CN203658568U - Low-voltage current transformer calibrating device - Google Patents

Low-voltage current transformer calibrating device Download PDF

Info

Publication number
CN203658568U
CN203658568U CN201420006433.3U CN201420006433U CN203658568U CN 203658568 U CN203658568 U CN 203658568U CN 201420006433 U CN201420006433 U CN 201420006433U CN 203658568 U CN203658568 U CN 203658568U
Authority
CN
China
Prior art keywords
assembly
primary
rod
support
transformer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN201420006433.3U
Other languages
Chinese (zh)
Inventor
侯兴哲
冯凌
周全
吴华
魏东
张进
欧熙
朱英
杨慧
曾啸龙
姚胜红
孔凡胜
安佰江
曾国华
方璟
曹祖亮
何玉朝
王曼
张能
涂志威
胡欢
张旭飞
张亚军
邓德勇
海志华
祁欣
方胜利
李原
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Electric Power Research Institute of State Grid Chongqing Electric Power Co Ltd
State Grid Corp of China SGCC
Wuhan NARI Ltd
Original Assignee
Electric Power Research Institute of State Grid Chongqing Electric Power Co Ltd
State Grid Corp of China SGCC
Wuhan NARI Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Electric Power Research Institute of State Grid Chongqing Electric Power Co Ltd, State Grid Corp of China SGCC, Wuhan NARI Ltd filed Critical Electric Power Research Institute of State Grid Chongqing Electric Power Co Ltd
Priority to CN201420006433.3U priority Critical patent/CN203658568U/en
Application granted granted Critical
Publication of CN203658568U publication Critical patent/CN203658568U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Testing Of Short-Circuits, Discontinuities, Leakage, Or Incorrect Line Connections (AREA)

Abstract

本实用新型公开了一种低压电流互感器检定装置,包括:测试台和自动接拆线装置,所述自动接拆线装置包括安装架、一次接线组件、二次接线组件和穿心组件,所述穿心组件安装在所述测试台上,所述安装架布置在所述测试台侧边对应所述穿心组件穿心端的位置,所述一次接线组件和二次接线组件相互配合地分别安装在所述安装架上。本实用新型通过采用将所述一次接线组件和二次接线组件安装在同一安装架上,并将所述穿心组件安装在测试台上的技术方案,解决了现有技术中需配置两个测试台而导致的占地面积大的问题。适用于互感器的检定。

The utility model discloses a low-voltage current transformer verification device, which comprises: a test bench and an automatic connection and disconnection device, the automatic connection and disconnection device includes a mounting frame, a primary wiring assembly, a secondary wiring assembly and a through-core assembly. The feed-through assembly is installed on the test bench, and the installation frame is arranged on the side of the test bench at a position corresponding to the feed-through end of the feed-through assembly, and the primary wiring assembly and the secondary wiring assembly are installed in cooperation with each other. on the mount. The utility model solves the need to configure two testing devices in the prior art by adopting the technical scheme of installing the primary wiring assembly and the secondary wiring assembly on the same mounting frame, and installing the through-core assembly on the test bench. The problem of large footprint caused by the platform. Applicable to the verification of transformers.

Description

低压电流互感器检定装置Low-voltage current transformer verification device

技术领域technical field

本实用新型涉及低压电流互感器检定领域,特别是涉及一种低压电流互感器检定装置。The utility model relates to the verification field of low-voltage current transformers, in particular to a verification device for low-voltage current transformers.

背景技术Background technique

随着我国电力事业的快速发展,作为电能计量装置的重要部件之一,计量用互感器的使用量也同步上升,而这些计量用互感器在使用前必须经过互感器计量检定部门的检定合格后才能使用,使得互感器计量检定部门,尤其是省市级互感器计量检定部门的互感器检定量也随之上升。目前,有些省份(如:浙江、江苏等)互感器的校验管理模式正逐步过渡到由省市级集中招标、集中采购、集中检验、统一配送的管理模式。该管理模式的转型使省市级计量检定部门的工作量大幅度上升,一些市级的互感器计量检定部门的年检定量达到十万只左右,这就促使相关部门采用更先进的校验方法和更先进的管理手段,使互感器的校验工作能够高效、准确的完成以适应电力事业的发展需要。With the rapid development of my country's electric power industry, as one of the important components of electric energy metering devices, the use of metering transformers has also increased simultaneously, and these metering transformers must pass the verification of the transformer metering verification department before use. Only then can it be used, so that the transformer measurement verification department, especially the provincial and municipal transformer measurement verification department, also increases the transformer verification amount. At present, some provinces (such as: Zhejiang, Jiangsu, etc.) are gradually transitioning to the management mode of centralized bidding, centralized procurement, centralized inspection, and unified distribution of transformers at the provincial and municipal levels. The transformation of this management mode has greatly increased the workload of provincial and municipal measurement and verification departments. The annual inspection quantity of some city-level transformer measurement and verification departments has reached about 100,000, which has prompted relevant departments to adopt more advanced verification methods and More advanced management methods enable the calibration of transformers to be completed efficiently and accurately to meet the development needs of the electric power industry.

