CN203741871U - Underground space building structure - Google Patents

Underground space building structure Download PDF

Info

Publication number
CN203741871U
CN203741871U CN201420044337.8U CN201420044337U CN203741871U CN 203741871 U CN203741871 U CN 203741871U CN 201420044337 U CN201420044337 U CN 201420044337U CN 203741871 U CN203741871 U CN 203741871U
Authority
CN
China
Prior art keywords
pile body
presstressed reinforcing
bearing structure
reinforcing steel
underground space
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN201420044337.8U
Other languages
Chinese (zh)
Inventor
刘献刚
付豫楹
熊小林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201420044337.8U priority Critical patent/CN203741871U/en
Application granted granted Critical
Publication of CN203741871U publication Critical patent/CN203741871U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model relates to an underground space building structure. The underground space building structure comprises a space bottom used as a building foundation and a space top connected with the ground. The space top is at least provided with a first part used for bearing large pressure and a second part used for bearing small pressure, and the difference value of the first force difference between the buoyancy and pressure borne by the second part and the second force difference between the buoyancy and pressure borne by the first part is larger than the maximum breaking-resistant strength of the joint position of the two parts. A first pile body set and a second pile body set are further included, the first pile body set and the second pile body set are arranged under the first part and the second part respectively and used for supporting and fixing the first part and the second part respectively, and therefore it is guaranteed that the force difference of the buoyancy and pressure borne by the second part is smaller than the maximum breaking-resistant strength and the maximum tensile resistance of the second pile body set.

