CN203877109U - Lifting storage rack for building prefabricated composite floor slabs - Google Patents

Lifting storage rack for building prefabricated composite floor slabs Download PDF

Info

Publication number
CN203877109U
CN203877109U CN201420174114.3U CN201420174114U CN203877109U CN 203877109 U CN203877109 U CN 203877109U CN 201420174114 U CN201420174114 U CN 201420174114U CN 203877109 U CN203877109 U CN 203877109U
Authority
CN
China
Prior art keywords
base
mounting
longitudinal
main frame
storage rack
Prior art date
Application number
CN201420174114.3U
Other languages
Chinese (zh)
Inventor
张亮
杜培俊
何兆芳
吕焱
Original Assignee
中国十七冶集团有限公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 中国十七冶集团有限公司 filed Critical 中国十七冶集团有限公司
Priority to CN201420174114.3U priority Critical patent/CN203877109U/en
Application granted granted Critical
Publication of CN203877109U publication Critical patent/CN203877109U/en

Links

Abstract

The utility model discloses a lifting storage rack for building prefabricated composite floor slabs, and belongs to residential construction auxiliary devices. The lifting storage rack is characterized by being mainly composed of an upper seat frame, a base, a first vertical plate, a second vertical plate and lifting lugs, the upper seat frame is mainly composed of a main frame, an auxiliary longitudinal beam and an auxiliary cross beam, the main frame is a rectangular frame mainly formed by installing and welding a front cross beam, a rear cross beam, a left longitudinal beam and a right longitudinal beam, the front cross beam and the rear cross beam are symmetrical and parallel to each other, the left longitudinal beam and the right longitudinal beam are symmetrical and parallel to each other, the auxiliary cross beam and the auxiliary longitudinal beam are installed and welded into the main frame in a cross or grid shape, a board is fixedly installed on the upper surface of the main frame, the left longitudinal beam and the right longitudinal beam of the main frame are symmetrically provided with the annular lifting lugs, the base is the same as the upper seat frame in size and is a rectangular frame mainly formed by installing and welding a front base cross beam, a rear base cross beam, a left base longitudinal beam and a right base longitudinal beam, the upper seat frame and the base are symmetrically and vertically arranged in a spaced mode, and the first vertical plate and the second vertical plate are correspondingly installed and welded to be fixedly connected. The lifting storage rack is safe and reliable to use, easy to operate and high in efficiency, and saves labor and time.