目前,国内低压电流互感器检定装置已可实现多达十二只互感器误差的同时检定,检定项目包括绝缘电阻测量、工频耐压试验、二次绕组匝间绝缘强度试验、磁饱和裕度测量和基本误差测量,这种多只同时检定装置无论在技术、实现方案、速度、计算机管理、自动数据处理方面已发展比较成熟。但该低压电流互感器检定装置在使用时还存在以下问题:At present, the domestic low-voltage current transformer verification device can realize the simultaneous verification of up to twelve transformer errors. The verification items include insulation resistance measurement, power frequency withstand voltage test, secondary winding turn-to-turn dielectric strength test, and magnetic saturation margin. Measurement and basic error measurement, this multi-simultaneous verification device has developed relatively mature in terms of technology, implementation plan, speed, computer management, and automatic data processing. However, the low-voltage current transformer verification device also has the following problems in use:

由于绝缘电阻测量和工频耐压试验在该低压电流互感器检定装置的绝缘耐压测试台上进行测试,而二次绕组匝间绝缘强度试验、磁饱和裕度测量和基本误差测量则在该低压电流互感器检定装置的误差测试台上进行测试,所以该低压电流互感器检定台需配置两个测试台,这样,增大了该低压电流互感器检定台的占地面积;而且,在两个测试台上进行测试时,需分别进行接、拆线,工序复杂。Since the insulation resistance measurement and the power frequency withstand voltage test are tested on the insulation withstand voltage test bench of the low-voltage current transformer verification device, the inter-turn insulation strength test of the secondary winding, the magnetic saturation margin measurement and the basic error measurement are performed on the The test is carried out on the error test bench of the low-voltage current transformer verification device, so the low-voltage current transformer verification bench needs to be equipped with two test benches, thus increasing the floor area of the low-voltage current transformer verification bench; When testing on a test bench, it is necessary to connect and disconnect the wires separately, and the process is complicated.

发明内容Contents of the invention

本实用新型的目的是为了克服上述背景技术的不足,提供一种占地面积小且工序简单的低压电流互感器检定装置。The purpose of this utility model is to provide a low-voltage current transformer testing device with a small footprint and simple process in order to overcome the above-mentioned deficiencies in the background technology.

为了实现以上目的,本实用新型提供的一种低压电流互感器检定装置,包括:测试台和自动接拆线装置,所述自动接拆线装置包括安装架、一次接线组件、二次接线组件和穿心组件,所述穿心组件安装在所述测试台上,所述安装架布置在所述测试台侧边对应所述穿心组件穿心端的位置,所述一次接线组件和二次接线组件相互配合地分别安装在所述安装架上。通过采用将所述一次接线组件和二次接线组件安装在同一安装架上,并将所述穿心组件安装在测试台上的技术方案,解决了现有技术中需配置两个测试台而导致的占地面积大的问题;同时,本检定装置进行绝缘电阻测量、工频耐压试验、二次绕组匝间绝缘强度试验、磁饱和裕度测量和基本误差测量时,只需进行一次接、拆线,工序简单。In order to achieve the above purpose, a low-voltage current transformer verification device provided by the utility model includes: a test bench and an automatic connection and disconnection device, and the automatic connection and disconnection device includes a mounting frame, a primary wiring assembly, a secondary wiring assembly and Feedthrough assembly, the feedthrough assembly is installed on the test bench, the installation frame is arranged on the side of the test bench at a position corresponding to the feedthrough end of the feedthrough assembly, the primary wiring assembly and the secondary wiring assembly They are respectively installed on the mounting brackets in cooperation with each other. By adopting the technical scheme of installing the primary wiring assembly and the secondary wiring assembly on the same mounting frame, and installing the through-hole assembly on the test bench, it solves the problem caused by the need to configure two test benches in the prior art. At the same time, when the verification device performs insulation resistance measurement, power frequency withstand voltage test, secondary winding inter-turn insulation strength test, magnetic saturation margin measurement and basic error measurement, only one connection, The stitches are removed, and the procedure is simple.

