CN203889493U - Elevator speed governor and door opener production line - Google Patents

Elevator speed governor and door opener production line Download PDF

Info

Publication number
CN203889493U
CN203889493U CN201420292157.1U CN201420292157U CN203889493U CN 203889493 U CN203889493 U CN 203889493U CN 201420292157 U CN201420292157 U CN 201420292157U CN 203889493 U CN203889493 U CN 203889493U
Authority
CN
China
Prior art keywords
door opener
normal open
erecting bed
open switch
manufacturing line
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn - After Issue
Application number
CN201420292157.1U
Other languages
Chinese (zh)
Inventor
李慧
嵇叶红
陶德志
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
HUZHOU HUAAO ELEVATOR CO., LTD.
Original Assignee
Huzhou Hua Ao Elevator Science And Technology Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Huzhou Hua Ao Elevator Science And Technology Ltd filed Critical Huzhou Hua Ao Elevator Science And Technology Ltd
Priority to CN201420292157.1U priority Critical patent/CN203889493U/en
Application granted granted Critical
Publication of CN203889493U publication Critical patent/CN203889493U/en
Withdrawn - After Issue legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses an elevator speed governor and door opener production line. The elevator speed governor and door opener production line comprises a support, a motor and a conveying belt. The conveying belt is mounted on the support. The motor is connected with the conveying belt and supplies power to the conveying belt for movement. The conveying belt comprises crawler belt sheets. Each crawler belt sheet is provided with a pull and push channel. A connecting rod is arranged in each pull and push channel. The elevator speed governor and door opener production line further comprises mounting tables. Each mounting table is detachably mounted on the corresponding connecting rod. The upper surfaces of the mounting tables and the upper surfaces of the crawler belt sheets are in the same horizontal plane. According to the elevator speed governor and door opener production line, the pull and push channels are formed in the crawler belt sheets, the connecting rods are arranged in the pull and push channels, and the connecting rods can be pulled out of the pull and push channels; when elevator speed governors are produced, only the production line composed of the crawler belt sheets is needed; when door openers of elevators are produced, the connecting rods are pulled out of the pull and push channels, the mounting tables are fixed to the connecting rods, and first fixed bases on the crawler belt sheets and second fixed bases on the mounting tables simultaneously act on the door openers to be machined; consequently, space waste is reduced, and the cost is lowered.