Description

A kind of underground space building structure
Technical field
The utility model relates to a kind of building structure, particularly a kind of underground space building structure.
Background technology
At present, along with the development of economic society, increasing highrise building appears in the middle of our city, but along with the increase of building quantity in the middle of city, available space is more and more in short supply, and just because of so, the development and utilization of the underground space has more and more been obtained attention.As shown in Figure 1, the common underground space 9, all be positioned at high-rise building 14 under, and there is darker longitudinal space, the underground space 9 generally includes as the space bottom 11 of ground and the top of space 10 of joining with ground, some pile body one end of stretching in soil are supported and fix bottom, described space, the other end is deep into underground being supported on rock stratum 15, and the top of space that carries above-ground structures or other object can be supported on bottom, described space 11 by column 12.In the time that bottom, described space 11 has been subject to different downward pressures, can there is the Part I 17 that bears heavier pressure and the Part II 18 that bears lighter pressure.But, the underground space 9 has formed Ship Structure in soil, owing to thering is moisture content in soil, this soil with moisture can produce buoyancy to the underground space of Ship Structure 9, the buoyancy that described Part II 18 is subject to and the difference of pressure are first definitely stressed, the buoyancy that described Part I 17 is subject to and the difference of pressure are second definitely stressed, in the time of the maximum fracture resistence force at the described first definitely stressed and the second absolute poor junction surface that is greater than two parts of power between stressed, this Part I 17 and Part II 18 in the vertical direction generation relative displacements, junction surface B point place there will be situation about fractureing as the position the most easily fractureing, wherein, to be space bottom 11 be not subject to any pressure and buoyancy time space bottom 11 can keep the maximum, force of not finding that fracture can bear to this maximum fracture resistence force.The use of conventional pile body 13 can be by preventing that by the mode pulling Part I 71 from Part II 18, relative length travel occurring to bottom, space 11, but, conventional pile body 13 tension cracking resistances are poor, and meeting is in the vertical direction generation cracking situation because the underground space 9 buoyancy are excessive, this be because conventional pile body excessive under the effect of buoyancy, the effect of the inner reinforcing bar tension of conventional pile body 13 power is extended, and pile body cracking of reinforced concrete is poor, thereby can cause pile body to occur cracking.Excessive by drawing crack because of buoyancy in order to prevent pile body, in existing form of construction work, conventionally adopt the mode that increases pile body, or adopt and there is the pile body of more reinforcing bar, thereby prevent that pile body is by drawing crack.
But, the quantity that rolls up conventional pile body can cause construction period long and improve building costs, if in the situation that not increasing pile body quantity, increases the reinforcing bar number of pile body inside, although also can improve pile body crack resistance, increase reinforcing bar number and also can increase building costs.
Utility model content
For this reason, the technical problems to be solved in the utility model is, propose a kind of bottom, space point that can avoid the underground space that is subject to different downward pressures and occur fracture, and accelerating construction progress and the underground space building structure that reduces costs largely.
Underground space building structure of the present utility model, comprising:
As the bottom, space of building lot and the top of space of joining with ground, described top of space at least has the Part I that bears heavier pressure and the Part II that bears lighter pressure; Difference between the second power between buoyancy and pressure that the poor and described Part I of the first power between the buoyancy that wherein said Part II is subject to and pressure is subject to is poor is greater than the maximum fracture resistence force at the junction surface of two parts;
Also comprise the first pile body group and the second pile body group, be arranged at respectively described Part I and described Part II vertically below, and respectively described Part I and described Part II supported and fixed, thereby guaranteeing the poor maximum stretching resistance that is less than described maximum fracture resistence force and described the second pile body group of power of the suffered buoyancy of Part II and the pressure that is subject to;
Wherein, described the second pile body group comprises some comprehensive function pile bodies, and described comprehensive function pile body comprises concrete pile body, and described concrete pile body has top and bottom; Also comprise bearing structure, described bearing structure is located at the top of described concrete pile body; In described concrete pile body, be provided with reinforcing cage and presstressed reinforcing steel, wherein, one end of described presstressed reinforcing steel is fixed on described reinforcing cage one end near described concrete pile body bottom, and the other end of described presstressed reinforcing steel is anchored on described bearing structure; Described presstressed reinforcing steel, in tensile state, is realized the compression to concrete pile body by described bearing structure.
Above-mentioned underground space building structure, described presstressed reinforcing steel is some, and along described concrete pile axon to being evenly arranged.
Above-mentioned underground space building structure, is attached with separation layer on described presstressed reinforcing steel, and described separation layer carries out physical isolation to described presstressed reinforcing steel and described concrete pile body, thereby after making bearing structure reach the length of time, described presstressed reinforcing steel can be by tension.
Above-mentioned underground space building structure, described bearing structure inside is provided with sheet steel pipe and steel mesh reinforcement, and described sheet steel pipe is connected with described bearing structure and described steel mesh reinforcement stationary positioned, and wherein, described presstressed reinforcing steel is located at described sheet steel pipe inside.
Above-mentioned underground space building structure, described presstressed reinforcing steel is steel tendon, steel strand or cable wire rope.
Above-mentioned underground space building structure, described bearing structure is cushion cap, described cushion cap comprises concrete floor and concrete cushion; Described bearing structure is provided with for presstressed reinforcing steel being anchored in to the fixed part on described bearing structure.
Above-mentioned underground space building structure, described bearing structure is base plate.
The utility model has the following advantages with respect to prior art:
1. below described Part I, be provided for the first pile body group that described Part I is supported and fixed, and below described Part II, be provided for the second pile body group that described Part II is supported and fixed, thereby guarantee the poor maximum stretching resistance that is less than described maximum fracture resistence force and described the second pile body group of power of the suffered buoyancy of Part II and the pressure that is subject to; Described the second pile body group comprises some comprehensive function pile bodies, and described comprehensive function pile body comprises concrete pile body, and described concrete pile body has top and bottom; Also comprise bearing structure, described bearing structure is located at the top of described concrete pile body; In described concrete pile body, be provided with reinforcing cage and presstressed reinforcing steel, wherein, one end of described presstressed reinforcing steel is fixed on described reinforcing cage one end near described concrete pile body bottom, and the other end of described presstressed reinforcing steel is anchored on described bearing structure; Described presstressed reinforcing steel, in tensile state, is realized the compression to concrete pile body by described bearing structure.More than in design, in comprehensive function pile body, add presstressed reinforcing steel, even while being subject to larger longitudinal pulling force, due to the effect of presstressed reinforcing steel, can prevent well that the reinforcing bar of pile body inside from extending, thereby can greatly strengthen the tension cracking resistance of pile body; And in the time that bottom, described space at least has the maximum fracture resistence force at the Part II that bears the Part I of heavier pressure and bear lighter pressure and the described first definitely stressed and the second absolute poor junction surface that is greater than two parts of power between stressed, this pile body is set under the Part II that is subject to lighter pressure, can reduce under the prerequisite of pile body quantity compared to existing technology, can effectively prevent that the situation of fracture occurs at the junction surface of described Part I and described Part II, and then under the prerequisite of guaranteeing workmanship, the construction speed of greatly having accelerated and reduce construction cost.
2. what the construction method more than was carried out comprehensive function stake by the mode of in-site pouring waters post pile, can greatly increase the anti-floating performance of pile body in soil inside, in addition, reach after design age at concrete, by anchor undercut seat adopt a tension equipment presstressed reinforcing steel is carried out to tension, the tension crack resistance of comprehensive function stake can be under the prerequisite that does not increase reinforcing bar use amount, effectively increased, the manufacturing cost with high tensile crack resistance comprehensive function pile body can be greatly saved.Therefore this comprehensive function stake, providing in the utility model can and possess good anti-floating performance and tension cracking resistance in original better pressure resistance simultaneously.
Brief description of the drawings
For content of the present utility model is more likely to be clearly understood, according to specific embodiment of the utility model also by reference to the accompanying drawings, the utility model is described in further detail below, wherein:
Fig. 1 is the structural representation of the underground space in prior art;
Fig. 2 is the structural representation of the underground space of the utility model the first embodiment;
Fig. 3 is the structural representation of the utility model comprehensive function pile body;
Detailed description of the invention
Embodiment 1
As shown in Figure 2, a kind of underground space building structure, comprising:
As the space bottom 11 of building lot and the top of space 10 of joining with ground, described top of space 10 at least has the Part I 17 that bears heavier pressure and the Part II 18 that bears lighter pressure; Difference between the second power between buoyancy and pressure that the poor and described Part I of the first power between the buoyancy that wherein said Part II is subject to and pressure is subject to is poor is greater than the maximum fracture resistence force at the junction surface of two parts;
Also comprise the first pile body group 13 and the second pile body group 16, be arranged at respectively described Part I 17 and described Part II 18 vertically below, and respectively described Part I 17 and described Part II 18 supported and fixed, thereby guaranteeing the poor maximum stretching resistance that is less than described maximum fracture resistence force and described the second pile body group of power of the suffered buoyancy of Part II and the pressure that is subject to;
Wherein, described the second pile body group 16 comprises some comprehensive function pile bodies, and as shown in Figure 3, described comprehensive function pile body comprises concrete pile body 1, and described concrete pile body 1 has top and bottom; Also comprise bearing structure, described bearing structure is located at the top of described concrete pile body 1; In described concrete pile body 1, be provided with reinforcing cage 8 and presstressed reinforcing steel 2, wherein, one end of described presstressed reinforcing steel 2 is fixed on described reinforcing cage 8 one end near described concrete pile body 1 bottom, and the other end of described presstressed reinforcing steel 2 is anchored on described bearing structure; Described presstressed reinforcing steel 2, in tensile state, is realized the compression to concrete pile body 1 by described bearing structure.
Described underground space building structure, described presstressed reinforcing steel is some, and along described concrete pile axon to being evenly arranged.
On described presstressed reinforcing steel, be attached with separation layer, described separation layer carries out physical isolation to described presstressed reinforcing steel 2 with described concrete pile body 1, thereby after making bearing structure reach the length of time, described presstressed reinforcing steel 2 can be by tension.
Described bearing structure inside is provided with sheet steel pipe 5 and steel mesh reinforcement (not marking) herein, and described sheet steel pipe 5 is connected with described bearing structure and described steel mesh reinforcement stationary positioned, and wherein, described presstressed reinforcing steel 2 is located at described sheet steel pipe 5 inside.
Described presstressed reinforcing steel 2 is steel tendon, steel strand or cable wire rope.
Described bearing structure is cushion cap, and described cushion cap comprises concrete floor 3 and concrete cushion 4; Described bearing structure is provided with for presstressed reinforcing steel 2 being anchored in to the fixed part 6 on described bearing structure, and described fixed part is pre-buried can 7.
Obviously, above-described embodiment is only for example is clearly described, and the not restriction to embodiment.For those of ordinary skill in the field, can also make other changes in different forms on the basis of the above description.Here without also giving exhaustive to all embodiments.And among the protection domain that the apparent variation of being extended out thus or variation are still created in the utility model.

