then permanent outlet structure escape works 4 are generally sand duct, flood discharge mesopore, diversion tunnel or overflow surface bay etc.; And when forever water retaining structure 3 is flexible dam, then permanent outlet structure escape works 4 are generally flood discharging tunnel, emptying tunnel, diversion tunnel or flood spillway.
When the utility model is implemented, interim water pond, reservoir area 2 is a short harmony dam, and be positioned at permanent water retaining structure 3 upstream certain distance, build up before diversion structure 1 time lock retaining and store full water, unnecessary water is then from the overflow of Shui Po top.After water conservancy diversion outlet structure escape works 1 time lock, the diversion passage of upstream toward downstream is blocked, and when needs supply certain water yield to downstream, utilizes aqueduct 6 from water pond artesian diversion or passes through pumping for water pump.Enter permanent water retaining structure reservoir area from the water of water pond 2 top overflow, reservoir starts retaining.When permanent water retaining structure 3 retains water to permanent outlet structure escape works 4 elevation, provide downstream ecology flow by these permanent outlet structure escape works 4.

Claims (6)

1. one kind provides down the structure of letting out ecological flow for reservoir initial filling, comprise permanent water retaining structure (3) and be arranged at the water conservancy diversion outlet structure escape works (1) above permanent water retaining structure (3), it is characterized in that: in described permanent water retaining structure (3), be provided with permanent outlet structure escape works (4), be provided with the interim water pond (2) in reservoir area in permanent water retaining structure (3) upstream.
2. according to claim 1ly a kind ofly provide down the structure of letting out ecological flow for reservoir initial filling, it is characterized in that: below, interim water pond, described reservoir area (2) is provided with the aqueduct (6) to permanent water retaining structure (3) downstream water supply.
3. according to claim 1ly a kind ofly provide down the structure of letting out ecological flow for reservoir initial filling, it is characterized in that: interim water pond (2) top, described reservoir area is provided with pumping equipment.
4. according to claim 3ly a kind ofly provide down the structure of letting out ecological flow for reservoir initial filling, it is characterized in that: described pumping equipment is suction pump (5).
5. according to claim 1ly a kind ofly provide down the structure of letting out ecological flow for reservoir initial filling, it is characterized in that: the interim water pond (2) in described reservoir area is built up before lock under water conservancy diversion outlet structure escape works (1), and stores full water.
6. according to claim 1ly a kind ofly provide down the structure of letting out ecological flow for reservoir initial filling, it is characterized in that: interim water pond, described reservoir area (2) is positioned at permanent water retaining structure (3) upstream 100 ~ 500m scope.
CN201420411841.7U 2014-07-24 2014-07-24 Structure for providing downward discharge ecological flow for initial reservoir storage Expired - Lifetime CN204023486U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420411841.7U CN204023486U (en) 2014-07-24 2014-07-24 Structure for providing downward discharge ecological flow for initial reservoir storage

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420411841.7U CN204023486U (en) 2014-07-24 2014-07-24 Structure for providing downward discharge ecological flow for initial reservoir storage

Publications (1)

Publication Number Publication Date
CN204023486U true CN204023486U (en) 2014-12-17

Family

ID=52063373

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420411841.7U Expired - Lifetime CN204023486U (en) 2014-07-24 2014-07-24 Structure for providing downward discharge ecological flow for initial reservoir storage

Country Status (1)

