CN203820810U - Improved blast furnace bottom cooling structure - Google Patents

Improved blast furnace bottom cooling structure Download PDF

Info

Publication number
CN203820810U
CN203820810U CN201420092806.3U CN201420092806U CN203820810U CN 203820810 U CN203820810 U CN 203820810U CN 201420092806 U CN201420092806 U CN 201420092806U CN 203820810 U CN203820810 U CN 203820810U
Authority
CN
China
Prior art keywords
blast furnace
water
tube
furnace bottom
forced air
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201420092806.3U
Other languages
Chinese (zh)
Inventor
宋志杰
蔡建新
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Baosteel Group Xinjiang Bayi Iron and Steel Co Ltd
Original Assignee
Baosteel Group Xinjiang Bayi Iron and Steel Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Baosteel Group Xinjiang Bayi Iron and Steel Co Ltd filed Critical Baosteel Group Xinjiang Bayi Iron and Steel Co Ltd
Priority to CN201420092806.3U priority Critical patent/CN203820810U/en
Application granted granted Critical
Publication of CN203820810U publication Critical patent/CN203820810U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Abstract

The utility model belongs to an improvement on an ironmaking blast furnace bottom cooling structure and particularly relates to an improved blast furnace bottom cooling structure comprising air cooling pipes uniformly distributed in the bottom of a blast furnace, wherein the air cooling pipes are internally provided with water cooling pipes with two sealed ends; each water cooling pipe located outside each air cooling pipe is provided with a water inlet and a water outlet; a sealing plate fixedly connected to an external port of each air cooling pipe is used for connecting and fixing the water cooling pipes; the sealing plate and a shell of the blast furnace are connected into a whole; the sealing plate is provided with a grouting hole and an air outlet; the grouting hole is provided with a grouting pipe with one end extending into the inner end of each air cooling pipe; and each air cooling pipe is internally provided with a thermocouple. The improved blast furnace bottom cooling structure is reasonable in structure and can be used for improving the cooling function of the bottom of the blast furnace, reducing the temperature of the bottom of the blast furnace, monitoring the temperature change at the bottom of the blast furnace and ensuring the safe operation of the bottom of the blast furnace.

