CN203875855U - Hole drilling and dust cleaning integrated electric hammer for planting bars on concrete structure - Google Patents

Hole drilling and dust cleaning integrated electric hammer for planting bars on concrete structure Download PDF

Info

Publication number
CN203875855U
CN203875855U CN201420241304.2U CN201420241304U CN203875855U CN 203875855 U CN203875855 U CN 203875855U CN 201420241304 U CN201420241304 U CN 201420241304U CN 203875855 U CN203875855 U CN 203875855U
Authority
CN
China
Prior art keywords
electric hammer
handle
concrete structure
planting
hole drilling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201420241304.2U
Other languages
Chinese (zh)
Inventor
黄丽华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201420241304.2U priority Critical patent/CN203875855U/en
Application granted granted Critical
Publication of CN203875855U publication Critical patent/CN203875855U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Earth Drilling (AREA)

Abstract

The utility model relates to a hole drilling and dust cleaning integrated electric hammer for planting bars on a concrete structure. According to the hole drilling and dust cleaning integrated electric hammer for planting the bars on the concrete structure, an electric hammer main machine extends to be provided with a motor rotating shaft, and the motor rotating shaft is provided with fan blades. An air inlet is formed in one side of the fan blades, and an air outlet tube is formed in the bottom end of the electric hammer. One end of a handle inner air tube is connected with the air outlet tube, the other end of the handle inner air tube is inserted into a handheld handle, an atomization generator is arranged on the handle inner air tube in a sleeved mode, and an anti-reflux cap is arranged at the top end of the electric hammer. A water filling opening is formed in one portion of the handheld handle, and an outlet in one end of the handheld handle is connected to a mist outlet tube. According to the hole drilling and dust cleaning integrated electric hammer for planting the bars on the concrete structure, the motor rotating shaft of the electric hammer main machine is extended to drive the fan blades to conduct air blasting, and the effect of various output purposes with the same power is achieved; the atomization generator is arranged in the handle inner air tube, the purpose that the air blown into a venturi is wet mist is achieved, and therefore the purposes of removing dust and fixing dust are achieved. The venturi is arranged on a drill bit in a sleeved mode, and the purposes of polymerizing airflow and removing dust are achieved.

