CN203702119U - Rated load switch applied to fracture acidizing process pipe column of oil-gas well - Google Patents

Rated load switch applied to fracture acidizing process pipe column of oil-gas well Download PDF

Info

Publication number
CN203702119U
CN203702119U CN201420001266.3U CN201420001266U CN203702119U CN 203702119 U CN203702119 U CN 203702119U CN 201420001266 U CN201420001266 U CN 201420001266U CN 203702119 U CN203702119 U CN 203702119U
Authority
CN
China
Prior art keywords
load switch
process pipe
lower contact
rated load
utility
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN201420001266.3U
Other languages
Chinese (zh)
Inventor
何伟
卿显君
易建国
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sichuan Weiwodun Petroleum Technology Co ltd
Original Assignee
SICHUAN WELDON CHEMICAL Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SICHUAN WELDON CHEMICAL Co Ltd filed Critical SICHUAN WELDON CHEMICAL Co Ltd
Priority to CN201420001266.3U priority Critical patent/CN203702119U/en
Application granted granted Critical
Publication of CN203702119U publication Critical patent/CN203702119U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

The utility model discloses a rated load switch applied to a fracture acidizing process pipe column of an oil-gas well which is aimed at solving the problem that a present process pipe column is taken out smoothly with great difficulty in a well. The rated load switch comprises an upper joint, a lower joint and a limiting mechanism connected with the upper joint. The limiting mechanism is detachably connected with the lower joint. The rated load switch applied to the fracture acidizing process pipe column of the oil-gas well has following beneficial effects: the rated load switch is reasonable in structure and ingenious in design and is convenient to use; the process pipe column in the well is smoothly taken out after construction; and therefore the rated load switch is of great utility value and promotional value.

