CN203717020U - Control system for high-altitude tunnel construction environment - Google Patents

Control system for high-altitude tunnel construction environment Download PDF

Info

Publication number
CN203717020U
CN203717020U CN201420078665.XU CN201420078665U CN203717020U CN 203717020 U CN203717020 U CN 203717020U CN 201420078665 U CN201420078665 U CN 201420078665U CN 203717020 U CN203717020 U CN 203717020U
Authority
CN
China
Prior art keywords
seamless steel
steel pipe
control system
tunneling direction
water pump
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201420078665.XU
Other languages
Chinese (zh)
Inventor
谢永利
张玉伟
刘大鹏
李又云
王琪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Changan University
Original Assignee
Changan University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Changan University filed Critical Changan University
Priority to CN201420078665.XU priority Critical patent/CN203717020U/en
Application granted granted Critical
Publication of CN203717020U publication Critical patent/CN203717020U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Abstract

The utility model discloses a control system for high-altitude tunnel construction environment. The control system comprises an oxygen generator, a water pump, a seamless steel tube in the tunneling direction, and a plurality of seamless steel tubes with spray nozzles, wherein the oxygen generator and the water pump are arranged at a high-altitude tunnel entrance, the inlet of the water pump is connected with a reservoir, the outlets of the oxygen generator and the water pump are communicated with the inlet end of the seamless steel tube in the tunneling direction respectively, the outlet end of the seamless steel tube in the tunneling direction is communicated with the seamless steel tubes with the spray nozzles, a certain inclined angle a is formed between each seamless steel tubes with the spray nozzles and the seamless steel tube in the tunneling direction, and the inclined angle a is larger than 0 degree and smaller and equal to 90 degrees. The control system is used for improving the severe environment condition of tunnel construction in high-altitude areas, and providing a relatively good construction environment for workers in the tunnel; more specifically, the control system has the advantages that the dust concentration in the construction process can be reduced, enough oxygen can be provided for the workers in tunnel face and second lining working areas, so that the physical health of the workers can be guaranteed, the construction progress can be accelerated, and the construction efficiency can be improved.