在上述方案中,所述一次接线组件包括一次电缸、一次定位导向板、一次横梁、一次气爪、双端压紧杆和一次接头总成,所述一次接头总成安装在所述双端压紧杆的一端或两端,两个所述双端压紧杆分别安装在同一所述一次气爪的两活动端,所述一次气爪安装在所述一次横梁下端,所述一次横梁上端与所述一次电缸的伸缩端相连,所述一次电缸的缸体部分通过所述一次定位导向板安装在所述安装架上;In the above solution, the primary wiring assembly includes a primary electric cylinder, a primary positioning guide plate, a primary beam, a primary air gripper, a double-end pressing rod and a primary joint assembly, and the primary joint assembly is installed on the double-end One end or both ends of the compression rod, the two double-ended compression rods are respectively installed on the two movable ends of the same primary air claw, the primary air claw is installed on the lower end of the primary beam, and the upper end of the primary beam is Connected with the telescopic end of the primary electric cylinder, the cylinder part of the primary electric cylinder is installed on the mounting frame through the primary positioning guide plate;

所述二次接线组件包括二次电缸、二次定位导向板、二次横梁和二次压针总成,所述二次压针总成安装在所述二次横梁下端,所述二次横梁上端与所述二次电缸的伸缩端相连,所述二次电缸的缸体部分通过所述二次定位导向板安装在所述安装架上;The secondary wiring assembly includes a secondary electric cylinder, a secondary positioning guide plate, a secondary beam and a secondary pressing pin assembly, the secondary pressing pin assembly is installed at the lower end of the secondary beam, and the secondary The upper end of the beam is connected to the telescopic end of the secondary electric cylinder, and the cylinder part of the secondary electric cylinder is installed on the mounting frame through the secondary positioning guide plate;

所述穿心组件包括铺设在所述测试台上的轨道、滑动安装在所述轨道上的滑杆、驱动所述滑杆在所述轨道上滑动的滑杆电机、沿所述轨道纵向布置的穿心杆滑架和滑动安装在所述穿心杆滑架上的穿心杆,所述穿心杆一端与所述滑杆相连。通过所述双端压紧杆连接两个所述接头总成,这样一个气爪上就可安装对所述接头总成,即相邻两气爪之间就可压紧一个互感器,从而减少了气爪的数量,降低了成本,而且多个气爪通过所述一次横梁共用一个电缸,减少电缸的数量,进一步的降低了成本且结构紧凑、体积小;同时,多个所述二次压针总成通过所述二次横梁共用一个电缸,进一步地减少电缸的数量,进一步的降低了成本且结构紧凑、体积小;而且,多个穿心杆通过所述滑杆同用一个电机,减少了电机的数量,进一步的降低了成本且结构紧凑、体积小。The core assembly includes a track laid on the test bench, a slide bar slidably installed on the track, a slide bar motor that drives the slide bar to slide on the track, and longitudinally arranged along the track. The through-rod slide frame and the through-rod slidingly installed on the through-rod slide, one end of the through-through rod is connected with the slide bar. The two joint assemblies are connected by the double-ended pressing rod, so that the joint assembly can be installed on one air claw, that is, a transformer can be pressed between two adjacent air claws, thereby reducing The number of air claws is reduced, and the cost is reduced, and a plurality of air claws share one electric cylinder through the primary beam, reducing the number of electric cylinders, further reducing the cost and having a compact structure and a small volume; at the same time, multiple secondary The secondary pressing needle assembly shares one electric cylinder through the secondary crossbeam, which further reduces the number of electric cylinders, further reduces the cost and is compact in structure and small in volume; One motor reduces the number of motors, further reduces the cost, and has a compact structure and a small volume.

在上述方案中,所述一次横梁的数量和所述二次横梁的数量分别与所述穿心杆的数量一致。通过采用配套设置多个所述一次横梁、二次横梁和穿心杆的技术方案,使本检定装置能同时检定多排互感器,从而提高了本检定装置的效率。In the above solution, the number of the primary cross beams and the number of the secondary cross beams are respectively consistent with the number of the through rods. By adopting the technical scheme of matching multiple primary beams, secondary beams and piercing rods, the verification device can simultaneously verify multiple rows of transformers, thereby improving the efficiency of the verification device.