Description

A kind of clear dirt one of boring electric hammer for the bar planting of concrete structure
Technical field
The utility model relates to a kind of clear dirt one of boring electric hammer for the bar planting of concrete structure.
Background technology
Chemical method bar planting refers to the bar planting of architectural engineering chemical method anchoring adhesive, is the interconnection technique that after a kind of reinforcing bar on building structure aseismatic reinforcing engineering, anchoring utilizes the effect of structure glue locking key grip force, is the optimal selection of structure bar planting reinforcing and heavy load fastening applications.Chemical method bar planting refers on the base materials such as concrete, body of wall rock and holes, and then injects high-strength anchoring adhesive, then inserts reinforcing bar or section bar, after adhesive curing, reinforcing bar and substrate bonding is integrated, and is the conventional a kind of architectural engineering technology of reinforcement and strengthening industry.General constructing operation: snap the line location.According to the reinforcement bar arrangement of design drawing and quantity, the original structure reinforcement location that staggers, marks out bar planting position.Please relevant department test line, just can hole after qualified.Boring.With the impact drilling, bit diameter should be than the large 5mm of bar diameter left and right, φ 25 reinforcing bars that reinforcing bar selects Shoudu Iron and Steel Co to produce, and drill bit is selected the alloy tool steel bit of φ 30.Hole depth size 15d (375mm), when the dark 400mm. boring of actual brill, drill bit keeps vertical with cylinder all the time.Hole flushing.Hole flushing is a most important link in bar planting, because the complete rear inside of hole drill has a lot of ashes, lime-ash, directly affects the quality of bar planting, so foreign material in hole must be cleaned out.Method is: put elongated bar with hairbrush, at the bottom of extending hole, repeatedly twitch back and forth, dust, disintegrating slag are taken out of, then used compressed air, blow out floating dust in hole.After having blown, be stained with alcohol or acetone scouring hole inwall with absorbent cotton again.But can not use scrub water, because of alcohol and acetone volatile, water is not volatile.With not being dried very soon in scrub water metapore.Boring will be asked units concerned's examinations such as design after having cleaned, can injecting glue after qualified.Injecting glue.Get one group of powerful anchoring adhesive, in threading sleeve, be arranged on special manual syringe, slowly pull plate machine, discharge the rarer glue in platinum bag mouth place and pass into disuse, at the bottom of then thread mixing mouth being stretched into hole, plastic tube as available not in length lengthens, then pull plate machine, under the moving shot device slow astern in plate machine hole, can discharge hole air like this.Full in order to make reinforcing bar implant in metapore glue, can not make again glue outflow, in hole, injecting glue reaches 80%.In hole, fill bar planting immediately after glue.Operate in beam bottom mother plate before injecting glue and just prop up, be convenient to reinforcing bar location after bar planting.Before bar planting, reinforcing bar implant part to be brushed repeatedly with wire brush, be removed rust dirty, then clean with alcohol or acetone.In boring, note after glue, the reinforcing bar of crossing through processing of rust removing has been put into aperture immediately, then unidirectional screw-in slowly, reverse reversion midway, until at the bottom of reinforcing bar stretches into hole.Curing conservation.Reinforcing bar is located after implanting on beam bottom mother plate, before powerful anchoring adhesive solidifies completely, can not vibrate reinforcing bar.Powerful anchoring adhesive just can complete curing at normal temperatures, just can carry out next procedure construction after 50h.
But in the operating process of current construction chemical method bar planting, boring clean this step very careless, conventionally some workmens directly with drill bit smash several under, just put into high-strength anchoring adhesive.So effect that does not at all have anchoring, therefore design strength is far not by far up to the mark.
Summary of the invention
The purpose of this utility model is to provide a kind of clear dirt one of boring electric hammer for the bar planting of concrete structure, thereby can ensure the complete hole of electric hammer drill, and some dust of this hole are also cleaned.
To achieve the above object, the utility model adopts following technical scheme: a kind of clear dirt one of boring electric hammer for the bar planting of concrete structure, its structure mainly comprises: tracheae in electric hammer main frame, machine shaft, flabellum, air inlet, escape pipe, handle, hold handle, water filling port, fog outlet, trunnion, drill bit, atomizing generator, counterflow-preventing cap, described electric hammer main frame is extended with machine shaft, and machine shaft is provided with flabellum; Described flabellum one side has air inlet, and bottom is provided with escape pipe;
Access escape pipe in tracheae one end in described handle, the other end inserts and holds in handle, and in described handle, on tracheae, cover has atomizing generator, and is provided with counterflow-preventing cap on top;
Described handle one place that holds is provided with water filling port;
Described holds on handle one end outlet access fog outlet;
Described electric hammer main frame clutch end is fixed with drill bit, and described drill bit overcoat has trunnion.
Above-mentioned holding in handle filled with and had pure water.
The beneficial effects of the utility model: drive flabellum to carry out air blast by extending the machine shaft of electric hammer main frame, realized the effect of the multiple output purposes of same power; Be provided with atomizing generator by tracheae in handle, the object that to have realized the air that is blown in trunnion be moistening fog, and then arrive the object of the solid dirt of dedusting; On drill bit, cover has trunnion, has realized the object of polymerization air-flow dedusting.
Brief description of the drawings
Fig. 1 is the structural representation of a kind of clear dirt one of boring electric hammer for the bar planting of concrete structure of the utility model.
Fig. 2 is that a kind of clear dirt one of boring electric hammer for the bar planting of concrete structure of the utility model is held handle structure schematic diagram.
1-electric hammer main frame in figure, 2-machine shaft, 3-flabellum, 4-air inlet, 5-escape pipe, tracheae in 6-handle, 7-holds handle, 8-water filling port, 9-fog outlet, 10-trunnion, 11-drill bit, 12-atomizing generator, 13-counterflow-preventing cap.
Detailed description of the invention
Below in conjunction with accompanying drawing 1-2, detailed description of the invention of the present utility model is made a detailed explanation.
Embodiment: a kind of clear dirt one of boring electric hammer for the bar planting of concrete structure, its structure mainly comprises: tracheae 6 in electric hammer main frame 1, machine shaft 2, flabellum 3, air inlet 4, escape pipe 5, handle, hold handle 7, water filling port 8, fog outlet 9, trunnion 10, drill bit 11, atomizing generator 12, counterflow-preventing cap 13, described electric hammer main frame 1 is extended with machine shaft 2, and machine shaft 2 is provided with flabellum 3; Described flabellum 3 one sides have air inlet 4, and bottom is provided with escape pipe 5;
Tracheae 6 one end access escape pipes 5 in described handle, the other end inserts and holds in handle 7, and in described handle, on tracheae 6, cover has atomizing generator 12, and is provided with counterflow-preventing cap 13 on top;
Described handle 7 one places that hold are provided with water filling port 8;
Described holds on handle 7 one end outlet access fog outlets 9;
Described electric hammer main frame 1 clutch end is fixed with drill bit 11, and described drill bit 11 overcoats have trunnion 10.
The above-mentioned interior filling of handle 7 of holding has pure water.
The utility model core is to hold handle 7 and a blower system being made up of machine shaft 2, flabellum 3, air inlet 4, produce air-flow by flabellum 3, held in handle 7 by escape pipe 5 inputs, in handle 7, be provided with atomizing generator 12 owing to holding, therefore when air-flow is through out-of-date, can take away a part of fog, then enter in trunnion 10 by fog outlet 9.In the time that drill bit 11 punches in running up, dust can fly upward everywhere, and now most dust can be wrapped up by trunnion 10, and interior with a large amount of moistening water smoke by trunnion 10.Therefore in by trunnion 10, the dust of most can be cured, and the gas that the dust in hole blows out by trunnion 10 is also cleaned.

