CN203891778U - Remote conveying, cooling and dust catching device for coal bed drilling ice particles - Google Patents

Remote conveying, cooling and dust catching device for coal bed drilling ice particles Download PDF

Info

Publication number
CN203891778U
CN203891778U CN201420299664.8U CN201420299664U CN203891778U CN 203891778 U CN203891778 U CN 203891778U CN 201420299664 U CN201420299664 U CN 201420299664U CN 203891778 U CN203891778 U CN 203891778U
Authority
CN
China
Prior art keywords
ice particle
drilling
drilling rod
ice
gas
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201420299664.8U
Other languages
Chinese (zh)
Inventor
王永龙
王振锋
孙玉宁
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Henan University of Technology
Original Assignee
Henan University of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Henan University of Technology filed Critical Henan University of Technology
Priority to CN201420299664.8U priority Critical patent/CN203891778U/en
Application granted granted Critical
Publication of CN203891778U publication Critical patent/CN203891778U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Earth Drilling (AREA)

Abstract

The utility model discloses a remote conveying, cooling and dust catching device for coal bed drilling ice particles. The remote conveying, cooling and dust catching device for the coal bed drilling ice particles comprises an ice particle storage box, an ice particle injector, a gas-solid coupling box, a drilling rod and a rotational flow drill bit. The ice particle injector is installed between the ice particle storage box and the gas-solid coupling box, the gas-solid coupling box is connected with the drilling rod through a drill tail air supplying device, and the rotational flow drill bit is installed at the front end of the drilling rod. The remote conveying, cooling and dust catching device for the coal bed drilling ice particles is novel in design. During moving, the ice particles make contact with the drilling rod with the surface temperature rising and rub with drilling cuttings particles, then the ice particles fuse continuously, the drilling rod is cooled, and at the same time, fine coal dust is caught.