Description

The handling storage rack of building prefabrication laminating type floor
Technical field
The utility model belongs to housing construction auxiliary device, especially relates to a kind of handling storage rack of precast floor slab.
Background technology
Along with the pilot conversion of housing industrialization, house prefabricated components are progressively applied.The prefabricated components that residential housing is used: as all prefabricated at PC(in wallboard, floor, balcony slab, the luffer boards that waft, beam and column etc.) member factory completes, then by transport vehicle in batches by component conveying to camp site, complete at the construction field (site) unloading, hanging and assembled work of prefabricated components.
But because prefabricated components are concrete products, the breakage that easily bumps in transportation, therefore, to prefabricated components deposit and transportation has higher requirements; The precast floor slab of superposed and stacked, because its size is numerous, after factory for prefabrication produces, stacks (7 floors of the maximum foldables stacking of 1 buttress) mainly with buttress for measure unit.But when the lifting work of carrying out floor, at present once can only complete the lifting job of 1 floor, can not complete the lifting job of floor (by the quantity handling simultaneously polylith floor of 1 buttress floor) in batches, cause the lifting job inefficiency of floor, affect the construction speed of house.
Summary of the invention
The purpose of this utility model is the handling storage rack that proposes a kind of building prefabrication laminating type floor.Not only simple and reasonable for structure, safe and reliable, and greatly improve the handling efficiency of building floor, accelerate the construction speed of house.
The purpose of this utility model is achieved in that a kind of handling storage rack (being called for short handling storage rack) of building prefabrication laminating type floor, it is characterized in that: the handling storage rack of this building prefabrication laminating type floor is mainly by upper mounting, base, riser I, riser II and hanger form, wherein, upper mounting is again mainly by main frame and secondary longeron, secondary crossbeam forms, this main frame is the rectangular frame that the main front and back crossbeam being arranged by symmetrical parallel and left-right longeron assembly welding form, and in main frame, be crisscross or be grid and be welded secondary crossbeam and secondary longeron, on the upper surface of main frame, fixedly mount plank simultaneously, with what be used as to protect, on the longeron of two of the left and right of main frame, offer symmetrically respectively hanger hole, front and back and mounting circular ring shape hanger in each hanger hole, this base is rectangular frame of the same size with upper mounting and that mainly formed by front and back bottom cross beam and left and right bottom girder assembly welding, by upper mounting, the symmetrical compartment of terrain of base is setting up and down, a left side at upper mounting, the middle part of right vertical beam and a left side for base, the riser I that is welded respectively between the middle part of right bottom girder is connected, and form the fork import of former and later two forklift tine, before upper mounting, before after cross member and base, the riser II longitudinally that is welded in uniform way respectively between rear bottom cross beam is connected, upper mounting is connected securely with base.
During use, first use fork truck, utilize the fork import on this handling storage rack, this handling storage rack fork is delivered to the position of dress floor, then, be placed on plank each piece floor is superimposed, Yi Duowei unit, and the quantity of the floor of once depositing on this handling storage rack is no more than 7; Before handling, adopt two ropes with elasticity bolt to bundle securely floor and this handling storage rack by hanger, prevent from occurring falling of floor in hoisting process, coordinate crane to complete lifting operation simultaneously, guarantee floor safety and firmness in hoisting process, the handling process operation of whole floor is simple, and saving of work and time efficiency is high.
The handling storage rack of the building prefabrication laminating type floor that the utility model proposes, not only simple and reasonable for structure, safe and reliable, and greatly improved the handling efficiency of building floor, accelerated the construction speed of house.
The handling storage rack of building prefabrication laminating type floor the utility model being proposed below in conjunction with drawings and Examples is further described.
Accompanying drawing explanation
Fig. 1 is the schematic perspective view of the handling storage rack of the building prefabrication laminating type floor that proposes of the utility model.
In Fig. 1:
1, upper mounting 2, base 3, fork import 4, hanger 5-1, riser I 5-2, riser II.
The specific embodiment
As shown in fig. 1, a kind of handling storage rack of building prefabrication laminating type floor (being called for short handling storage rack), it is characterized in that: the handling storage rack of this building prefabrication laminating type floor is mainly by upper mounting 1, base 2, riser I 5-1, riser II 5-2 and hanger 4 form, wherein, upper mounting 1 is again mainly by main frame and secondary longeron, secondary crossbeam forms, this main frame is the rectangular frame that the main front and back crossbeam being arranged by symmetrical parallel and left-right longeron assembly welding form, and in main frame, be crisscross or be grid and be welded secondary crossbeam and secondary longeron, on the upper surface of main frame, fixedly mount plank simultaneously, with what be used as to protect, on the longeron of two of the left and right of main frame, offer symmetrically respectively hanger hole, front and back and mounting circular ring shape hanger 4 in each hanger hole, this base 2 is rectangular frames of the same size with upper mounting 1 and that mainly formed by front and back bottom cross beam and left and right bottom girder assembly welding, by upper mounting 1, the symmetrical compartment of terrain of base 2 is setting up and down, a left side at upper mounting 1, a left side for the middle part of right vertical beam and base 2, the riser I that is welded respectively between the middle part of right bottom girder 5-1 is connected, and form the fork import 3 of former and later two forklift tine, before upper mounting 1, before after cross member and base 2, the riser II 5-2 longitudinally that is welded in uniform way respectively between rear bottom cross beam is connected, upper mounting 1 is connected securely with base 2.
During use, first use fork truck, utilize the fork import 3 on this handling storage rack, this handling storage rack fork is delivered to the position of dress floor, then, be placed on plank each piece floor is superimposed, Yi Duowei unit, and the quantity of the floor of once depositing on this handling storage rack is no more than 7; Before handling, adopt two ropes with elasticity bolt to bundle securely floor and this handling storage rack by hanger 4, prevent from occurring falling of floor in hoisting process, coordinate crane to complete lifting operation simultaneously, guarantee floor safety and firmness in hoisting process, the handling process operation of whole floor is simple, and saving of work and time efficiency is high.