Description

Be applied to the volume load switch of well fracturing acidification technique tubing string
Technical field
The utility model relates to a kind of volume load switch that is applied to well fracturing acidification technique tubing string.
Background technology
Along with going deep into of oil field development, stratum becomes increasingly complex, and interlayer difference is large, and the quantity of pressure break, acidifying layering also increases gradually, and layering measure process pipe string also becomes and becomes increasingly complex.Due to the complexity of process pipe string, the taking-up meeting in tubing string later stage is along with sand buries or the impact of the factors such as packer permanent set and become more and more difficult, and especially, aspect high angle hole and horizontal well, this problem is more outstanding.
Conventional process pipe string adopts layering sliding sleeve to add the form of structure of packer, ball seat conventionally, this kind of mode is because the ball seat adopting is overall structure, can not be split, thereby function singleness, itself and the effect of only just having played construction in layer that coordinates of layering sliding sleeve do not play the effect that helps and promote in the taking-up process of later stage process pipe string.In the time that needs take out tubing string, need all subsidiary instrument in tubing string is all loosening, and then utilize sizable upper lifting force by disposable process pipe string taking-up, operational risk is high, difficulty is large.And, if tubing string is long, in taking-up process, also can easily there is blocked portion phenomenon, and while running into this situation, just need many-sided adjustment, first make tubing string and subsidiary instrument thereof all loosening, and then apply larger upper lifting force and take out tubing string, this not only takes time and effort, and takes out poor effect.Therefore, existing taking-up mode is difficult to make process pipe string to take out smoothly in well.
Utility model content
The purpose of this utility model is to provide a kind of volume load switch that is applied to well fracturing acidification technique tubing string, mainly solves existing process pipe string and in well, is difficult to the problem of taking out smoothly.
To achieve these goals, the technical solution adopted in the utility model is as follows:
The volume load switch that is applied to well fracturing acidification technique tubing string, comprises top connection, lower contact, and the position-limit mechanism being connected with top connection; Described position-limit mechanism and lower contact removably connect.
Specifically, described position-limit mechanism comprises the adapter sleeve being connected with top connection, outer wall is flexibly connected with this adapter sleeve and falls into central tube wherein for the sliding sleeve fuse of process pipe string, and one end is connected in adapter sleeve, the other end and clamps under central tube outer wall supports the bullet pawl of lower contact; Described lower contact and adapter sleeve removably connect.
Further, described lower contact is connected with adapter sleeve by shear pin.
As preferably, the shearing force size of described shear pin is 5~50T.
Compared with prior art, the utlity model has following beneficial effect:
(1) the utility model reasonable in design, is skillfully constructed.
(2) the utility model can replace conventional ball seat to use aspect process pipe string, it not only can coordinate layering sliding sleeve to realize construction in layer, and utilize its detachable characteristic, the form that makes process pipe string can be divided into multistage is taken out one by one, thereby significantly reduce the taking-up difficulty of process pipe string, guarantee that process pipe string can take out smoothly in well, and taking-up mode of the present utility model is taken out tubing string after all subsidiary instrument in tubing string is all become flexible again, thereby operating procedure is very succinct, efficiency is quite high, the utility model has solved the defect of prior art, there is substantial feature and progress.
(3) the utility model is practical, easily manufactured, and it is suitable for applying aspect Oil/gas Well, particularly process pipe string.
Accompanying drawing explanation
Fig. 1 is structural representation of the present utility model.
Fig. 2 is that the utility model is installed to the structural representation in process pipe string.
Fig. 3 is that sliding sleeve fuse falls into the schematic diagram after central tube.
Fig. 4 is that the utility model is isolated the structural representation after lower contact.
Wherein, the component name that Reference numeral is corresponding is called:
1-layering sliding sleeve, 2-sliding sleeve fuse, 3-packer, 4-top connection, 5-central tube, 6-bullet pawl, 7-adapter sleeve, 8-lower contact, 9-shear pin.
The specific embodiment
Below in conjunction with drawings and Examples, the utility model is described in further detail, and embodiment of the present utility model includes but not limited to the following example.
Embodiment
As shown in Figure 1, the utility model is mainly used in taking-up aspect in process pipe string construction in layer and well, and it comprises top connection 4, position-limit mechanism and lower contact 8.Described position-limit mechanism comprises the adapter sleeve 7 being connected with top connection 4, the central tube 5 that outer wall is flexibly connected with this adapter sleeve 7, and one end is connected in adapter sleeve 7, the other end and clamps under central tube outer wall supports the bullet pawl 6 of lower contact 8; Described lower contact 8 is connected by shear pin 9 with adapter sleeve 7.
The utility model is special in the use of process pipe string designs, and below by use procedure of the present utility model, it is described in detail.
The utility model requires to arrange multiple according to the classification of process pipe string, in general, in process pipe string, include layering sliding sleeve 1, layering sliding sleeve 1 is provided with multiple, and by the first order, the second level ... N level is arranged in order, and between adjacent two stage layered sliding sleeves, is equipped with packer 3, and the utility model is connected between upper level packer and next stage layering sliding sleeve, the like, as shown in Figure 2.
In each layering sliding sleeve 1, be equipped with sliding sleeve fuse 2.Existing situation is that the sliding sleeve fuse 2 in layering sliding sleeve 1 can drop in ball seat through packer 3 in the time of construction, and in the utility model application aspect, this sliding sleeve fuse 2 can drop into central tube 5 inside through packer 3 in the time of construction, as shown in Figure 3, now, under sliding sleeve fuse 2 pressure-actings, central tube 5 can move to the direction of lower contact connection next stage layering sliding sleeve, lose support thereby cause playing one end that pawl 6 clamps lower contact 8, then reserve the space of inside contraction, and tentatively unclamp lower contact 8.Then, upper lifting pipe post, so that lower contact 8 separates, lower contact 8 final outcomes separate, except needs play pawl 6 is totally released it, also need to be decided by the shearing force of shear pin 9, the upper lifting force that top connection 4 is applied need to be not less than the shearing force of shear pin 9, to break shear pin 9, so can successfully separate lower contact 8.According to the physical condition of site operation, as preferably, in the present embodiment, the shearing force size of described shear pin 9 is 5~50T.
Top connection 4 is being applied after the upper lifting force that is not less than shear pin 9 shearing forces, play pawl 6 and continue inwardly to shrink and be totally released lower contact 8 under top connection 4 and adapter sleeve 7 drives, shear pin 9 is pulled off simultaneously, thereby cause lower contact 8 to depart from, then upper lifting pipe post, first order volume load switch top tubing string part is taken out, and the utility model is isolated structure after lower contact 8 as shown in Figure 4.First order volume load switch top tubing string part is lowered to fishing tool after taking out, and then in the same way successively by substratification sliding sleeve, third level layering sliding sleeve ... N stage layered sliding sleeve takes out one by one.
The utility model adopts position-limit mechanism to realize the separation of adjacent two stage layered sliding sleeves in process pipe string, it utilizes shear pin 9 to connect lower contact 8, and before having utilized dexterously sliding sleeve fuse 2 to fall into, after pressure change, realize and play the degree of tightness of pawl 6 to lower contact 8, can be the same with ball seat in the time of clamping lower contact 8, guarantee carrying out smoothly of construction in layer, and in the time unclamping, can reduce the load forces that tubing string takes out, no matter the utility model is to lower contact clamping or unclamps, it all can guarantee that process pipe string compressive strength is constant, and the utility model can be selected according to construction condition the shear pin of relevant shear power, thereby on meeting to the full extent, propose the requirement of load, and process pipe string can be taken out smoothly in well.
In addition, in to well, process pipe string is applied with while carrying load, if whole process pipe string is more loosening, without group card phenomenon, tubing string can disposable whole taking-ups, if carry after load in the maximum that uses well head to provide, there is not yet loosening sign in tubing string, can not disposable whole taking-ups, the lower contact in the utility model 8 and the part on it can be separated, after separately, in lower contact 8, the tubing string of part shortens relatively, thereby take out possibility be also greatly improved, there is hardly any taking-up difficulty; After top tubing string takes out, then from being newly lowered to fishing tool, the tubing string part being connected with lower contact is taken out, repeat successively, until tubing string in well is all taken out.
Those skilled in the art, according to above-described embodiment and in conjunction with after prior art and common practise, can know the technical scheme that the utility model is complete beyond all doubtly.And what deserves to be explained is; above-described embodiment is only preferably a kind of implementation of the utility model; should be in order to not limit protection domain of the present utility model; in every case any change and polishing of having no essential meaning of having done under body design thought of the present utility model and spirit; or be equal to displacement; its technical problem solving is consistent with the utility model in fact, also should be in protection domain of the present utility model.