Description

Drilling in coal ice particle is carried cooling dust trapping device at a distance
Technical field
The utility model belongs to the projecting coal bed mash gas pumping drilling safe construction in colliery, dedusting environment friendly technical field, is specifically related to drilling in coal ice particle and carries at a distance cooling dust trapping device.
Background technology
Gas pumping is the prerequisite of projecting coal bed safe working, gas pumping generally comprises the sport technique segments such as boring, sealing of hole and connection hole, wherein the most key with drilling construction, drilling depth has determined scope and the efficiency of gas pumping, projecting coal bed drilling construction amount is huge, the 0.1m ~ 0.4m boring of need constructing of 1 ton of coal of every production.Creep into for projecting coal bed, conventionally take the defeated slag of pneumatic conveying mode, with respect to hydraulic slag discharging mode, deslagging efficiency is high, presses wind little to the impact force of hole wall, survivable hole wall.For pneumatic conveying mode drilling process, job site dust is serious, and in the time occurring stopping up in boring, drill bit, drilling rod easily generate heat, and frictional heat is assembled, and easily occurs drilling gas burning, in the time of coal imperfect combustion, produces CO, is prone to CO accident.Drill bit, drilling rod cooling and dedusting are two large technical barriers of projecting coal bed drilling construction, at present, engineers and technicians arrange atomising device conventionally between for airduct and rig, the distinguished and admirable atomized drop that carries enters foot of hole along boring cavity, realize cooling and catch dirt, limited by droplet size and transmission range, it is unsatisfactory that dirt effect is caught in atomized drop cooling.Therefore, creep into cooling, dust removal problem for soft seam, be badly in need of a kind of new process and overcome the defect that conventional atomized drop wet type drilling process exists.
Utility model content
The utility model is in order to solve weak point of the prior art, provide a kind of drilling in coal ice particle to carry at a distance cooling dust trapping device, this process system carries by conventional liquid state the solid ice particle transport mode that is converted to by catching dirt medium, increase transmission range, solve in conventional atomized drop wet type drilling process because drop fed distance is short and unmanageable technical problem, simultaneously, ice particle be molten into endothermic process, drilling tool in hole in the condition of high temperature is played to cooling effect, reduce that drilling tool continuous high temperature in hole causes strength decreased and the probability that destroys, being conducive to the safe and efficient of projecting coal bed drilling construction creeps into.
For solving the problems of the technologies described above, the utility model adopts following technical scheme: a kind of soft seam creeps into ice particle and carries at a distance cooling dust trapping device, comprise ice particle storage bin, ice particle sprayer, Gas-solid Coupling case, drilling rod, eddy flow drill bit, it is characterized in that: described ice particle sprayer is arranged between ice particle storage bin and Gas-solid Coupling case, Gas-solid Coupling case is connected with drilling rod by boring tail air feed device, and eddy flow drill bit is arranged on the front end of drilling rod.
Described ice particle sprayer is made up of air motor, agitator tank, ice particle storage bin interface, helix transporting device, intervalve, tapered injection emitter and control valve, and ice particle sprayer is connected with ice particle storage bin through ice particle storage bin interface.
Described Gas-solid Coupling case is made up of blast connection, particle sprayer joint, blending bin, brill tail joint, blast connection is connected with supplying airduct by sebific duct, ice particle sprayer joint is connected with ice particle sprayer, bores tail joint and is taken over brill tail air feed device and be connected by rigid connecting.
Described eddy flow drill bit is made up of joint, arc eddy flow chamber, knife rest, carbide chip, and eddy flow drill bit is connected and is arranged on the front end of drilling rod with drilling rod by joint.
A kind of drilling in coal ice particle is carried cooling dust trapping device at a distance, comprises the following steps:
1.. complete for airduct, ice particle storage bin, ice particle sprayer, Gas-solid Coupling case, rig, drilling rod and drill bit and install and be connected, the drilling construction initial stage, only start air feed system, distinguished and admirablely take over, bore tail air feed device and drilling rod cavity is sent into foot of hole along Gas-solid Coupling case, rigid connecting, realize rotary drilling;
2.. drilling construction exceedes after 5m, start air motor, the helix transporting device of ice particle sprayer is delivered to tapered injection emitter by ice particle through intervalve, enter Gas-solid Coupling case, gas carries out just mixing at Gas-solid Coupling case with ice particle, takes over through boring tail air feed device and enters drilling rod inner chamber along rigid connecting, and Gas-solid Coupling body arrives eddy flow drill bit place, in arc eddy flow chamber, carry out secondary mixing, at the bottom of discharging arrival hole by eddy flow drill bit;
3.. gas, ice particle and drilling cuttings mixture discharge along the slagging channel between drill hole wall and drilling rod, affected by eddy flow drill bit, drilling rod temperature, the heat absorption of ice particle is melted, evaporation, in slagging channel, form gaseous state, liquid state, solid-state three-phase state, under the distinguished and admirable effect of high speed, further broken by the liquefy water droplet that forms of ice particle, in course of conveying, realize the cooling of drilling rod and catch drilling cuttings micronic dust.
Brief description of the drawings