Description

High Elevation Tunnel construction environment control system
[technical field]
The utility model belongs to drilling and blasting method constructing tunnel field, is specifically related to a kind of high Elevation Tunnel construction environment control system.
[background technology]
High altitude localities rarefaction of air, oxygen deficiency, temperature is lower, and environment is severe, and execution conditions quality is the bottleneck of restriction Tunnel Construction Schedule.Current is high height above sea level extremely frigid zones method for tunnel construction immature, still construct according to the traditional drilling and blasting method in plains region, but high altitude localities rarefaction of air, partial pressure of oxygen is low, ambient conditions is originally just very poor, if do not adopted an effective measure, to make in hole environment more severe, dust and pernicious gas too high levels, oxygen content deficiency etc., this not only can restrict workman operating efficiency, threaten workman healthy, also can reduce the delivery efficiency of construction machinery, this has brought no small obstacle to high height above sea level tunnel in cold area construction.
Current high height above sea level tunnel in cold area construction accessory system imperfection, ancillary works measure is single, such as carrying out road surface watering and lowering dust in order to reduce dust concentration, reduce harmful gas concentration and strengthen construction ventilation etc., but effect is very unobvious, and there is no too large improvement for the present situation of oxygen content deficiency.
Existing high altitude localities constructing tunnel ancillary method can not solve severe this present situation of tunnel construction environment completely, and still high by on-the-spot test dust concentration, oxygen content deficiency in tunnel, workman's efficiency is low, internal combustion engine loss is large, and delivery efficiency is low, in addition, add forced ventilation and will cause temperature in tunnel to reduce, this is extremely unfavorable to high Elevation Tunnel winter construction.
[utility model content]
The purpose of this utility model is for deficiency of the prior art, a kind of high Elevation Tunnel construction environment control system is provided, it is for improving high altitude localities constructing tunnel severe environmental conditions, for staff in tunnel provides a construction environment relatively preferably, specifically, reduce dust concentration in work progress, supply with the oxygen of face and two lining workspace staff's abundances, ensure that workman is healthy, accelerating construction progress, improves construction rate.
For achieving the above object, the utility model adopts following technical scheme:
High Elevation Tunnel construction environment control system, comprise oxygenerator, water pump, the seamless steel pipe of tunneling direction and some seamless steel pipes with nozzle, wherein, oxygenerator and water pump are arranged on high Elevation Tunnel hole place, the entrance of water pump connects reservoir, oxygenerator and water delivery side of pump are connected with the arrival end of the seamless steel pipe of tunneling direction respectively, the port of export at the seamless steel pipe of tunneling direction is connected with some seamless steel pipes with nozzle, and the seamless steel pipe with nozzle and the seamless steel pipe of tunneling direction have certain angle a, wherein, 0 ° of < a≤90 °.
The utility model further improves and is, between the outlet of oxygenerator and the entrance of the seamless steel pipe of tunneling direction, is provided with flow valve.
The utility model further improves and is, between the entrance of the seamless steel pipe of water delivery side of pump and tunneling direction, is provided with flow valve.
The utility model further improves and is, oxygenerator and water delivery side of pump are connected with the seamless steel pipe of tunneling direction by three way cock.
The utility model further improves and is, oxygenerator and water pump are arranged on oxygenerator and pump house.
The utility model further improves and is, between the seamless steel pipe with nozzle and the seamless steel pipe of tunneling direction, is provided with flow valve.
The utility model further improves and is, is arranged on two lining workspace and face workspaces of high Elevation Tunnel with the seamless steel pipe of nozzle.
The utility model further improves and is, is connected with the hose that is used to constructor that oxygen is provided on the nozzle of the seamless steel pipe with nozzle.
The utility model further improves and is, the seamless steel pipe of tunneling direction is formed by connecting by the threaded seamless steel pipe of some joints.
The utility model further improves and is, some pulleys are arranged on the rail of high Elevation Tunnel, and the seamless steel pipe bottom of tunneling direction is arranged on some pulleys.
With respect to prior art, a kind of high Elevation Tunnel construction environment control system of the utility model, it can carry out watering and lowering dust or disperse oxygen supply to high Elevation Tunnel according to actual needs, specifically, watering and lowering dust or disperse oxygen supply are carried out in face workspace to high Elevation Tunnel and two lining workspaces, greatly improve the construction environment of high Elevation Tunnel, main feature is that water supply and oxygen supply are integrated, take up space less as far as possible and reduce the impact on construction, can also be according to on-the-spot actual needs, determine the selection of watering and lowering dust or disperse oxygen system, specific aim is stronger, save energy consumption, to solve emphatically the too high and oxygen-deficient present situation of dust concentration in constructing tunnel.
[brief description of the drawings]