Description

The cooling structure of improved Blast Furnace Bottom
Technical field
The utility model belongs to the cooling structure of the improvement to iron-smelting blast furnace furnace bottom cooling structure, particularly a kind of improved Blast Furnace Bottom.
Background technology
In iron-smelting blast furnace maintenance process, find that the uniform forced air cooled tube of furnace bottom is because cupola well carbon brick subsides, cause forced air cooled tube distortion to subside, cooling air cannot carry out by furnace bottom forced air cooled tube cooling to furnace bottom, and there is very large hidden danger in the safe operation of cupola well therefore.Forced air cooled tube subsides and can cause furnace bottom forced air cooled tube cooling power to decline, as monitors not in placely, can be further worsens, and causes that forced air cooled tube stops up, cracking, finally may cause sudden burn-through of furnace hearth accident.
Utility model content
The purpose of this utility model is to provide a kind of cooling structure of improved Blast Furnace Bottom, it is rational in infrastructure, can improve the refrigerating function of Blast Furnace Bottom, reduces the temperature of Blast Furnace Bottom, and can monitor the temperature variation of Blast Furnace Bottom, ensure the safe operation of Blast Furnace Bottom.
The purpose of this utility model is achieved in that a kind of cooling structure of improved Blast Furnace Bottom, be included in the forced air cooled tube of uniform setting in Blast Furnace Bottom, the water cooling tube of closed at both ends is installed in forced air cooled tube, be positioned on the water cooling tube of forced air cooled tube outside water-in and water outlet are being set, shrouding affixed in the external port of forced air cooled tube is connected and fixed water cooling tube, shrouding and last furnace shell are connected as a single entity, grouting mouth and air outlet are being set on shrouding, the grout pipe that one end is being set gos deep into forced air cooled tube the inner in grouting mouthful is installed with thermopair in forced air cooled tube.
The utility model is transformed enforcement successively to 20 of Blast Furnace Bottom forced air cooled tubes, to the water cooling tube of closed at both ends be installed in forced air cooled tube, water-in and water outlet are being set on the water cooling tube being positioned at outside forced air cooled tube, shrouding affixed in the external port of forced air cooled tube is fixed water cooling tube, shrouding and last furnace shell are connected as a single entity, grouting mouth and air outlet are being set on shrouding, on grouting mouth, the grout pipe that gos deep into water cooling tube the inner are being set, thermopair is being installed in forced air cooled tube.Be in the milk, grouting requires the air outlet grout of must being in the milk, and after the grout of grouting air outlet, tightens thermopair base, connects the pipeline of water cooling tube import and export.
The utility model is owing to taking above technical scheme, and it has the following advantages:
1, recovered the function at the bottom of the cool furnace of furnace bottom forced air cooled tube.
2, by the air-cooled water-cooled that changes into, improve the cooling power of furnace bottom, force cooling to furnace bottom subsidence area.
3, ensured the safe operation of State of Blast Furnace labour later stage cupola well.
4, simple in structure, easy to implement.Can carry out gradation transformation to 20 forced air cooled tubes of furnace bottom implements.
5, the later stage is easy to safeguard, checks.
The utility model is rational in infrastructure, has realized the refrigerating function that improves Blast Furnace Bottom, has reduced the temperature of Blast Furnace Bottom, and has realized the temperature variation of Blast Furnace Bottom is monitored, and has ensured the safe operation of Blast Furnace Bottom.
Brief description of the drawings
Below in conjunction with accompanying drawing, the utility model is further described, Fig. 1 is structural representation of the present utility model.
Embodiment
A kind of cooling structure of improved Blast Furnace Bottom, as shown in Figure 1, be included in the forced air cooled tube 2 of uniform setting in Blast Furnace Bottom, the water cooling tube 4 of closed at both ends is installed in forced air cooled tube 2, be positioned on the water cooling tube 4 of forced air cooled tube 2 outsides water-in and water outlet 8 are being set, shrouding affixed in the external port of forced air cooled tube 2 is connected and fixed water cooling tube 4, shrouding and last furnace shell 1 are connected as a single entity, grouting mouth and air outlet 7 are being set on shrouding, the grout pipe 3 that one end is being set gos deep into forced air cooled tube 2 the inners in grouting mouthful is installed with thermopair 6 in forced air cooled tube 2.The water-in of water cooling tube 4 is arranged on the outer end end wall of water cooling tube 4, affixed the water inlet pipe 5 that gos deep into water cooling tube 4 the inners on water-in, and water outlet 8 is arranged on the tube wall of water cooling tube 4 outer ends.The inner end of water inlet pipe 5 is apart from the bottom 100-200mm of water cooling tube 4.The diameter of water cooling tube 4 is 76mm, and the diameter of water inlet pipe 5 is 42mm.What be positioned at forced air cooled tube 2 bottoms is a point cold blockage thing 9.

Claims (4)

1. the cooling structure of an improved Blast Furnace Bottom, be included in the forced air cooled tube (2) of uniform setting in Blast Furnace Bottom, it is characterized in that: the water cooling tube (4) that closed at both ends is installed in forced air cooled tube (2), be positioned on the outside water cooling tube (4) of forced air cooled tube (2) water-in and water outlet (8) are being set, shrouding affixed in the external port of forced air cooled tube (2) is connected and fixed water cooling tube (4), shrouding and last furnace shell (1) are connected as a single entity, grouting mouth and air outlet (7) are being set on shrouding, one end is being set on grouting mouth and is going deep into the inner grout pipe (3) of forced air cooled tube (2), thermopair (6) is installed in forced air cooled tube (2).
2. the cooling structure of a kind of improved Blast Furnace Bottom according to claim 1, it is characterized in that: the water-in of water cooling tube (4) is arranged on the outer end end wall of water cooling tube (4), affixed the inner water inlet pipe (5) of water cooling tube (4) that gos deep on water-in, water outlet (8) is arranged on the tube wall of water cooling tube (4) outer end.
3. the cooling structure of a kind of improved Blast Furnace Bottom according to claim 2, is characterized in that: the inner end of water inlet pipe (5) is apart from the bottom 100-200mm of water cooling tube (4).
4. the cooling structure of a kind of improved Blast Furnace Bottom according to claim 2, is characterized in that: the diameter of water cooling tube (4) is 76mm, and the diameter of water inlet pipe (5) is 42mm.
CN201420092806.3U 2014-03-03 2014-03-03 Improved blast furnace bottom cooling structure Expired - Fee Related CN203820810U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420092806.3U CN203820810U (en) 2014-03-03 2014-03-03 Improved blast furnace bottom cooling structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420092806.3U CN203820810U (en) 2014-03-03 2014-03-03 Improved blast furnace bottom cooling structure