Description

The manufacturing line of elevator governor and door opener
Technical field
The utility model relates to manufacturing line, particularly the manufacturing line of a kind of elevator governor and door opener.
Background technology
Manufacturing line is called again fitting line, is a kind of industrial mode of production, refers to the only absorbed work of processing some fragments of each production unit, to increase work efficiency and output; Substantially can be divided into according to the mode of movement of manufacturing line: this seven classes manufacturing line of belt assembly belt, plate chain line, double-speed chain, plug-in unit line, guipure line, suspension line and cylinder manufacturing line.
Elevator governor and door opener are because volume differs larger at present, and door opener is more much bigger than the volume of velocity limiter, therefore, has to use the manufacturing line of two different sizes.
Utility model content
The purpose of this utility model is, the manufacturing line of a kind of elevator governor and door opener is provided, and two manufacturing lines are integrated into a manufacturing line, in the time that needs are produced velocity limiter, adopts the manufacturing line being made up of shoe; In the time need to producing the door opener of elevator, pipe link is extracted out from pumping in passage, erecting bed is arranged on pipe link, the upper surface of erecting bed and the upper surface of shoe are in same level, thereby widen the width of manufacturing line, can be used in the door opener of producing elevator.
The technical solution of the utility model: the manufacturing line of a kind of elevator governor and door opener, comprise support, motor and belt conveyor, belt conveyor is rack-mount, motor is connected with belt conveyor, and the movement that motor is belt conveyor provides power, and described belt conveyor comprises shoe, shoe is provided with pumps passage, pump in passage and be provided with pipe link, also comprise erecting bed, erecting bed detouchable is arranged on pipe link; Shoe is provided with the first permanent seat, and erecting bed is provided with the second permanent seat, and the upper surface of erecting bed and the upper surface of shoe are in same level.According to the needs of assembling, in the time need to producing the door opener of elevator, pipe link is extracted out, erecting bed is arranged on pipe link, just can widen the width of manufacturing line, thereby can amass larger door opening machine for elevator for assembly, and need not again purchase new manufacturing line, thereby provide cost savings; If need to produce the velocity limiter of elevator, just erecting bed is unloaded from pipe link, pipe link is pushed into pumping passage, the manufacturing line being made up of shoe just can be used in the velocity limiter of producing elevator, thereby has saved space.For the production of product provides diversified function, and provide cost savings and space.
The manufacturing line of above-mentioned elevator governor and door opener, described pipe link is provided with at least two knock holees, the bottom of erecting bed is provided with registration mast, and the quantity of registration mast equates with the quantity of knock hole, and erecting bed is matched and is fixed on pipe link with knock hole by registration mast.
In the manufacturing line of above-mentioned elevator governor and door opener, connecting rod comprises strut bar and push rod, and knock hole is arranged on strut bar, and one end of strut bar is connected with push rod, and erecting bed is fastened between shoe and push rod.The height of push rod is higher than the height of strut bar, and push rod, strut bar and shoe form the draw-in groove of U-shaped, and erecting bed is fastened in U-shaped draw-in groove, thereby erecting bed is firmly fixed on pipe link.
In the manufacturing line of above-mentioned elevator governor and door opener, the width of erecting bed is identical with the width of shoe.Two adjacent pipe links, from pumping in passage and extract out accordingly, are installed erecting bed on two pipe links, and two erecting beds are closely connected, and multiple adjacent erecting beds have just been widened the width of manufacturing line.
In the manufacturing line of above-mentioned elevator governor and door opener, described motor is stepping motor, also comprises switch circuit, and switch circuit is electrically connected with stepping motor, for the startup of control step motor with close;
Switch circuit comprises start-up circuit and shut-off circuit, start-up circuit comprises the first normal open switch, the first AC contactor and the first relay, first normal open switch one end is electrically connected the other end and is electrically connected with the first relay with power supply, the first AC contactor and the first normal open switch parallel connection, stepping motor one end is electrically connected with the first relay, and the other end is connected with zero line.
In the manufacturing line of above-mentioned elevator governor and door opener, shut-off circuit comprises the second normal open switch, time relay, the second AC contactor and the second relay; The second normal open switch is connected with time relay, and the other end of the second normal open switch is electrically connected with power supply, and the other end of time relay is connected with zero line; The second AC contactor is in parallel with the second normal open switch, and the second relay is in parallel with time relay.