Fig. 1 is the structural representation of facing of the high Elevation Tunnel construction environment of the utility model control system;
Fig. 2 is the plan structure schematic diagram of the high Elevation Tunnel construction environment of the utility model control system.
Wherein: 1 is high Elevation Tunnel hole; 2 is three way cock; 3 is oxygenerator and pump house; 4,5,8,13 and 14 is flow valve; 6 is nozzle; 7 is connecting tee; 9 is face; 10 is rail; 11 is pulley; 12 is the seamless steel pipe of tunneling direction; 15 is oxygenerator; 16 is water pump.
[detailed description of the invention]
In order further to explain the utility model, make the purpose of this utility model, technical scheme, advantage clearer and more definite, below in conjunction with accompanying drawing, its detailed usage is described.
Referring to Fig. 1 and Fig. 2, a kind of high Elevation Tunnel construction environment control system of the utility model, comprises seamless steel pipe 12 and some seamless steel pipes with nozzle 6 of oxygenerator 15, water pump 16, tunneling direction.
Wherein, oxygenerator 15 and water pump 16 are arranged in the oxygenerator and pump house 3 at 1 place, high Elevation Tunnel hole, the entrance of water pump 16 connects reservoir, the outlet of oxygenerator 15 and water pump 16 is connected with the arrival end of the seamless steel pipe 12 of tunneling direction respectively, the port of export at the seamless steel pipe 12 of tunneling direction is connected with some seamless steel pipes with nozzle 6, and be arranged on two lining workspace and face workspaces 9 of high Elevation Tunnel with the seamless steel pipe of nozzle 6, the seamless steel pipe 12 of itself and tunneling direction has certain angle a, wherein, 0 ° of < a≤90 °, in addition, the seamless steel pipe with nozzle 6 that is arranged on two lining workspaces of high Elevation Tunnel is connected with the seamless steel pipe 12 of tunneling direction by connecting tee 7, on nozzle 6, can also be connected with the hose that is used to constructor that oxygen is provided.
In addition, between the outlet of oxygenerator 15 and the entrance of the seamless steel pipe of tunneling direction 12, be provided with flow valve 13; Between the entrance of the outlet of water pump 16 and the seamless steel pipe of tunneling direction 12, be provided with flow valve 14; Between seamless steel pipe with nozzle 6 and the seamless steel pipe of tunneling direction 12, be provided with flow valve 5 and flow valve 8.The outlet of oxygenerator 15 and water pump 16 can also be connected with the seamless steel pipe 12 of tunneling direction by three way cock 2.
Some pulleys 11 are arranged on the rail 10 of high Elevation Tunnel, and seamless steel pipe 12 bottoms of tunneling direction are arranged on some pulleys 11, are convenient to move, and can be advanced at any time face 9 workspaces, with the construction of following up.
For the utility model is further understood, now its operating principle is done to an explanation.
Oxygenerator of the present utility model and pump house 3 are arranged near high Elevation Tunnel hole 1, and water pump 16 connects reservoir, suit measures to local conditions, not affect normal construction as principle.
First explanation operation oxygen system, being applicable to face 9 workspaces drills, vertical bow member, the more working procedure of staff in the tunnels such as face of building the road, to supply with oxygen sufficient in tunnel, flow valve 13 is opened completely, flow valve 14 cuts out completely, flow valve 4 is opened completely, oxygenerator 15 work produce oxygen, seamless steel pipe 12 by tunneling direction and some seamless steel pipes with nozzle 6 are transported to two lining workspaces and face 9 workspaces, carry out disperse oxygen supply by nozzle 6, ensure the required oxygen of staff in high Elevation Tunnel hole, flow valve 5 can regulate workspace, Er Chen district oxygen output quantity according to actual needs, flow valve 8 can regulate face 9 workspace oxygen output quantities, along with face 9 workspace excavations, system can be by the construction of following up at any time of pulley 11 and rail 10, meet the required oxygen of staff in tunnel.In addition, construction oxygen system two serves as a contrast the nozzle 6 extensible hoses of workspace and face 9 workspaces, for indivedual constructor's rest oxygen uptakes.
Secondly explanation dust falling system operation, dust falling system carries out spray sprinkler depositing dust mainly for two lining workspaces and face 9 workspaces, be applicable to whitewashing and go out the great working procedure of slag dust output, flow valve 13 cuts out completely, flow valve 14 is opened completely, flow valve 4 is opened completely, reservoir water pressurizes by water pump 16, and then by seamless steel pipe 12 and some seamless steel pipe arrival two lining workspace and face 9 workspaces with nozzle 6 of tunneling direction, carry out spray sprinkler, to reduce dust concentration, flow valve 5 can regulate two lining workspace spray amount sizes as required, flow valve 8 can regulate face 9 workspace spray amount sizes, its advantage is can be according to the size of Dust Capacity in the tunnel size of adjustable spraying amount at any time, strong adaptability, save energy consumption.
What the utility model adopted is the seamless steel pipe 12 of segmented threaded tunneling direction, can carry out as required spreading, be the rail 10 with pulley 11 below, can follow up according to practice of construction progress, long hose can overlap in nozzle 6 places, for workman's oxygen uptake.
In sum, the utility model water system and oxygen system adopt integral manifold, can select according to different working procedures in high Elevation Tunnel, and the advantage of doing is like this: save energy consumption, raise the efficiency, and it is little to take up room, and little to construction infection.