Fig. 1 is the structural representation of the utility model duty;
Fig. 2 is the utility model ice particle sprayer structure chart;
Fig. 3 is the structure chart of the utility model Gas-solid Coupling case;
Fig. 4 is the structure chart of the utility model eddy flow drill bit;
When Fig. 5 is the utility model enforcement, dirt principle schematic is caught in cooling.
Detailed description of the invention
As shown in Figure 1 to 4, a kind of drilling in coal ice of the utility model particle is carried cooling dust trapping device at a distance, ice particle storage bin 3, ice particle sprayer 4, Gas-solid Coupling case 5, drilling rod 8, eddy flow drill bit 11, described ice particle sprayer 4 is arranged between ice particle storage bin 3 and Gas-solid Coupling case 5, Gas-solid Coupling case 5 is connected with drilling rod 8 by boring tail air feed device 7, and eddy flow drill bit 11 is arranged on the front end of drilling rod 8.Ice particle sprayer 4 by air motor 401, agitator tank 402, ice particle storage bin interface 403, revolve conveying device 404, intervalve 405, tapered injection emitter 406 and control valve 407 and form, ice particle sprayer 4 is connected with ice particle storage bin 3 through ice particle storage bin interface 403.Gas-solid Coupling case 5 is made up of blast connection 501, ice particle sprayer joint 502, blending bin 503, brill tail joint 504, blast connection 501 is connected with supplying airduct 1 by sebific duct 2, ice particle sprayer joint 502 is connected with ice particle sprayer 4, and brill tail joint 504 is taken over 6 by rigid connecting and is connected with brill tail air feed device 7.Eddy flow drill bit 11 is made up of joint 1101, arc eddy flow chamber 1102, knife rest 1103,1104 of carbide cutter tools, and eddy flow drill bit 11 is connected and is arranged on the front end of drilling rod 8 by joint 1101 and drilling rod 8.
A kind of drilling in coal ice particle is carried cooling dust trapping device at a distance, and using method comprises the following steps:
Complete for airduct 1, ice particle storage bin 3, ice particle sprayer 4, Gas-solid Coupling case 5, rig 9, drilling rod 8 and drill bit 11 and install and be connected, the drilling construction initial stage, only start air feed system, distinguished and admirablely take over 6, bore tail air feed device 7 and drilling rod 8 cavitys 13 are sent into foot of hole along Gas-solid Coupling case 5, rigid connecting, realize rotary drilling;
Drilling construction exceedes after 5m, start air motor 401, the helix transporting device 404 of ice particle sprayer 4 is delivered to tapered injection emitter 406 by ice particle through intervalve 405, enter Gas-solid Coupling case 5, gas mixes at Gas-solid Coupling case 5 for the first time with ice particle, takes over 6 enter drilling rod 8 inner chambers through boring tail air feed device 7 along rigid connecting, and Gas-solid Coupling body arrives eddy flow drill bit 11 places, in arc eddy flow chamber 1102, carry out secondary mixing, at the bottom of discharging arrival hole by eddy flow drill bit 11;
Gas, ice particle and drilling cuttings mixture discharge along the slagging channel 14 between drill hole wall 12 and drilling rod 8, affected by eddy flow drill bit 11, drilling rod 8 temperature, the heat absorption of ice particle is melted, evaporation, at the interior formation gaseous state of slagging channel 14, liquid state, solid-state three-phase state, under the distinguished and admirable effect of high speed, further broken by the liquefy water droplet that forms of ice particle, in course of conveying, realize the cooling of drilling rod and catch drilling cuttings micronic dust.
Introducing the utility model below carries cooling to catch dirt principle at a distance:
With reference to Fig. 5, gas mixes at Gas-solid Coupling case 5 for the first time with ice particle, the Gas-solid Coupling body forming is entered by drilling rod 8 cavitys 13, while arriving drill bit place, in arc eddy flow chamber 1102, carry out secondary mixing, in arc eddy flow chamber, gas and ice particle form vortex phenomenon, ice particle whirling motion phenomenon is obvious, piles up at drill bit place thereby reduce ice particle, is conducive to gas, ice particle mixes at the bottom of hole more uniformly with drilling cuttings.Gas, ice particle and drilling cuttings mixture discharge along the slagging channel 14 between drill hole wall 12 and drilling rod 8, from Di Dao hole, hole, can be divided into three phases:
Stage I: at foot of hole, drill bit breaks coal, drilling rod rotation and the friction of holing, cause the temperature at drill bit place the highest, at the bottom of ice particle arrives hole time, under eddy flow drill bit and drilling rod hot conditions, the heat absorption of part ice particle is melted, evaporation, foot of hole space medium is gaseous state, liquid state, solid-state three-phase state, wherein solid-state drilling cuttings and the ice particle not melting of comprising, the thawing of ice particle is played and is reduced drill bit and drilling rod temperature action, meanwhile, the water droplet of evaporating state can catch the effect of drilling cuttings micronic dust, has completed the first stage depositing dust effect at coal dust source place at the bottom of hole;
Stage II: outside along drill bit, drilling rod temperature has reduction trend, air-flow carries the ice particle, drilling cuttings and the drop that do not melt and carries outside hole, ice particle is in migration process, and part ice particle continues to melt, simultaneously, under the distinguished and admirable effect of high speed, further broken by the liquefy drop that forms of ice particle, in this stage, drilling cuttings micronic dust is further by drop particle capture;
Stage III: enter stage III, drilling rod surface temperature is in stable state, and meanwhile, ice particle, drilling cuttings and droplets mixing body are outwards carried with stable state under airflow function, the ratio that unit long drilled holes ice particle melts is stable, and drilling cuttings micronic dust is captured gradually in migration process.