在上述方案中,单根所述一次横梁上一次接头总成的数量和单根所述二次横梁上二次压针总成的数量相互配套,且至少为一套。通过在单根所述一次横梁和单根所述二次横梁上分别设置配套的多个一次接头总成和多个二次压针总成,这样,本检定装置每排可同时检定多个互感器,进一步地提高了本检定装置的效率。In the above solution, the number of primary joint assemblies on a single primary beam and the number of secondary pressing needle assemblies on a single secondary beam match each other, and there is at least one set. By setting a plurality of matching primary joint assemblies and multiple secondary pressure pin assemblies on the single primary beam and the single secondary beam, in this way, each row of the verification device can simultaneously verify multiple mutual inductance The device further improves the efficiency of the verification device.

在上述方案中,所述测试台上对应所述穿心组件穿心端的位置设有用于支撑所述穿心杆的第一穿心杆支撑组件,所述第一穿心杆支撑组件包括支撑支架和支撑气爪,所述支撑气爪通过所述支撑支架安装在所述测试台上对应所述穿心组件穿心端的位置。In the above scheme, a first through-rod support assembly for supporting the through-rod is provided at a position corresponding to the through-hole end of the through-hole assembly on the test platform, and the first through-rod support assembly includes a support bracket and a supporting air claw, the supporting air claw is installed on the test bench at a position corresponding to the through-core end of the through-core assembly through the support bracket.

在上述方案中,所述安装架与所述测试台相对的一侧设有支撑台,所述支撑台上设有用于支撑所述穿心杆的第二穿心杆支撑组件,所述第二穿心杆支撑组件包括相互配合的支撑框架和支撑气缸,所述支撑框架安装在所述支撑台上对应所述穿心组件穿心端的位置,所述支撑气缸竖直安装在所述支撑框架内。In the above solution, a support platform is provided on the opposite side of the installation frame to the test platform, and a second through-hole rod support assembly for supporting the through-hole rod is arranged on the support platform, and the second The piercing rod support assembly includes a supporting frame and a supporting cylinder that cooperate with each other. The supporting frame is installed on the support platform at a position corresponding to the piercing end of the piercing assembly, and the supporting cylinder is vertically installed in the supporting frame. .

在上述方案中,所述支撑台和所述测试台分别布置在所述安装架的两侧,且所述支撑台与所述测试台为整体式结构,这样进一步地缩小了本检定装置的体积。In the above solution, the support platform and the test platform are respectively arranged on both sides of the installation frame, and the support platform and the test platform are integral structures, which further reduces the volume of the verification device .

本实用新型与现有技术对比,充分显示其优越性在于:Compared with the prior art, the utility model fully demonstrates its superiority in that:

1、通过采用将所述一次接线组件和二次接线组件安装在同一安装架上,并将所述穿心组件安装在测试台上的技术方案,解决了现有技术中需配置两个测试台而导致的占地面积大的问题;1. By adopting the technical solution of installing the primary wiring assembly and the secondary wiring assembly on the same mounting frame, and installing the through-core assembly on the test bench, it solves the problem of having to configure two test benches in the prior art The problem of large footprint caused by it;

2、本检定装置进行绝缘电阻测量、工频耐压试验、二次绕组匝间绝缘强度试验、磁饱和裕度测量和基本误差测量时,只需进行一次接、拆线,工序简单;2. When the verification device performs insulation resistance measurement, power frequency withstand voltage test, secondary winding inter-turn insulation strength test, magnetic saturation margin measurement and basic error measurement, it only needs to be connected and disconnected once, and the process is simple;

3、通过所述双端压紧杆连接两个所述接头总成,这样一个气爪上就可安装2对所述接头总成,即相邻两气爪之间就可压紧一个互感器,从而减少了气爪的数量,降低了成本,而且多个气爪通过所述一次横梁共用一个电缸,减少电缸的数量,进一步的降低了成本且结构紧凑、体积小;3. Connect the two joint assemblies through the double-ended pressing rod, so that two pairs of joint assemblies can be installed on one air claw, that is, one transformer can be pressed between two adjacent air claws , thereby reducing the number of air claws and reducing the cost, and multiple air claws share one electric cylinder through the primary crossbeam, reducing the number of electric cylinders, further reducing the cost and having a compact structure and small volume;

4、多个所述二次压针总成通过所述二次横梁共用一个电缸,进一步地减少电缸的数量,进一步的降低了成本且结构紧凑、体积小;4. A plurality of secondary press needle assemblies share one electric cylinder through the secondary crossbeam, which further reduces the number of electric cylinders, further reduces costs, and has a compact structure and small volume;