In the manufacturing line of above-mentioned elevator governor and door opener, also comprise divider resistance and normally closed switch, divider resistance and normally closed switch are arranged between the first normal open switch and the second normal open switch and power supply, divider resistance and normally closed switch series connection, the other end of divider resistance is electrically connected with power supply, and the other end of normally closed switch is electrically connected with the first normal open switch and the second normal open switch.
Compared with prior art, the utility model is pumped passage by offering in shoe, pumps in passage pipe link is set, and pipe link can be extracted out from pumping in passage, in the time producing elevator governor, and the manufacturing line that only need to be formed by shoe; In the time producing the door opener of elevator, pipe link is extracted out from pumping in passage, erecting bed is fixed on pipe link, the second permanent seat on the first permanent seat and erecting bed on shoe acts on door opener to be processed simultaneously, realize the integration of two manufacturing lines, save space, reduced cost.
Brief description of the drawings
Fig. 1 is the structural representation of a kind of embodiment of the present utility model;
Fig. 2 is the matching relationship schematic diagram of shoe and erecting bed;
Fig. 3 is the structural representation of erecting bed;
Fig. 4 is the structural representation of pipe link;
Fig. 5 is the annexation schematic diagram of a kind of embodiment of switch circuit.
Being labeled as in accompanying drawing: 1-control panel, 2-motor, 3-the first permanent seat, 4-belt conveyor, 5-shoe, 6-registration mast, 7-erecting bed, 8-strut bar, 9-support, 10-pipe link, 11-the second permanent seat, 12-push rod, 13-start-up circuit, 14-shut-off circuit, 15-pumps passage, 16-knock hole, R1-divider resistance, K1-normally closed switch, SB1-the first normal open switch, KA1-the first AC contactor, KM1-the first relay, m-stepping motor, SB2-the second normal open switch, KA2-the second AC contactor, KT1-time relay, KM2-the second relay, QS1-the first knife switch, QS2-the second knife switch.
Detailed description of the invention
Below in conjunction with drawings and Examples, the utility model is further described.
Embodiment mono-of the present utility model: as shown in Figure 1 to Figure 3, the manufacturing line of a kind of elevator governor and door opener, comprise support 9, motor 2 and belt conveyor 4, belt conveyor 4 is arranged on support 9, and motor 2 is connected with belt conveyor 4, motor 2 provides power for the movement of belt conveyor 4, described belt conveyor 4 comprises shoe 5, and shoe 5 is provided with pumps passage 15, pumps and in passage 15, is provided with pipe link 10, also comprise erecting bed 7, erecting bed 7 detouchables are arranged on pipe link 10; Shoe 5 is provided with the first permanent seat 3, and erecting bed 7 is provided with the second permanent seat 11, and the upper surface of the upper surface of erecting bed 7 and shoe 5 is in same level.
As shown in Figure 3 and Figure 4, in the manufacturing line of above-mentioned elevator governor and door opener, described pipe link 10 is provided with at least two knock holees 16, the bottom of erecting bed 7 is provided with registration mast 6, the quantity of registration mast 6 equates with the quantity of knock hole 16, and erecting bed 7 is matched and is fixed on pipe link 10 with knock hole 16 by registration mast 6.Pipe link 10 comprises strut bar 8 and push rod 12, and knock hole 16 is arranged on strut bar 8, and one end of strut bar 8 is connected with push rod 12, and erecting bed 7 is fastened between shoe 5 and push rod 12.The width of erecting bed 7 is identical with the width of shoe 5.
The principle of work of embodiment mono-: above-mentioned motor 2 is stepping motors, stepping motor and control panel 1 are electrically connected, and stepping motor is controlled start and stop by control panel 1.Belt conveyor 4 is made up of multiple shoes 5 of parallel connection, in shoe 5, is provided with and pumps passage 15, pumps in passage 15 and is provided with pipe link 10, and pipe link 10 can be from pumping the interior extraction of passage 15.Also comprise erecting bed 7, erecting bed 7 detouchable that matches with knock hole 16 by registration mast 6 is fixed on pipe link 10.
In the time producing door opening machine for elevator, because the volume of door opener is larger, only use the manufacturing line being formed by shoe 5 can not realize the requirement that the base of door opener is completely fixed.By pipe link 10 from pumping the interior extraction of passage 15, erecting bed 7 is fixed on pipe link 10 by registration mast 6 and knock hole 16, because the upper surface of erecting bed 7 and the upper surface of shoe 5 are in same level, and, the width of the width of erecting bed 7 and shoe 5 equates, therefore widened the width of manufacturing line, can the base of door opener have been fixed by the first permanent seat 3 and the second permanent seat 11, then progressively installed according to operation.In the time that needs assemble velocity limiter, due to the small volume of velocity limiter, erecting bed 7 is unloaded from pipe link 10, pipe link 10 is pushed and pumped in passage 15, base by the first permanent seat 3 clamshell doors machines on shoe 5 is fixed, and then progressively installs according to operation.
