CN203742047U - Storage room with detachable roof - Google Patents

Storage room with detachable roof Download PDF

Info

Publication number
CN203742047U
CN203742047U CN201420015905.1U CN201420015905U CN203742047U CN 203742047 U CN203742047 U CN 203742047U CN 201420015905 U CN201420015905 U CN 201420015905U CN 203742047 U CN203742047 U CN 203742047U
Authority
CN
China
Prior art keywords
plate
shaped frame
roof
frame
room
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN201420015905.1U
Other languages
Chinese (zh)
Inventor
王幼军
运志涛
宋胜利
杨怀远
程超
吴必华
陈俊
饶冰
杨彪
曹萍
汪志彬
江飞
李志�
史华军
徐佳佳
吴晟
李翠红
薛睿韬
赵阳阳
李克白
乐党救
林小兵
虞媛
张宽
曹豫岩
吕文娟
陈乐�
陈正时
田玉清
赵衡
王童威
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
North China Power Engineering Co Ltd of China Power Engineering Consulting Group
Northwest Electric Power Design Institute of China Power Engineering Consulting Group
Southwest Electric Power Design Institute Co Ltd of China Power Engineering Consulting Group
China Power Engineering Consulting Group East China Electric Power Design Institute Co Ltd
China Power Engineering Consultant Group Central Southern China Electric Power Design Institute Corp
Northeast Electric Power Design Institute of China Power Engineering Consulting Group
Original Assignee
Northwest Electric Power Design Institute of China Power Engineering Consulting Group
Southwest Electric Power Design Institute Co Ltd of China Power Engineering Consulting Group
China Power Engineering Consulting Group East China Electric Power Design Institute Co Ltd
China Power Engineering Consultant Group Central Southern China Electric Power Design Institute Corp
Northeast Electric Power Design Institute of China Power Engineering Consulting Group
North China Electric Power Design Institute of China Power Engineering Consulting Group Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Northwest Electric Power Design Institute of China Power Engineering Consulting Group, Southwest Electric Power Design Institute Co Ltd of China Power Engineering Consulting Group, China Power Engineering Consulting Group East China Electric Power Design Institute Co Ltd, China Power Engineering Consultant Group Central Southern China Electric Power Design Institute Corp, Northeast Electric Power Design Institute of China Power Engineering Consulting Group, North China Electric Power Design Institute of China Power Engineering Consulting Group Corp filed Critical Northwest Electric Power Design Institute of China Power Engineering Consulting Group
Priority to CN201420015905.1U priority Critical patent/CN203742047U/en
Application granted granted Critical
Publication of CN203742047U publication Critical patent/CN203742047U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Working Measures On Existing Buildindgs (AREA)

Abstract

The utility model discloses a storage room with a detachable roof. The room comprises a main frame composed of a plurality of steel beams, and the roof covering the main frame, wherein the roof is composed of two plate-shaped frame bodies which are arranged in an inclined mode, the top ends of the two plate-shaped frame bodies are connected to form a ridge, lifting lugs are arranged on the upper surfaces of the plate-shaped frame bodies, a horizontally-arranged rectangular frame is connected below the plate-shaped frame bodies, the rectangular frame is connected with the main frame through a bolt component, and a plurality of supporting beams attached to the lower surfaces of the plate-shaped frame bodies are arranged on the inner side of the rectangular frame. The assembled type steel structure building type is adopted, the room is arranged locally, construction is easy and convenient, occupied land is saved, the requirement of a standby smoothing reactor for temperature and humidity storage can be met with the small investment, the roof can be wholly hung and dismantled, equipment can be hung out of the roof, and does not need to be carried out of a gate of the room, the size of the storage room is greatly reduced, the construction cost of the storage room is saved, the equipment is convenient to hang, and the equipment can be conveniently put into operation, used and operated.