Claims (10)

1. high Elevation Tunnel construction environment control system, it is characterized in that, comprise oxygenerator (15), water pump (16), the seamless steel pipe (12) of tunneling direction and the seamless steel pipe of some band nozzles (6), wherein, oxygenerator (15) and water pump (16) are arranged on high Elevation Tunnel hole (1) and locate, the entrance of water pump (16) connects reservoir, the outlet of oxygenerator (15) and water pump (16) is connected with the arrival end of the seamless steel pipe (12) of tunneling direction respectively, the port of export at the seamless steel pipe (12) of tunneling direction is connected with the seamless steel pipe of some band nozzles (6), and the seamless steel pipe of band nozzle (6) and the seamless steel pipe (12) of tunneling direction have certain angle a, wherein, 0 ° of < a≤90 °.
2. high Elevation Tunnel construction environment control system according to claim 1, is characterized in that, between the entrance of the seamless steel pipe (12) of the outlet of oxygenerator (15) and tunneling direction, is provided with flow valve.
3. high Elevation Tunnel construction environment control system according to claim 1, is characterized in that, between the entrance of the seamless steel pipe (12) of the outlet of water pump (16) and tunneling direction, is provided with flow valve.
4. high Elevation Tunnel construction environment control system according to claim 1, is characterized in that, the outlet of oxygenerator (15) and water pump (16) is connected with the seamless steel pipe (12) of tunneling direction by three way cock (2).
5. high Elevation Tunnel construction environment control system according to claim 1, is characterized in that, oxygenerator (15) and water pump (16) are arranged on oxygenerator and pump house (3).
6. high Elevation Tunnel construction environment control system according to claim 1, is characterized in that, between the seamless steel pipe of band nozzle (6) and the seamless steel pipe (12) of tunneling direction, is provided with flow valve.
7. high Elevation Tunnel construction environment control system according to claim 1, is characterized in that, the seamless steel pipe of band nozzle (6) is arranged on two lining workspace and face workspace (9) of high Elevation Tunnel.
8. high Elevation Tunnel construction environment control system according to claim 1, is characterized in that, on the nozzle (6) of the seamless steel pipe of band nozzle (6), is connected with the hose that is used to constructor that oxygen is provided.
9. high Elevation Tunnel construction environment control system according to claim 1, is characterized in that, the seamless steel pipe (12) of tunneling direction is formed by connecting by the threaded seamless steel pipe of some joints.
10. according to the high Elevation Tunnel construction environment control system described in claim 1 or 9, it is characterized in that, some pulleys (11) are arranged on the rail (10) of high Elevation Tunnel, and seamless steel pipe (12) bottom of tunneling direction is arranged on some pulleys (11).
CN201420078665.XU 2014-02-24 2014-02-24 Control system for high-altitude tunnel construction environment Expired - Fee Related CN203717020U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420078665.XU CN203717020U (en) 2014-02-24 2014-02-24 Control system for high-altitude tunnel construction environment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420078665.XU CN203717020U (en) 2014-02-24 2014-02-24 Control system for high-altitude tunnel construction environment

Publications (1)

Publication Number Publication Date
CN203717020U true CN203717020U (en) 2014-07-16