Embodiment bis-of the present utility model: the manufacturing line of a kind of elevator governor and door opener, comprise support 9, motor 2 and belt conveyor 4, belt conveyor 4 is arranged on support 9, motor 2 is connected with belt conveyor 4, and motor 2 provides power for the movement of belt conveyor 4, and described belt conveyor 4 comprises shoe 5, shoe 5 is provided with pumps passage 15, pump in passage 15 and be provided with pipe link 10, also comprise erecting bed 7, erecting bed 7 detouchables are arranged on pipe link 10; Shoe 5 is provided with the first permanent seat 3, and erecting bed 7 is provided with the second permanent seat 11, and the upper surface of the upper surface of erecting bed 7 and shoe 5 is in same level.
As shown in Figure 5, in the manufacturing line of above-mentioned elevator governor and door opener, described motor 2 is stepping motor m, also comprises switch circuit, and switch circuit is electrically connected with stepping motor m, for the startup of control step motor m with close;
Switch circuit comprises start-up circuit 13 and shut-off circuit 14, start-up circuit 13 comprises the first normal open switch SB1, the first AC contactor KA1 and the first relay K M1, first normal open switch SB1 one end is electrically connected the other end and is electrically connected with the first relay K M1 with power supply, the first AC contactor KA1 and the first normal open switch SB1 parallel connection, stepping motor m one end is electrically connected with the first relay K M1, and the other end is connected with zero line N.
In the manufacturing line of above-mentioned elevator governor and door opener, shut-off circuit 14 comprises the second normal open switch SB2, time relay KT1, the second AC contactor KA2 and the second relay K M2; The second normal open switch SB2 connects with time relay KT1, and the other end of the second normal open switch SB2 is electrically connected with power supply, and the other end of time relay KT1 is connected with zero line N; The second AC contactor KA2 is in parallel with the second normal open switch SB2, and the second relay K M2 is in parallel with time relay KT1.
In the manufacturing line of above-mentioned elevator governor and door opener, also comprise divider resistance R1 and normally closed switch K1, divider resistance R1 and normally closed switch K1 are arranged between the first normal open switch SB1 and the second normal open switch SB2 and power supply, divider resistance R1 and normally closed switch K1 series connection, the other end of divider resistance R1 is electrically connected with power supply, and the other end of normally closed switch K1 is connected with the first normal open switch SB1 and the second normal open switch electricity SB2.
In the time preparing operation manufacturing line, first manual closing the first knife switch QS1 and the second knife switch QS2, now three of three-phase electricity phase line L1, L2, L3 all have energising, and therefore, between three phase line L1, L2, L3 and zero line N, there is voltage difference in zero line N ground connection.
After closed the first knife switch QS1 and the second knife switch QS2, press the first normal open switch SB1, the first relay K M1 energising, conducting after the first AC contactor KA1 energising, after the first AC contactor KA1 conducting, stepping motor m energising brings into operation.
In the time that needs production control line quits work, press the second normal open switch SB2, conducting after the second relay K M2 energising, conducting after the second AC contactor KA2 energising, because time relay KT1 is in parallel with the second relay K M2, so also conducting of time relay KT1, the time relay KT1 of conducting is by the first relay K M1 and the second relay K M2 short circuit, make to disconnect after the first relay K M1 and the second relay K M2 power-off, after the first relay K M1 disconnects, stepping motor m quits work.Unclamp after the second normal open switch SB2, second normal open switch SB2 reply off-state, meanwhile time relay KT1 starts timing, arrive the default time after time relay KT1 also disconnect, thereby by whole down circuitry.If run into unusual condition and fail to realize the power-off of circuit, can press normally closed switch K1, can emergency power off.
Wherein, the operation that stepping motor m is manufacturing line provides power, drives the belt conveyor 4 of manufacturing line to move.The elevator brake that need to assemble or safety tongs are placed on manufacturing line, stepping motor m pause certain hour when the elevator brake assembling when needs or safety tongs arrive the station of specifying, in the process of pausing, elevator brake or safety tongs are assembled, the time that stepping motor m pauses realizes by stepping motor m is set.The belt conveyor 4 of existing manufacturing line is all uniform movement, and the manufacturing line of elevator governor of the present utility model and door opener compared with prior art makes the distribution hommization more of time, reasonable distribution time.Because current workshop is all to adopt synchronous dynamo to provide power for manufacturing line, the belt conveyor 4 of manufacturing line is uniform movement, and workshop of the present utility model has avoided following the belt conveyor 4 of manufacturing line to move the problem that just can assemble with manufacturing line.