5、多个穿心杆通过所述滑杆同用一个电机,减少了电机的数量,进一步的降低了成本且结构紧凑、体积小;5. A plurality of piercing rods use the same motor through the sliding rod, which reduces the number of motors, further reduces the cost, and has a compact structure and small volume;

6、通过采用配套设置多个所述一次横梁、二次横梁和穿心杆的技术方案,使本检定装置能同时检定多排互感器,从而提高了本检定装置的效率;6. By adopting the technical scheme of supporting a plurality of said primary beams, secondary beams and piercing rods, the verification device can simultaneously verify multiple rows of transformers, thereby improving the efficiency of the verification device;

7、通过在单根所述一次横梁和单根所述二次横梁上分别设置配套的多个一次接头总成和多个二次压针总成,这样,本检定装置每排可同时检定多个互感器,进一步地提高了本检定装置的效率。7. By setting a plurality of matching primary joint assemblies and a plurality of secondary pressing pin assemblies on the single primary beam and the single secondary beam, in this way, each row of the verification device can simultaneously verify multiple A transformer further improves the efficiency of the verification device.

本实用新型具有体积小、工序简单、成本低和效率高等优点。The utility model has the advantages of small size, simple process, low cost and high efficiency.

附图说明Description of drawings

图1为本实施例的结构示意图;Fig. 1 is the structural representation of present embodiment;

图2为图1的主视结构示意图;Fig. 2 is a schematic diagram of the front view of Fig. 1;

图3为图1的左视结构示意图;Fig. 3 is a schematic diagram of the left view structure of Fig. 1;

图4为图1的后视结构示意图;Fig. 4 is a rear view structural schematic diagram of Fig. 1;

图5为图4的俯视结构示意图;Fig. 5 is a top view structural schematic diagram of Fig. 4;

图6为本实施例去掉传输装置3后的另一结构示意图;FIG. 6 is another structural schematic diagram of the present embodiment after the transmission device 3 is removed;

图7为本实施例去掉测试台和安装架后的结构示意图;Fig. 7 is the schematic diagram of the structure after removing the test bench and the mounting frame for the present embodiment;

图8为图7的侧视结构示意图;Fig. 8 is a side view structural schematic diagram of Fig. 7;

图9为图7的后视结构示意图;Fig. 9 is a rear view structural schematic diagram of Fig. 7;

图10为图7中只保留一套一次接线组件和二次接线组件的结构示意图;Fig. 10 is a schematic structural view of only one set of primary wiring assembly and secondary wiring assembly in Fig. 7;

图11为图10的侧视结构示意图;Fig. 11 is a side view structural schematic diagram of Fig. 10;

图12为图7中只保留一次接线组件的结构示意图;Fig. 12 is a schematic structural diagram of only one wiring assembly retained in Fig. 7;

图13为图12的侧视结构示意图;Fig. 13 is a side view structural schematic diagram of Fig. 12;

图14为一次接线组件的结构示意图;Fig. 14 is a structural schematic diagram of a wiring assembly;

图15为图7中只保留二次接线组件的结构示意图;Fig. 15 is a schematic structural diagram of only retaining the secondary wiring assembly in Fig. 7;

图16为图15的侧视结构示意图;Fig. 16 is a side view structural schematic diagram of Fig. 15;

图17为二次接线组件的结构示意图;Fig. 17 is a schematic structural diagram of a secondary wiring assembly;

图18为本实施例中传输装置的结构示意图;FIG. 18 is a schematic structural diagram of the transmission device in this embodiment;

图19为图18的侧视结构示意图;Figure 19 is a schematic side view of the structure of Figure 18;

图20为图19的俯视结构示意图;Fig. 20 is a schematic top view of Fig. 19;

图21为图18的后视结构示意图;Fig. 21 is a rear view structural schematic diagram of Fig. 18;

图22为互感器托盘定位机构处于回缩状态时的结构示意图;Fig. 22 is a schematic structural view of the positioning mechanism of the transformer tray when it is in a retracted state;

图23为互感器托盘定位机构处于伸出状态时的结构示意图;Fig. 23 is a structural schematic diagram when the transformer tray positioning mechanism is in an extended state;

图24为本实施例的使用状态结构示意图;Fig. 24 is a schematic structural diagram of the use status of this embodiment;

图25为图24的主视结构示意图;Fig. 25 is a schematic diagram of the front view of Fig. 24;

图26为图25一次接线时的结构示意图;Fig. 26 is a schematic diagram of the structure of Fig. 25 during primary wiring;

图27为图25二次接线时的结构示意图;Fig. 27 is a schematic structural diagram of Fig. 25 during secondary wiring;

图28为图25穿心时的结构示意图。Fig. 28 is a schematic diagram of the structure when Fig. 25 is passed through the heart.