Claims (4)

1. a drilling in coal ice particle is carried cooling dust trapping device at a distance, comprise ice particle storage bin, ice particle sprayer, Gas-solid Coupling case, drilling rod, eddy flow drill bit, it is characterized in that: described ice particle sprayer is arranged between ice particle storage bin and Gas-solid Coupling case, Gas-solid Coupling case is connected with drilling rod by boring tail air feed device, and eddy flow drill bit is arranged on the front end of drilling rod.
2. a kind of drilling in coal ice particle according to claim 1 is carried cooling dust trapping device at a distance, it is characterized in that: described ice particle sprayer is made up of air motor, agitator tank, ice particle storage bin interface, helix transporting device, intervalve, tapered injection emitter and control valve, and ice particle sprayer is connected with ice particle storage bin through ice particle storage bin interface.
3. a kind of drilling in coal ice particle according to claim 1 is carried cooling dust trapping device at a distance, it is characterized in that: described Gas-solid Coupling case is made up of blast connection, ice particle sprayer joint, blending bin, brill tail joint, blast connection is connected with supplying airduct by sebific duct, particle sprayer joint is connected with ice particle sprayer, bores tail joint and is taken over brill tail air feed device and be connected by rigid connecting.
4. a kind of drilling in coal ice particle according to claim 1 is carried cooling dust trapping device at a distance, it is characterized in that: described eddy flow drill bit is made up of joint, arc eddy flow chamber, knife rest, carbide chip, eddy flow drill bit is connected and is arranged on the front end of drilling rod with drilling rod by joint.
CN201420299664.8U 2014-06-09 2014-06-09 Remote conveying, cooling and dust catching device for coal bed drilling ice particles Expired - Fee Related CN203891778U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420299664.8U CN203891778U (en) 2014-06-09 2014-06-09 Remote conveying, cooling and dust catching device for coal bed drilling ice particles

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420299664.8U CN203891778U (en) 2014-06-09 2014-06-09 Remote conveying, cooling and dust catching device for coal bed drilling ice particles

Publications (1)

Publication Number Publication Date
CN203891778U true CN203891778U (en) 2014-10-22

Family

ID=51718194

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420299664.8U Expired - Fee Related CN203891778U (en) 2014-06-09 2014-06-09 Remote conveying, cooling and dust catching device for coal bed drilling ice particles

Country Status (1)

Country Link
CN (1) CN203891778U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104018784A (en) * 2014-06-04 2014-09-03 河南理工大学 Cooling and dust catching device for remotely conveying coal bed drilling ice particles and application method thereof

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104018784A (en) * 2014-06-04 2014-09-03 河南理工大学 Cooling and dust catching device for remotely conveying coal bed drilling ice particles and application method thereof
CN104018784B (en) * 2014-06-04 2017-02-15 河南理工大学 Cooling and dust catching device for remotely conveying coal bed drilling ice particles and application method thereof

Similar Documents

Publication Publication Date Title
CN103352718B (en) Fully-sealed wind power slagging gas-drainage deep well drilling system and method
CN203268734U (en) Conveying device used for material discharging of stock bin
CN104018784B (en) Cooling and dust catching device for remotely conveying coal bed drilling ice particles and application method thereof
CN103147708A (en) Through type down hole hammer reverse circulation drilling dust collection device
CN106869834A (en) A kind of coal bed drilling drilling hole dust collector device
CN109207659A (en) A kind of granulating device and heat recovery method of liquid slag
CN102042026A (en) Dense shallow hole dust catcher for coal mines
CN103757155A (en) Coke dry quenching water mist granulation device
CN201891427U (en) Dust removal system for pneumatic dry drilling
CN203891778U (en) Remote conveying, cooling and dust catching device for coal bed drilling ice particles
CN103161415B (en) Negative pressure drilling system
CN203296725U (en) Through type DTH hammer reverse circulation drilling dust collecting device
CN206338031U (en) A kind of underground self-advancing type high-pressure abrasive material gas jet drilling prosthetic device
CN104453721A (en) Anti-sloughing hole reverse circulation sampling bit
CN100582433C (en) Hole bottom annular spacing strong suction device of through type down-the-hole hammer
CN101319599B (en) Side suction type reverse circulation drilling bit
CN203050511U (en) Whirlwind type jet drill bit
CN103075105B (en) Cyclone type jet bit
CN114165177B (en) Low-temperature air composite drilling and orifice negative pressure dust removal system
CN203271644U (en) Negative pressure drilling system for preventing transfinite gas
CN101864895A (en) Positive-circulation drilling and dedusting technique of chamber down-hole hammer and double-wall pipe
CN213711045U (en) Inert gas drilling and deslagging equipment
CN112228068B (en) Inert gas drilling and deslagging equipment and method
CN203066910U (en) Negative-pressure drilling system
CN203334951U (en) Down hole hammer

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20141022

Termination date: 20170609

CF01 Termination of patent right due to non-payment of annual fee