Claims (3)

1. the volume load switch that is applied to well fracturing acidification technique tubing string, is characterized in that, comprises top connection (4), lower contact (8), and the position-limit mechanism being connected with top connection (4); Described position-limit mechanism and lower contact (8) removably connect; Described position-limit mechanism comprises the adapter sleeve (7) being connected with top connection (4), outer wall is flexibly connected with this adapter sleeve (7) and falls into central tube (5) wherein for the sliding sleeve fuse of process pipe string, and one end is connected in adapter sleeve (7), the other end and clamps under central tube outer wall supports the bullet pawl (6) of lower contact (8); Described lower contact (8) removably connects with adapter sleeve (7).
2. the volume load switch that is applied to well fracturing acidification technique tubing string according to claim 1, is characterized in that, described lower contact (8) is connected with adapter sleeve (7) by shear pin (9).
3. the volume load switch that is applied to well fracturing acidification technique tubing string according to claim 2, is characterized in that, the shearing force size of described shear pin (9) is 5~50T.
CN201420001266.3U 2014-01-02 2014-01-02 Rated load switch applied to fracture acidizing process pipe column of oil-gas well Expired - Lifetime CN203702119U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420001266.3U CN203702119U (en) 2014-01-02 2014-01-02 Rated load switch applied to fracture acidizing process pipe column of oil-gas well

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420001266.3U CN203702119U (en) 2014-01-02 2014-01-02 Rated load switch applied to fracture acidizing process pipe column of oil-gas well

Publications (1)

Publication Number Publication Date
CN203702119U true CN203702119U (en) 2014-07-09

