CN203821253U - Holding device for broadening and splicing concrete girder bridge - Google Patents

Holding device for broadening and splicing concrete girder bridge Download PDF

Info

Publication number
CN203821253U
CN203821253U CN201420198744.4U CN201420198744U CN203821253U CN 203821253 U CN203821253 U CN 203821253U CN 201420198744 U CN201420198744 U CN 201420198744U CN 203821253 U CN203821253 U CN 203821253U
Authority
CN
China
Prior art keywords
bridge
holding device
model
utility
broadening
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201420198744.4U
Other languages
Chinese (zh)
Inventor
任伟
陈榕峰
吕颖钊
盖轶婷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Changan University
Original Assignee
Changan University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Changan University filed Critical Changan University
Priority to CN201420198744.4U priority Critical patent/CN203821253U/en
Application granted granted Critical
Publication of CN203821253U publication Critical patent/CN203821253U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Abstract

The utility model discloses a holding device for broadening and splicing concrete girder bridge. The holding device comprises an upper beam and a lower beam which are held on the upper side and the lower side of a wet seam between a new bridge and an old bridge respectively, wherein steel plates are both fixed on the upper side and the lower side of the upper beam or the lower beam; the upper beam and the lower beam are connected through screws and nuts. The holding device disclosed by the utility model is safe, reliable, easy to control in quality, low in cost, simple in method, and convenient to popularize.

Description

A kind of concrete beam bridge is widened splicing clamping device
Technical field
The utility model belongs to concrete-bridge and widens concatenation construction technical field, and what be specifically related to is that a kind of concrete beam bridge is widened splicing clamping device.
Background technology
In current highway extension project project, the key link that bridge jointing is widened work is exactly the splicing of the old and new's bridge.But the feature due to highway extension project, in whole work progress, all cannot seal the traffic of original road completely, this has carried out great difficulty to new old bridge splicing tape, especially last one critical process---wet seam is built, close traffic state is not poured into a mould wet joint concrete, due to the directly formation of the wet joint concrete intensity of impact of bridge vibration of beam (changing of the relative positions of the old and new's structure).
Utility model content
The utility model object is to provide a kind of for highway extension project, carries out bridge widening concatenation construction concrete beam bridge and widen splicing clamping device in the situation that of close traffic not, and it can solve existing problem in background technology effectively.
In order to solve existing problem in background technology, it comprises top rail and the lower transverse beam that is clamped in new bridge and the upper and lower both sides of the wet seam crossing of old bridge, the both sides up and down of described top rail or lower transverse beam are all fixed with steel plate, between described top rail and lower transverse beam, by screw rod, are connected with nut.
Between described nut and steel plate, be provided with backing plate.
Owing to having adopted above technical scheme, the utlity model has following beneficial effect: safe and reliable, quality is easy to control, and cost is low, and method is simple, is convenient to promote.
Accompanying drawing explanation
In order to be illustrated more clearly in the utility model, below in conjunction with accompanying drawing, embodiment is briefly described.
Fig. 1 is mounting structure schematic diagram of the present utility model;
Fig. 2 is the A-A sectional view of Fig. 1;
Fig. 3 is stereogram of the present utility model;
Fig. 4 is local mounting structure schematic diagram of the present utility model.
The specific embodiment
For technological means, creation characteristic that the utility model is realized, reach object and effect is easy to understand, the accompanying drawing below in conjunction with in the utility model embodiment, is clearly and completely described the technical scheme in the utility model embodiment.
Referring to Fig. 1-4, this specific embodiment is to be achieved by the following technical solutions, it comprises top rail 1 and the lower transverse beam 2 that is clamped in new bridge and the upper and lower both sides of the wet seam crossing of old bridge, the both sides up and down of described top rail 1 or lower transverse beam 2 are all fixed with steel plate 3, between described top rail 1 and lower transverse beam 2, by screw rod 5, be connected with nut 4, diameter is not less than 28mm, the box-structure that utilizes channel-section steel 1 mirror set to be made into, the powerful resistance to tension of the bending resistance that its cross section is good and screw rod 5 clamps the old and new's bridge girder, reach the object of carrying out the old and new's Bridge Concatenation Construction and guaranteeing good splicing effect under the state that is open to traffic.
Between described nut 4 and steel plate 3, be provided with backing plate 6.
Owing to having adopted above technical scheme, the utlity model has following beneficial effect: safe and reliable, quality is easy to control, and cost is low, and method is simple, is convenient to promote.
Finally it should be noted that: above embodiment only, in order to the technical solution of the utility model to be described, is not intended to limit; Although the utility model is had been described in detail with reference to previous embodiment, those of ordinary skill in the art is to be understood that, its technical scheme that still can record aforementioned each embodiment is modified, or part technical characterictic is wherein equal to replacement; And these modifications or replacement do not make the essence of appropriate technical solution depart from the spirit and scope of each embodiment technical scheme of the utility model.