Claims (7)

1. a underground space building structure, is characterized in that comprising:
As the bottom, space of building lot and the top of space of joining with ground, described top of space at least has the Part I that bears heavier pressure and the Part II that bears lighter pressure; Difference between the second power between buoyancy and pressure that the poor and described Part I of the first power between the buoyancy that wherein said Part II is subject to and pressure is subject to is poor is greater than the maximum fracture resistence force at the junction surface of two parts;
Also comprise the first pile body group and the second pile body group, be arranged at respectively described Part I and described Part II vertically below, respectively described Part I and described Part II supported and fixed, thereby guaranteeing the poor maximum stretching resistance that is less than described maximum fracture resistence force and described the second pile body group of power of the suffered buoyancy of described Part II and the pressure that is subject to;
Wherein, described the second pile body group comprises some comprehensive function pile bodies, and described comprehensive function pile body comprises concrete pile body, and described concrete pile body has top and bottom; Also comprise bearing structure, described bearing structure is located at the described top of described concrete pile body; In described concrete pile body, be provided with reinforcing cage and presstressed reinforcing steel, wherein, one end of described presstressed reinforcing steel is fixed on described reinforcing cage one end near the described bottom of described concrete pile body, and the other end of described presstressed reinforcing steel is anchored on described bearing structure; Described presstressed reinforcing steel, in tensile state, is realized the compression to described concrete pile body by described bearing structure.
2. underground space building structure according to claim 1, is characterized in that:
Described presstressed reinforcing steel is some, and along described concrete pile axon to being evenly arranged.
3. underground space building structure according to claim 1 and 2, it is characterized in that: on described presstressed reinforcing steel, be attached with separation layer, described separation layer carries out physical isolation to described presstressed reinforcing steel and described concrete pile body, thereby after making described bearing structure reach the length of time, described presstressed reinforcing steel can be by tension.
4. underground space building structure according to claim 3, it is characterized in that: described bearing structure inside is provided with sheet steel pipe and steel mesh reinforcement, described sheet steel pipe is connected with described bearing structure and described steel mesh reinforcement stationary positioned, and wherein, described presstressed reinforcing steel is located at the inside of described sheet steel pipe.
5. underground space building structure according to claim 4, is characterized in that: described presstressed reinforcing steel is steel tendon, steel strand or cable wire rope.
6. underground space building structure according to claim 5, is characterized in that: described bearing structure is cushion cap, and described cushion cap comprises concrete floor and concrete cushion; Described bearing structure is provided with for described presstressed reinforcing steel is anchored in to the fixed part on described bearing structure.
7. underground space building structure according to claim 6, is characterized in that: described bearing structure is base plate.
CN201420044337.8U 2014-01-24 2014-01-24 Underground space building structure Expired - Lifetime CN203741871U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420044337.8U CN203741871U (en) 2014-01-24 2014-01-24 Underground space building structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420044337.8U CN203741871U (en) 2014-01-24 2014-01-24 Underground space building structure

Publications (1)

Publication Number Publication Date
CN203741871U true CN203741871U (en) 2014-07-30

Family

ID=51341692

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420044337.8U Expired - Lifetime CN203741871U (en) 2014-01-24 2014-01-24 Underground space building structure

Country Status (1)

Country Link
CN (1) CN203741871U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105256829A (en) * 2014-01-24 2016-01-20 刘献刚 Building structure of underground space

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105256829A (en) * 2014-01-24 2016-01-20 刘献刚 Building structure of underground space
CN105256827A (en) * 2014-01-24 2016-01-20 刘献刚 Building structure of underground space
CN105256825A (en) * 2014-01-24 2016-01-20 刘献刚 Building structure of underground space
CN105256828A (en) * 2014-01-24 2016-01-20 刘献刚 Building structure of underground space
CN105256826A (en) * 2014-01-24 2016-01-20 刘献刚 Building structure of underground space

Similar Documents

Publication Publication Date Title
CN104294753B (en) A kind of hollow pier stud syndeton of bridge prefabrication and construction
CN101649604B (en) Construction bracket of 1# block of inclined pull bridge and constructing method thereof
CN105064511A (en) Connecting structure of prestress hollow floor slab and H-shaped steel beam and construction method thereof
CN105350531B (en) The pile tube anchor pole composite foundation and construction technology of tension compression bidirectional load can be born
CN103966953B (en) Based on the post-tensioned prestressed large-span concrete beam construction method of non-bending steel cable
CN104294823B (en) A kind of construction method of pile for prestressed pipe anti-floating pile raft structure
CN203200751U (en) Prestress anti-floating pile
CN104594360A (en) Composite double-row pile foundation pit supporting structure
CN205224025U (en) Prestressing force anti -floating pile
CN203741871U (en) Underground space building structure
CN103790180B (en) The building pile body construction method of the underground space and underground space building structure
CN203808103U (en) Underground space building structure
CN203741830U (en) Concrete comprehensive acting pile
CN204401627U (en) To pull-type prestressed pipe pile pit supporting construction
CN103924617A (en) Underground space building pile shaft construction method and underground space building structure
CN201794215U (en) Pretensioning method prestress reinforced concrete prefabricated beam
CN105756077A (en) Foundation ring rock anchor rod foundation
CN204983246U (en) Hollow shear wall structure of close post of assembled
CN204703545U (en) A kind of reinforcing mixing board wall for brick is taken root structure
CN209194512U (en) Composite screw pilework
CN203160237U (en) Anti-floating anchor rod structure of raft
CN201794216U (en) Reinforced concrete prefabricated beam pre-stressed by pre-tensioning method
CN203808053U (en) Concrete combined action pile
CN204401608U (en) A kind of precast hollow uplift pile and process units thereof
CN205046554U (en) Core combined type anti structure of floating of stress tube stake is in advance irritated to built -in anchor rope

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20140730