Family

ID=51052575

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420001266.3U Expired - Lifetime CN203702119U (en) 2014-01-02 2014-01-02 Rated load switch applied to fracture acidizing process pipe column of oil-gas well

Country Status (1)

Country Link
CN (1) CN203702119U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105003227A (en) * 2015-08-03 2015-10-28 中国石油集团川庆钻探工程有限公司 Separable type hydraumatic sliding sleeve for oil gas well

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105003227A (en) * 2015-08-03 2015-10-28 中国石油集团川庆钻探工程有限公司 Separable type hydraumatic sliding sleeve for oil gas well
CN105003227B (en) * 2015-08-03 2018-05-25 中国石油集团川庆钻探工程有限公司 The detachable hydraulic sliding sleeve of oil/gas well

Similar Documents

Publication Publication Date Title
CN104632126B (en) A kind of big orifice bridging plug and its set method
CN103015955B (en) Open-hole horizontal well multi-cluster sliding sleeve staged fracturing string and fracturing method thereof
CN104929603B (en) Sleeve pipe infinite stages staged fracturing method
CN203685152U (en) Oil-gas well fracture acidizing technique pipe
CN105507858A (en) Immiscible gas injection and oil replacement type exploitation method for ultra-deep fractured-vuggy carbonate reservoirs
CN103711470B (en) A kind of well fracturing acidification technique tubing string and removing method thereof
CN107255023A (en) Exempt to bore bridging plug with the big orifice for setting function of giving up
CN103075139A (en) Immovable string hydraulic jetting technology for fracture acidizing and string for immovable string hydraulic jetting technology for fracture acidizing
CN207122297U (en) It is a kind of that there is the big orifice for setting function of giving up to exempt to bore bridging plug
CN203702119U (en) Rated load switch applied to fracture acidizing process pipe column of oil-gas well
CN202338316U (en) Five-layer layered compression fracture technology pipe column capable of mechanical isolating and progressive unpacking
CN202596589U (en) Process column for transforming well completion hierarchically with casing pipes and sliding sleeves
CN202215223U (en) Technology for limit-free staged fracturing down-hole string of horizontal open well
CN203626787U (en) Pipe string capable of realizing perforating and fracturing integration through hydraulic jetting fracturing technique and double-packer single-chuck fracturing technique
CN203808896U (en) Long-section casing damage well expansion pipe double-card casing pipe layered packing repairing device
CN102619495A (en) Multi-section delaminated fracturing tool string for vertical shaft immovable pipe column
CN103696718A (en) Method and device for repairing double-clamping-sleeve of expansion pipe of long section of casing damage well in layered partition manner
CN207686667U (en) Bridge plug component and bridge plug frac system
CN205260017U (en) Formula of can giving up bowling fracturing sliding sleeve
CN202832375U (en) Breakable ball injection fracturing slide sleeve
CN203394491U (en) Integrated perforating and fracturing tubing string for selective and repetitive reconstruction of old well in oil field
CN102418508A (en) Water jet packing tool
CN204098889U (en) Controllable high-temperature slide sleeve packer staged fracturing tool
CN203685094U (en) Layered sealing, separating and repairing device for expansion pipes with multiple clamped sleeves for long-segment casing damage well
CN103089227A (en) Large drift diameter drilling-free segmented fracture well completion sliding sleeve device

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 618300 Guanghan, Sichuan, China Town, small town, Fenghuang Village, the association of the three

Patentee after: SICHUAN WEWODON CHEMICAL CO.,LTD.

Address before: 618300 Guanghan, Sichuan, China Town, small town, Fenghuang Village, the association of the three

Patentee before: SICHUAN WELDON CHEMICALS CO.,LTD.

CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: 618000 Community 3, Fenghuang Village, Xiaohan Town, Guanghan City, Deyang City, Sichuan Province

Patentee after: Sichuan Weiwodun Petroleum Technology Co.,Ltd.

Address before: 618300 group 3, Fenghuang village, Xiaohan Town, Guanghan City, Deyang City, Sichuan Province

Patentee before: SICHUAN WEWODON CHEMICAL CO.,LTD.

CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20140709