Claims (1)

1. the handling storage rack of a building prefabrication laminating type floor, it is characterized in that: the handling storage rack of this building prefabrication laminating type floor is mainly by upper mounting (1), base (2), hanger (4) and riser I (5-1), riser II (5-2) forms, wherein, upper mounting (1) is again mainly by main frame and secondary longeron, secondary crossbeam forms, this main frame is the rectangular frame that the main front and back crossbeam being arranged by symmetrical parallel and left-right longeron assembly welding form, and in main frame, be crisscross or be grid and be welded secondary crossbeam and secondary longeron, on the upper surface of main frame, fixedly mount plank simultaneously, on the longeron of two of the left and right of main frame, offer symmetrically respectively hanger hole, front and back and mounting circular ring shape hanger (4) in each hanger hole, this base (2) is rectangular frame of the same size with upper mounting (1) and that mainly formed by front and back bottom cross beam and left and right bottom girder assembly welding, by upper mounting (1), the symmetrical compartment of terrain of base (2) is setting up and down, a left side in upper mounting (1), a left side for the middle part of right vertical beam and base (2), the riser I that is welded respectively between the middle part of right bottom girder (5-1) is connected, and form the fork import (3) of former and later two forklift tine, before upper mounting (1), before after cross member and base (2), the riser II (5-2) longitudinally that is welded in uniform way respectively between rear bottom cross beam is connected, upper mounting (1) is connected securely with base (2).
CN201420174114.3U 2014-04-11 2014-04-11 Lifting storage rack for building prefabricated composite floor slabs CN203877109U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420174114.3U CN203877109U (en) 2014-04-11 2014-04-11 Lifting storage rack for building prefabricated composite floor slabs

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420174114.3U CN203877109U (en) 2014-04-11 2014-04-11 Lifting storage rack for building prefabricated composite floor slabs

Publications (1)

Publication Number Publication Date
CN203877109U true CN203877109U (en) 2014-10-15

Family

ID=51677636

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420174114.3U CN203877109U (en) 2014-04-11 2014-04-11 Lifting storage rack for building prefabricated composite floor slabs

Country Status (1)

Country Link
CN (1) CN203877109U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104150068A (en) * 2014-08-15 2014-11-19 中国十七冶集团有限公司 Prefabricated composite floor slab transport device and use method thereof
CN108086479A (en) * 2017-09-01 2018-05-29 王晓军 A kind of new builing structure body
CN108910717A (en) * 2018-08-08 2018-11-30 中国十七冶集团有限公司 A kind of handling apparatus for prefabricated base board
CN109230981A (en) * 2018-11-15 2019-01-18 刘贤顺 A kind of hoisting tooling

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104150068A (en) * 2014-08-15 2014-11-19 中国十七冶集团有限公司 Prefabricated composite floor slab transport device and use method thereof
CN108086479A (en) * 2017-09-01 2018-05-29 王晓军 A kind of new builing structure body
CN108910717A (en) * 2018-08-08 2018-11-30 中国十七冶集团有限公司 A kind of handling apparatus for prefabricated base board
CN108910717B (en) * 2018-08-08 2019-08-06 中国十七冶集团有限公司 A kind of handling apparatus for prefabricated base board
CN109230981A (en) * 2018-11-15 2019-01-18 刘贤顺 A kind of hoisting tooling

Similar Documents

Publication Publication Date Title
PH12014501858A1 (en) Preformed formwork for forming concrete floor slab for a height adjustable shipping container building structure
CN202687760U (en) Engineering lifting hoisting cage
CN102587647A (en) Early-removal formwork system for concreting of constructions comprising beams, plates and columns
CN202400723U (en) Lifting tool type hanger frame for prefabricated parts
CN202186826U (en) Block transportation device
PH12015500868A1 (en) Methods, systems and components for multi-storey building construction
CN201614738U (en) Support device for mould board assembly of steel reinforced concrete transfer beams
CN103243930B (en) System and method for modularized construction of super high-rise steel structures
CN203499229U (en) Operating platform for construction of elevator shaft
CN201809036U (en) Hanging hopper with detachable chassis
US9279260B2 (en) Modular panel concrete form for self-lifting concrete form system
CN103935911A (en) Tower crane attached wall support structure and construction method thereof
CN203531344U (en) Tool type scaffold
CN103053045B (en) Assembled battery support
CN203947490U (en) Combination moving type concrete premade tower crane foundation
CN202370234U (en) Tool type elevator hoistway construction platform
CN202483154U (en) High bearing capacity suspending scaffold
CN204001652U (en) The portable exterior wall operating platform of fabricated shear wall structure
CN203682938U (en) Decorating crane
CN103366844B (en) Nuclear power station upper-part in-reactor component installation method
CN202337344U (en) Scaffold structure in cargo cabin of bulk cargo ship
CN203462736U (en) Operating platform for lift shaft structural steel construction
CN105627038A (en) Energy storage equipment base
CN204510650U (en) A kind of precast splice type stringer type stairway
CN204126230U (en) Assembly scaffold unit

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant