CN203848666U - Gold dressing agent preparation device - Google Patents

Gold dressing agent preparation device Download PDF

Info

Publication number
CN203848666U
CN203848666U CN201420087362.4U CN201420087362U CN203848666U CN 203848666 U CN203848666 U CN 203848666U CN 201420087362 U CN201420087362 U CN 201420087362U CN 203848666 U CN203848666 U CN 203848666U
Authority
CN
China
Prior art keywords
boiler
layer
agent preparation
gold ore
preparation facilities
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201420087362.4U
Other languages
Chinese (zh)
Inventor
熊宝琳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201420087362.4U priority Critical patent/CN203848666U/en
Application granted granted Critical
Publication of CN203848666U publication Critical patent/CN203848666U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Manufacture And Refinement Of Metals (AREA)

Abstract

A gold dressing agent preparation device comprises a boiler (1) and a smelting furnace (2) which are connected by adopting a pipeline (3). The boiler (1) is arranged to be cylindrical, a coal inlet (1.1) is arranged at the top of the boiler (1), an air outlet (1.2) is arranged on the side wall of the upper end of the boiler (1) and connected with the pipeline (3), a water sprinkling port (1.8) is arranged on the side wall of the upper end of the boiler (1), a load bearing plate (1.3) is arranged at the bottom of the boiler (1), a hole (1.4) is formed in the load bearing plate (1.3), the bottom of the boiler (1) is connected to an inverted-conical slag outlet (1.5), a flange disc (1.6) is connected on the slag outlet (1.5), an ignition port (1.7) is arranged on the side wall of the boiler (1), and the like. The gold dressing agent preparation device has the advantages of high energy resource utilization rate, firm and reliable structure and long service life.