Family

ID=51156184

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420078665.XU Expired - Fee Related CN203717020U (en) 2014-02-24 2014-02-24 Control system for high-altitude tunnel construction environment

Country Status (1)

Country Link
CN (1) CN203717020U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104533430A (en) * 2015-01-05 2015-04-22 中国电建集团华东勘测设计研究院有限公司 Breakage and slippage type rockburst risk relieving high-pressure water injection device and construction method of breakage and slippage type rockburst risk relieving high-pressure water injection device
CN111577364A (en) * 2020-05-06 2020-08-25 中铁二院工程集团有限责任公司 High-altitude tunnel step oxygen supply system and use method thereof
CN111700759A (en) * 2020-06-24 2020-09-25 中南大学 Oxygen enrichment device and method for high-altitude mine driving face
CN113058180A (en) * 2021-03-23 2021-07-02 中国科学技术大学 Staged fire extinguishing and rescuing system and method for high-altitude tunnel

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104533430A (en) * 2015-01-05 2015-04-22 中国电建集团华东勘测设计研究院有限公司 Breakage and slippage type rockburst risk relieving high-pressure water injection device and construction method of breakage and slippage type rockburst risk relieving high-pressure water injection device
CN111577364A (en) * 2020-05-06 2020-08-25 中铁二院工程集团有限责任公司 High-altitude tunnel step oxygen supply system and use method thereof
CN111700759A (en) * 2020-06-24 2020-09-25 中南大学 Oxygen enrichment device and method for high-altitude mine driving face
CN111700759B (en) * 2020-06-24 2021-04-09 中南大学 Oxygen enrichment device and method for high-altitude mine driving face
CN113058180A (en) * 2021-03-23 2021-07-02 中国科学技术大学 Staged fire extinguishing and rescuing system and method for high-altitude tunnel
CN113058180B (en) * 2021-03-23 2021-10-22 中国科学技术大学 Staged fire extinguishing and rescuing system and method for high-altitude tunnel

Similar Documents

Publication Publication Date Title
CN203717020U (en) Control system for high-altitude tunnel construction environment
WO2018121142A1 (en) Mixing and guniting device of new type for tbm
CN201344042Y (en) Cooling capacity arrangement system for coal face in high temperature mine
CN104329109A (en) Gob retardant efficient spraying system and spraying method
CN204689452U (en) Multipurpose tower machine
CN102937033A (en) Efficient nitrogen injection and fire extinguishing system for mining
CN102606189B (en) Fire extinguishing and cooling system for coal cavities and loose areas in fire district of coal field
CN102182458A (en) Induced draft water curtain dust removing device for intercepted coal mining machine
CN206996271U (en) A kind of device for realizing the multistage spray ammonia of SCR denitrating flue gas
CN210969332U (en) Bridge construction is with spraying maintenance system
CN207844547U (en) A kind of stock yard heap material strip sprinkling dust-removing device
CN205839672U (en) Construction site reusable assembled spray dust-reducing system
CN206722755U (en) A kind of hot cold shock three-level breaks device for coal
CN105401943A (en) Pressurized air-water suction water curtain dust suppression device for fully mechanized mining of soft rock
CN205357898U (en) Install special plant protection machinery who spouts medicine device
CN112627878B (en) Tunnel dust removal equipment
CN209572724U (en) A kind of wisdom agricultural subsurface irrigation device
CN207913417U (en) A kind of depositing dust spray system
CN109538280B (en) Self-pressing type cooling and dedusting system utilizing mine aquifer
CN203452833U (en) Mining foam dust settling device
CN207348890U (en) A kind of constructing tunnel heat sink
CN206653509U (en) A kind of precast beam intelligence curing means
CN215672089U (en) Pneumatic spraying dust removal equipment based on down-the-hole drill
CN203091163U (en) Spraying gun of grout spraying machine
CN206299400U (en) This layer of dust-proof flame retarding construction of extraction borehole

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20140716

Termination date: 20160224