Country Link
CN (1) CN204023486U (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105002863A (en) * 2015-04-03 2015-10-28 中国电建集团贵阳勘测设计研究院有限公司 Ecological flow guaranteeing method based on downstream reservoir scheduling
CN105155488A (en) * 2015-07-03 2015-12-16 中国电建集团贵阳勘测设计研究院有限公司 Arrangement mode and structure of small ecological flow unit of underground powerhouse of hydropower station
CN109555090A (en) * 2019-01-15 2019-04-02 中国电建集团华东勘测设计研究院有限公司 Ecological flow for hydroenergy storage station is released facility and implementation method
CN111241709A (en) * 2019-04-10 2020-06-05 中国电建集团贵阳勘测设计研究院有限公司 Multistage emptying hole simulation debugging system and simulation debugging method
CN113481928A (en) * 2021-07-27 2021-10-08 中国三峡建工(集团)有限公司 High-water-level water storage method for construction period of high-dam large reservoir and at initial operation stage
CN117646404A (en) * 2024-01-29 2024-03-05 陕西省水利电力勘测设计研究院 System and method for discharging ecological flow in whole process of hydraulic junction engineering

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105002863A (en) * 2015-04-03 2015-10-28 中国电建集团贵阳勘测设计研究院有限公司 Ecological flow guaranteeing method based on downstream reservoir scheduling
CN105155488A (en) * 2015-07-03 2015-12-16 中国电建集团贵阳勘测设计研究院有限公司 Arrangement mode and structure of small ecological flow unit of underground powerhouse of hydropower station
CN109555090A (en) * 2019-01-15 2019-04-02 中国电建集团华东勘测设计研究院有限公司 Ecological flow for hydroenergy storage station is released facility and implementation method
CN109555090B (en) * 2019-01-15 2024-04-09 中国电建集团华东勘测设计研究院有限公司 Ecological flow discharge facility for pumped storage power station and implementation method
CN111241709A (en) * 2019-04-10 2020-06-05 中国电建集团贵阳勘测设计研究院有限公司 Multistage emptying hole simulation debugging system and simulation debugging method
CN113481928A (en) * 2021-07-27 2021-10-08 中国三峡建工(集团)有限公司 High-water-level water storage method for construction period of high-dam large reservoir and at initial operation stage
CN117646404A (en) * 2024-01-29 2024-03-05 陕西省水利电力勘测设计研究院 System and method for discharging ecological flow in whole process of hydraulic junction engineering
CN117646404B (en) * 2024-01-29 2024-05-03 陕西省水利电力勘测设计研究院 System and method for discharging ecological flow in whole process of hydraulic junction engineering

Similar Documents

Publication Publication Date Title
CN204023486U (en) Structure for providing downward discharge ecological flow for initial reservoir storage
CN204811321U (en) Solar energy siphon suction pipe pump
CN203594007U (en) Power station hub downstream water supply structure
CN106930252A (en) A kind of Novel flush storage station water system
CN105155484A (en) Method for reconstructing temporary diversion tunnel into permanent flood discharge facility
CN206245384U (en) A kind of energy-conserving and environment-protective water conservancy irrigation device with rainwater-collecting and water filtration function
CN104452685B (en) A kind of classification buoyancy lift type checkdam
CN206206294U (en) A kind of the siphon priming device
CN205012292U (en) Water conservancy regulation and control gate
CN204023523U (en) Internal gate valve chamber structure of dam body
CN202187327U (en) Water level controller for siphon drainage pipe
CN204511793U (en) A kind of low water head energy collecting device
CN104005448B (en) A kind of Wall in Plain Reservoir intake structure
CN204377590U (en) A kind of surge flow irrigation system experimental device
CN210482455U (en) Pump station diversion and drainage combined overpass culvert gate
CN108589628A (en) A kind of method and device for flood retarding project decentralization ecological water
CN208533449U (en) A kind of device for flood retarding project decentralization ecological water
CN204311415U (en) A kind of classification buoyancy lift type checkdam
CN102912761B (en) Wind force dredging method for river
CN203947523U (en) A kind of Wall in Plain Reservoir intake structure
CN203080591U (en) Mountain land water accumulation integrated-irrigation system
CN209194485U (en) Diversion tunnel structure
CN206681070U (en) A kind of multi-functional discharge pump works
CN203569549U (en) Inspection well flow limiting device for buried pipe drainage
CN206667363U (en) A kind of submergence type culvert water inlet structure

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20141217