Description

A kind of gold ore agent preparation facilities
Technical field
The utility model belongs to a kind of appliance arrangement technical field of structures, especially belongs to the technical field of structures for gold ore agent preparation facilities.
Background technology
Conventional gold ore agent preparation facilities is generally plain cylindrical furnace transformation, adopts the raw material of coal as burning use, its maximum shortcoming be waste energy, the preparation temperature of seriously polluted and wayward gold ore agent.
Summary of the invention
The utility model is the defect in order to address the above problem just, and a kind of novel gold ore agent preparation facilities is provided, and it is high that this device has energy utilization rate, firm in structure reliable, the advantage of long service life.
The utility model adopts following technical scheme to realize.
A kind of gold ore agent preparation facilities, comprises boiler, smelting furnace; Between the utility model boiler and combustion furnace, adopt pipeline to be connected; Boiler is set to cylindrical shape; Top is provided with coal-in port, and upper end sidewall sets out gas port and is connected with pipeline; Upper end sidewall is provided with watering mouthful; Boiler bottom is provided with bearing plate, arranges porose on bearing plate; Boiler bottom is connected with inverted cone-shaped slag notch, is connected with ring flange on slag notch; Boiler side walls is provided with lighting-up tuyere;
Smelting furnace is arranged on base; Smelting furnace is set to respectively iron plate layer, fire brick layer, ventilating layer, stainless steel layer from outside to inside; The bottom of stainless steel layer is provided with corrosion resistant plate, and the bottom of corrosion resistant plate and stainless steel layer forms combustion chamber, and combustion chamber is connected with pipeline; Being provided with igniting hole stretches in combustion chamber through iron plate layer, fire brick layer, ventilating layer, stainless steel layer successively;
On pipeline, be provided with valve and fire hole.
Gold ore agent described in the utility model refers to the gold ore agent that application number is " 2013100225852 ".
The utility model pipeline is stainless steel tube, and diameter is 100mm ± 10mm.
The vertical range of the utility model lighting-up tuyere distance from bottom bearing plate is more than 300mm.
The aperture in the utility model hole is 5mm-20mm.
The thickness of the utility model iron plate layer is 10mm ± 2mm.
The thickness of the utility model fire brick layer is 250mm ± 20mm.
The width of the utility model ventilating layer is 100mm ± 10mm.
The thickness of the utility model stainless steel layer is 100mm ± 10mm.
The height of the utility model combustion chamber is 200mm ± 20mm.
The utility model has the advantage of, 1, the effect of boiler is not for producing heat, but in order to generate coal gas, and then utilize the preparation as gold ore agent of heat energy that coal gas produces, its heat utilization rate is higher; 2, simple in structure, easy to process; 3, the parameter in structure can ensure the utlity model has extraordinary quality, and it is firm in structure reliable, long service life, and this structural design can meet the preparation demand of the utility model to gold ore agent completely.
Detailed description of the invention
See Fig. 1, a kind of gold ore agent preparation facilities, comprises boiler 1, smelting furnace 2; Between the utility model boiler 1 and combustion furnace 2, adopt pipeline 3 to be connected; Boiler 1 is set to cylindrical shape; Top is provided with coal-in port 1.1, and upper end sidewall sets out gas port 1.2 and is connected with pipeline 3; Upper end sidewall is provided with watering mouth 1.8; When coal in boiler, burn aglow after, watering mouthful open, watering generate coal gas; Boiler 1 bottom is provided with bearing plate 1.3, arranges porose 1.4 on bearing plate 1.3; Boiler 1 bottom is connected with inverted cone-shaped slag notch 1.5, is connected with ring flange 1.6 on slag notch 1.5; Boiler 1 sidewall is provided with lighting-up tuyere 1.7;
Smelting furnace 2 is arranged on base 2.1; Base 2.1 can be set to tiltable type, is convenient to topple over.Smelting furnace 2 is set to respectively iron plate layer 2.2, fire brick layer 2.3, ventilating layer 2.4, stainless steel layer 2.5 from outside to inside; The bottom of stainless steel layer 2.5 is provided with corrosion resistant plate 2.6, and corrosion resistant plate 2.6 forms combustion chamber 2.7 with the bottom of stainless steel layer 2.5, and combustion chamber 2.7 is connected with pipeline 3; Being provided with igniting hole 2.8 stretches in combustion chamber 2.7 through iron plate layer 2.2, fire brick layer 2.3, ventilating layer 2.4, stainless steel layer 2.5 successively; Smelting furnace 2 tops can be provided with cover plate.
On pipeline 3, be provided with valve 3.1 and fire hole 3.2.
The utility model pipeline 3 is stainless steel tube, and diameter is 100mm ± 10mm.
The vertical range of the utility model lighting-up tuyere 1.7 distance from bottom bearing plates 1.3 is more than 300mm.
The aperture in the utility model hole 1.4 is 5mm-20mm.
The thickness of the utility model iron plate layer 2.2 is 10mm ± 2mm.
The thickness of the utility model fire brick layer 2.3 is 250mm ± 20mm.
The width of the utility model ventilating layer 2.4 is 100mm ± 10mm.
The thickness of the utility model stainless steel layer 2.5 is 100mm ± 10mm.
The height of the utility model combustion chamber 2.7 is 200mm ± 20mm.

Claims (9)