图中,测试台1,自动接拆线装置2,安装架2a,一次接线组件2b,一次电缸2b1,一次定位导向板2b2,一次横梁2b3,一次气爪2b4,双端压紧杆2b5,一次接头总成2b6,二次接线组件2c,二次电缸2c1,二次定位导向板2c2,二次横梁2c3,二次压针总成2c4,穿心组件2d,轨道2d1,滑杆2d2,滑杆电机2d3,穿心杆滑架2d4,穿心杆2d5,第一穿心杆支撑组件2e,支撑支架2e1,支撑气爪2e2,第二穿心杆支撑组件2f,支撑框架2f1,支撑气缸2f2,传输装置3,倍速链传输机构3a,支架3a1,倍速链3a2,运输电机3a3,互感器托盘定位机构3b,导轨3b1,可升降定位支撑台总成3b2,定位底板3b2a,电动定位销3b2b,互感器托盘支撑台3b2c,定位电机3b3,传感器3b4,挡停板3b5,支撑台4,互感器托盘5。In the figure, the test bench 1, the automatic connection and disconnection device 2, the installation frame 2a, the primary wiring assembly 2b, the primary electric cylinder 2b1, the primary positioning guide plate 2b2, the primary beam 2b3, the primary air claw 2b4, and the double-ended pressing rod 2b5, Primary connector assembly 2b6, secondary wiring assembly 2c, secondary electric cylinder 2c1, secondary positioning guide plate 2c2, secondary beam 2c3, secondary pressing needle assembly 2c4, core-through assembly 2d, track 2d1, slide bar 2d2, Sliding rod motor 2d3, piercing rod carriage 2d4, piercing rod 2d5, first piercing rod supporting assembly 2e, supporting bracket 2e1, supporting air gripper 2e2, second piercing rod supporting assembly 2f, supporting frame 2f1, supporting cylinder 2f2, transmission device 3, double-speed chain transmission mechanism 3a, bracket 3a1, double-speed chain 3a2, transport motor 3a3, transformer tray positioning mechanism 3b, guide rail 3b1, liftable positioning support platform assembly 3b2, positioning bottom plate 3b2a, electric positioning pin 3b2b , The transformer tray support table 3b2c, the positioning motor 3b3, the sensor 3b4, the stop plate 3b5, the support table 4, and the transformer tray 5.

具体实施方式Detailed ways

下面结合附图及实施例对本实用新型作进一步的详细描述,但该实施例不应理解为对本实用新型的限制。The utility model will be further described in detail below in conjunction with the accompanying drawings and embodiments, but the embodiments should not be construed as limiting the utility model.

如图1所示,本实用新型实际使用时需配套传输装置3一起组成互感器自动检定线,该互感器自动检定线包括:测试台1、自动接拆线装置2和用于将互感器托盘5从上步工位运输至所述自动接拆线装置2的接拆线工位的传输装置3;As shown in Figure 1, when the utility model is used in practice, it needs to be equipped with a transmission device 3 to form an automatic test line for a transformer. 5 transporting from the last step station to the transmission device 3 of the connecting and disconnecting station of the automatic connecting and disconnecting device 2;

所述自动接拆线装置2包括安装架2a、一次接线组件2b、二次接线组件2c和穿心组件2d,所述穿心组件2d安装在所述测试台1上,所述安装架2a布置在所述测试台1侧边对应所述穿心组件2d穿心端的位置,所述一次接线组件2b和二次接线组件2c相互配合地分别安装在所述安装架2a上;The automatic connection and disconnection device 2 includes a mounting frame 2a, a primary wiring assembly 2b, a secondary wiring assembly 2c, and a core-through assembly 2d, the core-through assembly 2d is installed on the test bench 1, and the mounting frame 2a is arranged At the position on the side of the test bench 1 corresponding to the through-hole end of the lead-through assembly 2d, the primary wiring assembly 2b and the secondary wiring assembly 2c are respectively mounted on the mounting frame 2a in cooperation with each other;