Description

Between detachable roof formula stores
Technical field
The utility model relates to a kind of detachable building, between referring to that particularly a kind of detachable roof formula stores.
Background technology
The smoothing reactor for subsequent use of current conversion station is often outdoor is at present placed on the spot power distribution equipment region or is placed in the interior storeroom of spare product and part in station.Smoothing reactor for subsequent use is outdoor placement the application life that can reduce smoothing reactor for subsequent use on the spot often; Be placed in the interior storeroom of spare product and part in station, take up room larger, reduced the storage area of the storeroom of spare product and part, and the humiture of storeroom of spare product and part inside is had higher requirements, output investment ratio is larger.If set up a storage area for smoothing reactor separately, the access size of storage area is larger, facilitate smoothing reactor transport, and convenient for a dead lift, the space in storage area is also greater than the volume of smoothing reactor, and these have all increased cost.
Utility model content
The storage area volume that the purpose of this utility model is to overcome the medium-and-large-sized equipment of prior art is large, builds and the high defect of maintenance cost, provides the little and main equipment of a kind of volume to pick and place between detachable roof formula stores easily.
For achieving the above object, between the designed detachable roof formula of the utility model stores, comprise the main body frame being formed by many girder steels, with the roof covering on main body frame, described roof is made up of two plate-shaped frames that are in tilted layout, the top of two boards shape framework engages formation ridge, the upper surface of described plate-shaped frame is provided with hanger, described plate-shaped frame below is connected with the rectangle frame of horizontal arrangement, described rectangle frame is connected with main body frame by bolt assembly, described rectangle frame inner side be also provided with the many brace summers that are fitted in plate-shaped frame soffit.
Preferably, described hanger is arranged on the bottom of plate-shaped frame.
Preferably, described girder steel and brace summer are H section steel beam.
Preferably, described plate-shaped frame is connected with rectangle frame by the many dowels of vertically arranging.
Preferably, on described plate-shaped frame, be coated with sandwiched plate roofing.
Preferably, the side of described main body frame is coated with sandwiched plate metope.
The beneficial effects of the utility model: between detachable roof formula stores, adopt assembling type steel structure type of construction, arrange on the spot, easy construction, save and take up an area, less input just can meet the requirement of smoothing reactor for subsequent use storage humiture, and roof can integral hoisting and dismounting, equipment can hang out from roof, do not need to take out of by gate, room, volume between greatly reducing to store, saves cost between storage, and hanging device is convenient, for being used operation, equipment investment operation provides convenience.
Brief description of the drawings
Fig. 1 is the structural representation between detachable roof formula of the present utility model stores.
Fig. 2 is the sectional structure schematic diagram of Fig. 1.
Fig. 3 is the structure for amplifying schematic diagram of roof edge in Fig. 2.
Detailed description of the invention
Below in conjunction with the drawings and specific embodiments, the utility model is described in further detail.
As shown in Figures 1 to 3, between detachable roof formula stores, comprise the main body frame 1 being formed by many girder steels 8, with the roof 2 covering on main body frame 1, roof 2 is made up of two plate-shaped frames that are in tilted layout 3, the top of two boards shape framework 3 engages formation ridge, and the upper surface of plate-shaped frame 3 is provided with hanger 4, and hanger 4 is arranged on the bottom of plate-shaped frame 3.Plate-shaped frame 3 belows are connected with the rectangle frame 7 of horizontal arrangement, plate-shaped frame 3 is connected with rectangle frame 7 by the many dowels 11 of vertically arranging, rectangle frame 7 is connected with main body frame 1 by bolt assembly 6, rectangle frame 7 inner sides be also provided with the many brace summers 5 that are fitted in plate-shaped frame 3 soffits.
Girder steel 8 and brace summer 5 are H section steel beam.On plate-shaped frame 3, be coated with sandwiched plate roofing 9.The side of main body frame 1 is coated with sandwiched plate metope 10.
While using between above-mentioned detachable roof formula storage, the bolt assembly 6 between rectangle frame 7 and main body frame 1 is removed, crane hook is hung on hanger 4, just can complete hanging of roof 2, and then smoothing reactor for subsequent use just can recall the use that puts into operation easily.

Claims (6)

1. between a detachable roof formula stores, comprise the main body frame (1) being formed by many girder steels (8), with the roof (2) covering on main body frame (1), it is characterized in that: described roof (2) are made up of two plate-shaped frames that are in tilted layout (3), the top of two boards shape framework (3) engages formation ridge, the upper surface of described plate-shaped frame (3) is provided with hanger (4), described plate-shaped frame (3) below is connected with the rectangle frame (7) of horizontal arrangement, described rectangle frame (7) is connected with main body frame (1) by bolt assembly (6), described rectangle frame (7) inner side be also provided with the many brace summers (5) that are fitted in plate-shaped frame (3) soffit.
2., between detachable roof formula according to claim 1 stores, it is characterized in that: described hanger (4) is arranged on the bottom of plate-shaped frame (3).
3., between detachable roof formula according to claim 1 stores, it is characterized in that: described girder steel (8) and brace summer (5) are H section steel beam.
4. between detachable roof formula according to claim 1 stores, it is characterized in that: described plate-shaped frame (3) is connected with rectangle frame (7) by the many dowels (11) of vertically arranging.
5., between storing according to the detachable roof formula described in claim 1~4 any one, it is characterized in that: on described plate-shaped frame (3), be coated with sandwiched plate roofing (9).
6., between storing according to the detachable roof formula described in claim 1~4 any one, it is characterized in that: the side of described main body frame (1) is coated with sandwiched plate metope (10).
CN201420015905.1U 2014-01-10 2014-01-10 Storage room with detachable roof Expired - Lifetime CN203742047U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420015905.1U CN203742047U (en) 2014-01-10 2014-01-10 Storage room with detachable roof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420015905.1U CN203742047U (en) 2014-01-10 2014-01-10 Storage room with detachable roof

Publications (1)

Publication Number Publication Date
CN203742047U true CN203742047U (en) 2014-07-30