Claims (2)

1. the clear dirt one of the boring electric hammer for the bar planting of concrete structure, its structure mainly comprises: tracheae (6) in electric hammer main frame (1), machine shaft (2), flabellum (3), air inlet (4), escape pipe (5), handle, hold handle (7), water filling port (8), fog outlet (9), trunnion (10), drill bit (11), atomizing generator (12), counterflow-preventing cap (13), it is characterized in that: electric hammer main frame (1) is extended with machine shaft (2), machine shaft (2) is provided with flabellum (3); Described flabellum (3) one sides have air inlet (4), and bottom is provided with escape pipe (5);
Tracheae (6) one end access escape pipe (5) in described handle, the other end inserts and holds in handle (7), and in described handle, the upper cover of tracheae (6) has atomizing generator (12), and is provided with counterflow-preventing cap (13) on top;
Described handle (7) one places that hold are provided with water filling port (8);
Described holds on handle (7) one end outlet access fog outlet (9);
Described electric hammer main frame (1) clutch end is fixed with drill bit (11), and described drill bit (11) overcoat has trunnion (10).
2. according to a kind of clear dirt one of the boring electric hammer for the bar planting of concrete structure described in claim 1, it is characterized in that the described filling in handle (7) of holding has pure water.
CN201420241304.2U 2014-08-12 2014-08-12 Hole drilling and dust cleaning integrated electric hammer for planting bars on concrete structure Expired - Fee Related CN203875855U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420241304.2U CN203875855U (en) 2014-08-12 2014-08-12 Hole drilling and dust cleaning integrated electric hammer for planting bars on concrete structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420241304.2U CN203875855U (en) 2014-08-12 2014-08-12 Hole drilling and dust cleaning integrated electric hammer for planting bars on concrete structure

Publications (1)

Publication Number Publication Date
CN203875855U true CN203875855U (en) 2014-10-15

Family

ID=51676398

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420241304.2U Expired - Fee Related CN203875855U (en) 2014-08-12 2014-08-12 Hole drilling and dust cleaning integrated electric hammer for planting bars on concrete structure

Country Status (1)

Country Link
CN (1) CN203875855U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107511801A (en) * 2017-09-13 2017-12-26 中冶天工集团天津有限公司 The air blast electric hammer of itself strength borehole cleaning after a kind of drilling for bar planting
CN109653130A (en) * 2017-06-05 2019-04-19 成荣鹏 Highway barrier Rebar bonding device and its construction method
US11872665B2 (en) 2021-04-01 2024-01-16 Milwaukee Electric Tool Corporation Integrated dust extractor and power tool

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109653130A (en) * 2017-06-05 2019-04-19 成荣鹏 Highway barrier Rebar bonding device and its construction method
CN109653130B (en) * 2017-06-05 2020-11-06 东阳市琰安建筑工程有限公司 Highway guardrail bar planting device
CN107511801A (en) * 2017-09-13 2017-12-26 中冶天工集团天津有限公司 The air blast electric hammer of itself strength borehole cleaning after a kind of drilling for bar planting
US11872665B2 (en) 2021-04-01 2024-01-16 Milwaukee Electric Tool Corporation Integrated dust extractor and power tool

Similar Documents

Publication Publication Date Title
CN105888259A (en) Concrete steel bar planting method
CN203875855U (en) Hole drilling and dust cleaning integrated electric hammer for planting bars on concrete structure
CN109878262A (en) A kind of fine arts paintbrush cleaning device
CN202943063U (en) Electric centrifugal descaling device
CN109333295A (en) A kind of rust removing device for reinforcing steel bars
CN214836213U (en) Convenient clear hole instrument in muscle hole is planted from inhaling formula
CN206779074U (en) Anchor hole hole cleaner
CN211500566U (en) Dustproof clear hole device
CN201316230Y (en) Multi-functional dust suction rod
CN101596754B (en) Label peeling machine
CN206716648U (en) A kind of pipeline dust remover for IVC equipment
CN203818252U (en) Chip self-suction type drilling device for template
CN206882348U (en) Labware cleaning device
CN207325409U (en) Hand-held cleaning plant
CN109680638A (en) A kind of civil engineering smoothing machine
CN209139371U (en) Multifunctional self-suction bar planting hole cleaning equipment
CN209918869U (en) Air shovel for sand cleaning and repairing of casting
CN202458205U (en) Eyelet dust remover
CN212672708U (en) Commodity concrete production dust fall pipeline based on hydrologic cycle
CN206662997U (en) A kind of grinding workpieces room filtration drum type dust remover
CN205587371U (en) Hole device is blown in building engineering bar planting
CN211917311U (en) Bar planting dust collector
CN206166149U (en) Washing brush
CN206607535U (en) A kind of enclosing sweeping robot
CN209702794U (en) A kind of steel mill's dedusting steel-smelting converter device of high-efficiency low-pollution

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20141015

Termination date: 20150812

EXPY Termination of patent right or utility model