1. a gold ore agent preparation facilities, comprises boiler (1), smelting furnace (2); It is characterized in that, between boiler (1) and combustion furnace (2), adopt pipeline (3) to be connected; Boiler (1) is set to cylindrical shape; Top is provided with coal-in port (1.1), and upper end sidewall sets out gas port (1.2) and is connected with pipeline (3); Upper end sidewall is provided with watering mouthful (1.8); Boiler (1) bottom is provided with bearing plate (1.3), arranges porose (1.4) on bearing plate (1.3); Boiler (1) bottom is connected with inverted cone-shaped slag notch (1.5), is connected with ring flange (1.6) on slag notch (1.5); Boiler (1) sidewall is provided with lighting-up tuyere (1.7);
Smelting furnace (2) is arranged on base (2.1); Smelting furnace (2) is set to respectively iron plate layer (2.2), fire brick layer (2.3), ventilating layer (2.4), stainless steel layer (2.5) from outside to inside; The bottom of stainless steel layer (2.5) is provided with corrosion resistant plate (2.6), and corrosion resistant plate (2.6) forms combustion chamber (2.7) with the bottom of stainless steel layer (2.5), and combustion chamber (2.7) is connected with pipeline (3); Being provided with igniting hole (2.8) stretches in combustion chamber (2.7) through iron plate layer (2.2), fire brick layer (2.3), ventilating layer (2.4), stainless steel layer (2.5) successively;
On pipeline (3), be provided with valve (3.1) and fire hole (3.2).
2. a kind of gold ore agent preparation facilities according to claim 1, is characterized in that, pipeline (3) is stainless steel tube, and diameter is 100mm ± 10mm.
3. a kind of gold ore agent preparation facilities according to claim 1, is characterized in that, the vertical range of lighting-up tuyere (1.7) distance from bottom bearing plate (1.3) is more than 300mm.
4. a kind of gold ore agent preparation facilities according to claim 1, is characterized in that, the aperture of hole (1.4) is 5mm-20mm.
5. a kind of gold ore agent preparation facilities according to claim 1, is characterized in that, the thickness of iron plate layer (2.2) is 10mm ± 2mm.
6. a kind of gold ore agent preparation facilities according to claim 1, is characterized in that, the thickness of fire brick layer (2.3) is 250mm ± 20mm.
7. a kind of gold ore agent preparation facilities according to claim 1, is characterized in that, the width of ventilating layer (2.4) is 100mm ± 10mm.
8. a kind of gold ore agent preparation facilities according to claim 1, is characterized in that, the thickness of stainless steel layer (2.5) is 100mm ± 10mm.
9. a kind of gold ore agent preparation facilities according to claim 1, is characterized in that, the height of combustion chamber (2.7) is 200mm ± 20mm.
CN201420087362.4U 2014-02-28 2014-02-28 Gold dressing agent preparation device Expired - Fee Related CN203848666U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420087362.4U CN203848666U (en) 2014-02-28 2014-02-28 Gold dressing agent preparation device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420087362.4U CN203848666U (en) 2014-02-28 2014-02-28 Gold dressing agent preparation device

Publications (1)

Publication Number Publication Date
CN203848666U true CN203848666U (en) 2014-09-24

Family

ID=51561673

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420087362.4U Expired - Fee Related CN203848666U (en) 2014-02-28 2014-02-28 Gold dressing agent preparation device

Country Status (1)

Country Link
CN (1) CN203848666U (en)

Similar Documents

Publication Publication Date Title
CN204127954U (en) Gas ignition jet pipe and mineral hot furnace
CN203848666U (en) Gold dressing agent preparation device
CN204202415U (en) A kind of Novel galvanizing annealing furnace radiator tubes heat exchanger
CN104329935B (en) A kind of modified blast furnace
CN204141982U (en) A kind of resistance to deformation water cold electric furnace body of heater
CN204880693U (en) Unload convenient energy -conserving boiler of sediment
CN104110679A (en) Fuel gas ignition jet tube and submerged arc furnace utilizing same
CN202066016U (en) Burner for dead soaking pit
CN202561724U (en) Novel steam heating furnace
CN103216853A (en) Heating stove
CN203286590U (en) Heating furnace
CN204730641U (en) A kind of heating furnace
CN204177181U (en) A kind of modified Novel blast furnace
CN218262302U (en) Shaft kiln
CN103148517A (en) Heating furnace
CN203375481U (en) Coal furnace
CN206330424U (en) Crucible type magnesium alloy melting and heat preservation stove
CN207515518U (en) Biomass zinc-coated wire annealing furnace
CN201607119U (en) Novel light kiln
CN207418795U (en) A kind of blast funnace hot blast stove for preventing temperature excessively high
CN204373377U (en) A kind of gas-fired air furnace
CN205316663U (en) Initial heating hot -blast furnace of gas retort
CN204042963U (en) Be applicable to the oven roof sealing device of combustion chamber
CN205170388U (en) Fluidized bed furnace for sulfuric acid production
CN203964023U (en) A kind of top air intake type saving furnace

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20140924

Termination date: 20170228

CF01 Termination of patent right due to non-payment of annual fee