Claims (7)

1. the manufacturing line of an elevator governor and door opener, comprise support (9), motor (2) and belt conveyor (4), belt conveyor (4) is arranged on support (9), motor (2) is connected with belt conveyor (4), the movement that motor (2) is belt conveyor (4) provides power, it is characterized in that, described belt conveyor (4) comprises shoe (5), shoe (5) is provided with pumps passage (15), pump and in passage (15), be provided with pipe link (10), also comprise erecting bed (7), erecting bed (7) detouchable is arranged on pipe link (10), shoe (5) is provided with the first permanent seat (3), erecting bed (7) is provided with the second permanent seat (11), and the upper surface of the upper surface of erecting bed (7) and shoe (5) is in same level.
2. the manufacturing line of elevator governor according to claim 1 and door opener, it is characterized in that, described pipe link (10) is provided with at least two knock holees (16), the bottom of erecting bed (7) is provided with registration mast (6), the quantity of registration mast (6) equates with the quantity of knock hole (16), and erecting bed (7) is matched and is fixed on pipe link (10) with knock hole (16) by registration mast (6).
3. the manufacturing line of elevator governor according to claim 2 and door opener, it is characterized in that, pipe link (10) comprises strut bar (8) and push rod (12), knock hole (16) is arranged on strut bar (8), one end of strut bar (8) is connected with push rod (12), and erecting bed (7) is fastened between shoe (5) and push rod (12).
4. the manufacturing line of elevator governor according to claim 3 and door opener, is characterized in that, the width of erecting bed (7) is identical with the width of shoe (5).
5. the manufacturing line of elevator governor according to claim 1 and door opener, it is characterized in that, described motor (2) is stepping motor, also comprises switch circuit, switch circuit is electrically connected with stepping motor, for the startup of control step motor with close;
Switch circuit comprises start-up circuit (13) and shut-off circuit (14), start-up circuit (1) comprises the first normal open switch, the first AC contactor and the first relay, first normal open switch one end is electrically connected the other end and is electrically connected with the first relay with power supply, the first AC contactor and the first normal open switch parallel connection, stepping motor one end is electrically connected with the first relay, and the other end is connected with zero line.
6. the manufacturing line of elevator governor according to claim 5 and door opener, is characterized in that, shut-off circuit (14) comprises the second normal open switch, time relay, the second AC contactor and the second relay; The second normal open switch is connected with time relay, and the other end of the second normal open switch is electrically connected with power supply, and the other end of time relay is connected with zero line; The second AC contactor is in parallel with the second normal open switch, and the second relay is in parallel with time relay.
7. the manufacturing line of elevator governor according to claim 6 and door opener, it is characterized in that, also comprise divider resistance and normally closed switch, divider resistance and normally closed switch are arranged between the first normal open switch and the second normal open switch and power supply, divider resistance and normally closed switch series connection, the other end of divider resistance is electrically connected with power supply, and the other end of normally closed switch is electrically connected with the first normal open switch and the second normal open switch.
CN201420292157.1U 2014-06-03 2014-06-03 Elevator speed governor and door opener production line Withdrawn - After Issue CN203889493U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420292157.1U CN203889493U (en) 2014-06-03 2014-06-03 Elevator speed governor and door opener production line