Claims (2)

1. a concrete beam bridge is widened splicing clamping device, it is characterized in that it comprises top rail and the lower transverse beam that is clamped in new bridge and the upper and lower both sides of the wet seam crossing of old bridge, the both sides up and down of described top rail or lower transverse beam are all fixed with steel plate, between described top rail and lower transverse beam, by screw rod, are connected with nut.
2. a kind of concrete beam bridge according to claim 1 is widened splicing clamping device, it is characterized in that being provided with backing plate between described nut and steel plate.
CN201420198744.4U 2014-04-18 2014-04-18 Holding device for broadening and splicing concrete girder bridge Expired - Fee Related CN203821253U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420198744.4U CN203821253U (en) 2014-04-18 2014-04-18 Holding device for broadening and splicing concrete girder bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420198744.4U CN203821253U (en) 2014-04-18 2014-04-18 Holding device for broadening and splicing concrete girder bridge

Publications (1)

Publication Number Publication Date
CN203821253U true CN203821253U (en) 2014-09-10

Family

ID=51476770

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420198744.4U Expired - Fee Related CN203821253U (en) 2014-04-18 2014-04-18 Holding device for broadening and splicing concrete girder bridge

Country Status (1)

Country Link
CN (1) CN203821253U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107119575A (en) * 2017-06-27 2017-09-01 余姚市绿波机械科技有限公司 A kind of bridge plate splicing clamp for being easy to clamping
CN111877194A (en) * 2020-09-08 2020-11-03 浙江世润建创科技发展有限公司 Manufacturing and using method of splicing clamp for new and old bridges

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107119575A (en) * 2017-06-27 2017-09-01 余姚市绿波机械科技有限公司 A kind of bridge plate splicing clamp for being easy to clamping
CN111877194A (en) * 2020-09-08 2020-11-03 浙江世润建创科技发展有限公司 Manufacturing and using method of splicing clamp for new and old bridges
CN111877194B (en) * 2020-09-08 2022-05-27 浙江世润建创科技发展有限公司 Manufacturing and using method of splicing clamp for new and old bridges

Similar Documents

Publication Publication Date Title
CN206591448U (en) Novel bridge widens bracing means
CN203821253U (en) Holding device for broadening and splicing concrete girder bridge
CN203795829U (en) Hoop assembly
CN203393625U (en) Staggered slab and staggered joint adjusting device for engineering steel templates
CN204753390U (en) Bridge construction support bracket
CN205587889U (en) Hydraulic pressure connecting rod is with assembling mould
CN203530849U (en) Limiting fixing tray for steel tube arch bridge arch rib installing
CN204825656U (en) Cast -in -place formwork support structure in bridge sound barrier basis
CN104060819B (en) Utilize the method for typified form construction shear wall and typified form used
CN204608576U (en) The positioner that a kind of precast concrete road kerb is installed
CN108166400A (en) A kind of great cantilever plane swivel structure and its construction method
CN203684672U (en) Column template clamp
CN204934989U (en) A kind of steel tower cross-arm welder
CN210637085U (en) Hydraulic trolley for lining
CN204530456U (en) A kind of Novel comb tooth plate stretching device anchor bolt
CN202688898U (en) Transverse position adjusting device for steel beam
CN206843957U (en) Bridge construction Rotary ball hinge apparatus for adjusting position
CN202055182U (en) Positioner for circular arc-shaped steel bar of pier
CN201826258U (en) Steel support buttress fixing device
CN205120486U (en) Experimental frock of welded steel fabric solder joint resistance to shear
CN203462403U (en) Reinforced cast-in-situ box girder template
CN204067028U (en) A kind of distribution transformer fuel tank locating pin jig of adjustable dimension
CN204195149U (en) Rail of semi-automatic cutting machine assists moulding bed
CN202192351U (en) Device for cutting H-section steel
CN203846836U (en) Cast-in-place concrete pool wall rubber water stop band reinforcing device

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20140910

Termination date: 20150418

EXPY Termination of patent right or utility model