通过采用将所述一次接线组件2b和二次接线组件2c安装在同一安装架2a上,并将所述穿心组件2d安装在测试台1上的技术方案,解决了现有技术中需配置两个测试台而导致的占地面积大的问题;同时,本检定线进行绝缘电阻测量、工频耐压试验、二次绕组匝间绝缘强度试验、磁饱和裕度测量和基本误差测量时,只需进行一次接、拆线,工序简单。By adopting the technical scheme of installing the primary wiring assembly 2b and the secondary wiring assembly 2c on the same mounting frame 2a, and installing the through-hole assembly 2d on the test bench 1, it solves the problem of the need to configure two wiring assemblies in the prior art. The problem of large floor area caused by a test bench; at the same time, when this verification line is used for insulation resistance measurement, power frequency withstand voltage test, secondary winding inter-turn insulation strength test, magnetic saturation margin measurement and basic error measurement, only It needs to be connected and disconnected once, and the process is simple.

所述传输装置3包括倍速链传输机构3a和互感器托盘定位机构3b,所述倍速链传输机构3a包括支架3a1、铺设在所述支架3a1顶部两侧的倍速链3a2和驱动所述倍速链3a2的运输电机3a3;所述互感器托盘定位机构3b包括铺设在所述支架3a1上的导轨3b1、滑动安装在所述导轨3b1上的可升降定位支撑台总成3b2和用于驱动所述可升降定位支撑台总成3b2在所述导轨3b1上滑动的定位电机3b3;所述互感器托盘定位机构3b设有初始工位、奇数排互感器检定工位和偶数排互感器检定工位。The transmission device 3 includes a double-speed chain transmission mechanism 3a and a transformer tray positioning mechanism 3b, and the double-speed chain transmission mechanism 3a includes a support 3a1, a double-speed chain 3a2 laid on both sides of the top of the support 3a1 and driving the double-speed chain 3a2 The transport motor 3a3; the transformer tray positioning mechanism 3b includes a guide rail 3b1 laid on the support 3a1, a liftable positioning support platform assembly 3b2 slidably installed on the guide rail 3b1 and used to drive the liftable The positioning support platform assembly 3b2 is a positioning motor 3b3 that slides on the guide rail 3b1; the transformer tray positioning mechanism 3b is provided with an initial station, an odd-numbered transformer verification station and an even-numbered transformer verification station.

通过采用将所述互感器托盘定位机构3b设置奇数排互感器检定工位和偶数排互感器检定工位的技术方案,增大了本检定线一次可检定的互感器数,从而提高了本检定线的效率。By adopting the technical scheme of setting the transformer tray positioning mechanism 3b with odd-numbered transformer verification stations and even-numbered transformer verification stations, the number of transformers that can be verified in this verification line at one time is increased, thereby improving the verification. line efficiency.

上述定位电机3b3为伺服电机,该伺服电机安装在所述支架3a1上对应所述两根导轨3b1之间的位置,该伺服电机通过皮带带动所述可升降定位支撑台总成3b2在所述导轨3b1上滑动,该伺服电机可准确的控制所述可升降定位支撑台总成3b2的移动位置,从而可准确地控制互感器托盘5上的奇数排互感器和偶数排互感器依次移动到所述接拆线工位上,从而增大了本检定线一次可检定的互感器数,进步一地提高了本检定线的效率。The above-mentioned positioning motor 3b3 is a servo motor, which is installed on the bracket 3a1 corresponding to the position between the two guide rails 3b1, and the servo motor drives the liftable positioning support platform assembly 3b2 on the guide rail through a belt 3b1, the servo motor can accurately control the moving position of the liftable positioning support platform assembly 3b2, so that the odd-numbered and even-numbered transformers on the transformer tray 5 can be accurately controlled to move sequentially to the Connecting to the dismantling station, thereby increasing the number of transformers that can be verified by this verification line at one time, and further improving the efficiency of this verification line.