Publications (1)

Publication Number Publication Date
CN203820810U true CN203820810U (en) 2014-09-10

Family

ID=51476330

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420092806.3U Expired - Fee Related CN203820810U (en) 2014-03-03 2014-03-03 Improved blast furnace bottom cooling structure

Country Status (1)

Country Link
CN (1) CN203820810U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106065424A (en) * 2016-08-25 2016-11-02 陈学红 A kind of blast furnace cooling stave
CN111424133A (en) * 2020-05-15 2020-07-17 宁夏诚安顺祥冶金工程技术服务有限公司 Novel composite air-cooled durable silicomanganese furnace
CN113957189A (en) * 2021-10-15 2022-01-21 上海宝冶冶金工程有限公司 Grouting construction method for water-cooled tube at furnace bottom

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106065424A (en) * 2016-08-25 2016-11-02 陈学红 A kind of blast furnace cooling stave
CN111424133A (en) * 2020-05-15 2020-07-17 宁夏诚安顺祥冶金工程技术服务有限公司 Novel composite air-cooled durable silicomanganese furnace
CN113957189A (en) * 2021-10-15 2022-01-21 上海宝冶冶金工程有限公司 Grouting construction method for water-cooled tube at furnace bottom
CN113957189B (en) * 2021-10-15 2023-02-21 上海宝冶冶金工程有限公司 Grouting construction method for furnace bottom water-cooled tube

Similar Documents

Publication Publication Date Title
CN203820810U (en) Improved blast furnace bottom cooling structure
CN109022789B (en) Titanium sponge reduction distillation system with straight passageway
CN203550609U (en) Water cooling plant for submerged arc furnace
CN106190189B (en) High-efficient waste heat recovery device of coke oven raw gas tedge
CN204115519U (en) A kind of built-in lower perforated plate formula graphite heat exchanger
CN203629172U (en) High-temperature cooling water jacket for camera in furnace
CN203855414U (en) Tubular graphitization furnace
CN205403462U (en) A cooling device and system for soft magnetic ferrite sintering high -temperature gas
CN204824714U (en) Coke oven crude gas waste heat recovery heat transfer device
CN202582201U (en) Cooling plate for metallurgical furnace
CN204115528U (en) A kind of lower supporting type graphite heat exchanger
CN206843528U (en) RH stoves wind rubber seal with the fire resisting of glass heatproof
CN203489668U (en) Vacuum induction cold crucible casting device
CN204027347U (en) The voltage loss protecting system of water cooling plant
CN203556361U (en) Glass reaction kettle
CN201810919U (en) Gland-free type telescopic device
CN204874635U (en) Intensive condenser tube structure of wind gap cooling wall
CN203820811U (en) Device for improving cooling intensity of blast furnace bottom
CN204555771U (en) Many housing moduleizations Multi-stage heat pipe exchanger
CN201599797U (en) Cooling device of lime kiln burner
CN203346427U (en) Alumina-magnesite carbon brick for converters
CN103994656B (en) Cooling Section of Tunnel Kiln heat pipe heat exchanging system and using method thereof
CN202660540U (en) Circulating fluidized bed boiler water-cooling furnace top
CN204301539U (en) A kind of high-temperature furnace gas water-cooled cooling equipment
CN203203412U (en) Mechanical cooler capable of achieving waste heat utilization

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20140910

Termination date: 20150303

EXPY Termination of patent right or utility model