Family

ID=51341866

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420015905.1U Expired - Lifetime CN203742047U (en) 2014-01-10 2014-01-10 Storage room with detachable roof

Country Status (1)

Country Link
CN (1) CN203742047U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106894561A (en) * 2017-04-18 2017-06-27 中船第九设计研究院工程有限公司 A kind of detachable steel structure Roof
CN106992437A (en) * 2016-01-20 2017-07-28 Ls 产电株式会社 Power distribution cabinet

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106992437A (en) * 2016-01-20 2017-07-28 Ls 产电株式会社 Power distribution cabinet
CN106992437B (en) * 2016-01-20 2020-09-15 Ls 产电株式会社 Power distribution cabinet
CN106894561A (en) * 2017-04-18 2017-06-27 中船第九设计研究院工程有限公司 A kind of detachable steel structure Roof

Similar Documents

Publication Publication Date Title
CN103526949A (en) Lifting and slipping device for wall-attached vertical structure and construction method thereof
CN202530571U (en) Box type house convenient to dismount and mount
CN203742047U (en) Storage room with detachable roof
CN203247868U (en) Large-span steel structure construction temporary supporting frame
CN204626998U (en) A kind of attached lift scaffold discharging platform
CN204001416U (en) For the assemble type truss of the factory building of constructing
CN205000518U (en) Take combination formula floor board in stair hole
CN204342306U (en) A kind of novel roofing crane foundation
CN203187296U (en) Box type girder overturning device
CN204357138U (en) Simple steel structure lifting upending frame
CN205171997U (en) Concrete structure holds in palm on early system top of tearing open
CN204579313U (en) A kind of vegetables heat preservation greenhouse
CN203782987U (en) Thermal-insulation energy-saving roof boarding
CN204224149U (en) Steel structure secondary member hoisting device
CN204173796U (en) A kind of Novel sling
CN204938748U (en) A kind of crane girder inner supporting structure
CN203716512U (en) Building insulation shed
CN203878957U (en) Protective screen module unit
CN205000517U (en) Modular shingle
CN105201218A (en) Top strut used for assembling container house
CN203865425U (en) Board turning-over machine special for building wallboards
CN205777434U (en) A kind of hoistway operation rack device
CN205476531U (en) Big load core section of thick bamboo hydraulic lifting material platform
CN203903793U (en) Gantry hoisting frame applied to heavy equipment
CN204738426U (en) Stone material edge list socket formula hoist and mount curtain

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee

Owner name: CENTRAL SOUTHERN CHINA ELECTRIC POWER DESIGN INSTI

Free format text: FORMER NAME: CENTRAL SOUTHERN CHINA ELECTRIC POWER DESIGN INSTITUTE, CHINA POWER ENGINEERING CONSULTING GROUP COR

CP03 Change of name, title or address

Address after: 430071 No. 668, democracy Road, Wuchang District, Hubei, Wuhan

Patentee after: CENTRAL SOUTHERN CHINA ELECTRIC POWER DESIGN INSTITUTE OF CHINA POWER ENGINEERING CONSULTING Group Corp.

Patentee after: NORTHEAST ELECTRIC POWER DESIGN INSTITUTE CO., LTD. OF CHINA POWER ENGINEERING CONSULTING Group

Patentee after: EAST CHINA ELECTRIC POWER DESIGN INSTITUTE CO., LTD. OF CHINA POWER ENGINEERING CONSULTING Group

Patentee after: NORTHWEST ELECTRIC POWER DESIGN INSTITUTE CO., LTD. OF CHINA POWER ENGINEERING CONSULTING Group

Patentee after: Southwest Electric Power Design Institute CO., Ltd. of China Power Engineering Consulting Group

Patentee after: NORTH CHINA POWER ENGINEERING CO., LTD. OF CHINA POWER ENGINEERING CONSULTING Group

Address before: 430071 Power Engineering Company of Zhongnan Power Design Institute, 668 Democratic Road, Wuchang District, Hubei, Wuhan

Patentee before: CENTRAL SOUTHERN CHINA ELECTRIC POWER DESIGN INSTITUTE, CHINA POWER ENGINEERING CONSULTING Group Corp.

Patentee before: NORTHEAST ELECTRIC POWER DESIGN INSTITUTE OF CHINA POWER ENGINEERING CONSULTING Group

Patentee before: CHINA POWER ENGINEERING CONSULTING Group CORPORATION EAST CHINA ELECTRIC POWER DESIGN INSTITUTE

Patentee before: NORTHWEST ELECTRIC POWER DESIGN INST. OF CHINA POWER ENGINEERING CONSULTING Group

Patentee before: SOUTHWEST ELECTRIC POWER DESIGN INSTITUTE OF CHINA POWER ENGINEERING CONSULTING Group Corp.

Patentee before: NORTH CHINA POWER ENGINEERING CO., LTD. OF CHINA POWER ENGINEERING CONSULTING Group

CX01 Expiry of patent term

Granted publication date: 20140730

CX01 Expiry of patent term