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420292157.1U CN203889493U (en) 2014-06-03 2014-06-03 Elevator speed governor and door opener production line

Publications (1)

Publication Number Publication Date
CN203889493U true CN203889493U (en) 2014-10-22

Family

ID=51715924

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420292157.1U Withdrawn - After Issue CN203889493U (en) 2014-06-03 2014-06-03 Elevator speed governor and door opener production line

Country Status (1)

Country Link
CN (1) CN203889493U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103979261A (en) * 2014-06-03 2014-08-13 湖州华奥电梯科技有限公司 Production line of elevator speed limiter and door opener
CN109955051A (en) * 2019-05-09 2019-07-02 湖州师范学院求真学院 A kind of full-automatic assembly pipeline of power distribution cabinet

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103979261A (en) * 2014-06-03 2014-08-13 湖州华奥电梯科技有限公司 Production line of elevator speed limiter and door opener
CN103979261B (en) * 2014-06-03 2016-03-09 默纳克电梯有限公司 Production line of elevator speed limiter and door opener
CN109955051A (en) * 2019-05-09 2019-07-02 湖州师范学院求真学院 A kind of full-automatic assembly pipeline of power distribution cabinet
CN109955051B (en) * 2019-05-09 2020-05-26 湖州师范学院求真学院 Full-automatic assembly conveying line for power distribution cabinet

Similar Documents

Publication Publication Date Title
CN203889493U (en) Elevator speed governor and door opener production line
CN104003183A (en) Anti-collision conveying equipment with locating function
CN104525826B (en) A kind of automatic nailing device of compatible 1-4 pole chopper
CN103979261B (en) Production line of elevator speed limiter and door opener
CN203877345U (en) Production line for elevator brake and safety tongs
CN203994709U (en) High frequency double heat seal machine
CN106246524A (en) A kind of electric oil-immersed plunger pump oil pumping system service intermittent control method
CN204413034U (en) The automatic nailing device of a kind of compatible 1-4 pole breaker
CN203877344U (en) Assembly line of bicycles
CN103979258B (en) The assembling line of bicycle
CN204992899U (en) Adjustment type motor cabinet
CN103979259B (en) Production line of elevator brake and safety gear
CN208391422U (en) A kind of pressing lock screws apptss
CN105329651A (en) Motor rotor dynamic balancing detection feeding device
CN205484438U (en) Movable plug and testing arrangement of household appliances circular telegram test usefulness
CN111497326B (en) Automatic groover of carton processing production
CN103306959A (en) Power air compressor and control method thereof
CN203779546U (en) Shell dismounting tool
CN203787582U (en) Quick cable connection strip used between high-voltage frequency converter cabinets
CN202561409U (en) Continuous oiling machine of bearing
CN202394752U (en) Automatic regulating mechanism for assembly production line of small-sized low-voltage electrical appliance
CN108543875A (en) A kind of hardware stamping processing multistation Quadratic Finite Element manipulator
CN205303299U (en) Vacuum contactor
CN203894644U (en) Automatic water feed control device of hotel water tank
CN204278254U (en) A kind of foam cement plate cutting production line

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee

Owner name: MNK ELEVATOR CO., LTD.

Free format text: FORMER NAME: HUZHOU HUAAO ELEVATOR TECHNOLOGY CO., LTD.

CP01 Change in the name or title of a patent holder

Address after: 313009 No. 99 Station Road, Nanxun Town, Nanxun District, Zhejiang, Huzhou

Patentee after: HUZHOU HUAAO ELEVATOR CO., LTD.

Address before: 313009 No. 99 Station Road, Nanxun Town, Nanxun District, Zhejiang, Huzhou

Patentee before: Huzhou Hua Ao elevator Science and Technology Ltd.

AV01 Patent right actively abandoned

Granted publication date: 20141022

Effective date of abandoning: 20160309

C25 Abandonment of patent right or utility model to avoid double patenting