上述一次接线组件2b包括一次电缸2b1、一次定位导向板2b2、一次横梁2b3、一次气爪2b4、双端压紧杆2b5和一次接头总成2b6,所述一次接头总成2b6安装在所述双端压紧杆2b5的一端或两端,两个所述双端压紧杆2b5分别安装在同一所述一次气爪2b4的两活动端,所述一次气爪2b4安装在所述一次横梁2b3下端,所述一次横梁2b3上端与所述一次电缸2b1的伸缩端相连,所述一次电缸2b1的缸体部分通过所述一次定位导向板2b2安装在所述安装架2a上。所述一次接头总成2b6的结构可参考中国专利201220593783.5一次压紧接线组件,在此不再赘述。The above-mentioned primary wiring assembly 2b includes a primary electric cylinder 2b1, a primary positioning guide plate 2b2, a primary beam 2b3, a primary air claw 2b4, a double-ended pressing rod 2b5 and a primary joint assembly 2b6, and the primary joint assembly 2b6 is installed on the One or both ends of the double-ended pressing rod 2b5, the two double-ended pressing rods 2b5 are respectively installed on the two movable ends of the same primary air claw 2b4, and the primary air claw 2b4 is installed on the primary beam 2b3 The lower end, the upper end of the primary beam 2b3 is connected to the telescopic end of the primary electric cylinder 2b1, and the cylinder body part of the primary electric cylinder 2b1 is installed on the mounting frame 2a through the primary positioning guide plate 2b2. The structure of the primary joint assembly 2b6 can refer to the Chinese patent 201220593783.5 primary compression wiring assembly, which will not be repeated here.

通过所述双端压紧杆2b5连接两个所述接头总成2b6,这样一个气爪2b4上就可安装2对所述接头总成2b6,即相邻两气爪2b4之间就可压紧一个互感器,从而减少了气爪2b4的数量,降低了成本;同时,多个气爪2b4通过所述一次横梁2b3共用一个电缸,减少电缸的数量,进一步的降低了成本且结构紧凑、体积小。Connect the two joint assemblies 2b6 through the double-ended pressing rod 2b5, so that two pairs of the joint assemblies 2b6 can be installed on one air claw 2b4, that is, the two adjacent air claws 2b4 can be compressed One transformer, thereby reducing the number of air claws 2b4 and reducing the cost; at the same time, multiple air claws 2b4 share one electric cylinder through the primary beam 2b3, reducing the number of electric cylinders, further reducing the cost and compact structure, small volume.

如图14所示,该一次接线组件2b的具体动作过程如下(参见图12、图13和图26):As shown in Figure 14, the specific action process of the primary wiring assembly 2b is as follows (see Figure 12, Figure 13 and Figure 26):

一次接线过程:首先,所述一次电缸2b1驱动所述一次横梁2b3向下运动,从而带动所述一次气爪2b4上的一次接头总成2b6下移至工作位;然后,所述传输装置3将装有互感器的互感器托盘5运输至所述接拆线工位;最后,所述一次气爪2b4驱动所述一次接头总成2b6将互感器上的输出母排夹紧,完成一次接线。Primary wiring process: first, the primary electric cylinder 2b1 drives the primary beam 2b3 to move downward, thereby driving the primary joint assembly 2b6 on the primary air gripper 2b4 to move down to the working position; then, the transmission device 3 Transport the transformer tray 5 with the transformer to the connection and disassembly station; finally, the primary air claw 2b4 drives the primary joint assembly 2b6 to clamp the output busbar on the transformer to complete the primary wiring .

一次拆线过程:检定完毕后,首先,所述一次气爪2b4驱动所述一次接头总成2b6松开互感器上的输出母排;然后,所述传输装置3将检定完毕的互感器托盘5退回;最后,所述一次电缸2b1驱动所述一次横梁2b3向上运动,从而带动所述一次气爪2b4上的一次接头总成2b6上移至初始位置,完成一次拆线。One-time disassembly process: after the verification is completed, firstly, the primary air gripper 2b4 drives the primary joint assembly 2b6 to loosen the output busbar on the transformer; then, the transmission device 3 transfers the verified transformer tray 5 Back; finally, the primary electric cylinder 2b1 drives the primary crossbeam 2b3 to move upward, thereby driving the primary joint assembly 2b6 on the primary air gripper 2b4 to move upward to the initial position to complete a stitch removal.

所述二次接线组件2c包括二次电缸2c1、二次定位导向板2c2、二次横梁2c3和二次压针总成2c4,所述二次压针总成2c4安装在所述二次横梁2c3下端,所述二次横梁2c3上端与所述二次电缸2c1的伸缩端相连,所述二次电缸2c1的缸体部分通过所述二次定位导向板2c2安装在所述安装架2a上。多个所述二次压针总成2c4通过所述二次横梁2c3共用一个电缸,进一步地减少电缸的数量,进一步的降低了成本且结构紧凑、体积小。The secondary wiring assembly 2c includes a secondary electric cylinder 2c1, a secondary positioning guide plate 2c2, a secondary beam 2c3 and a secondary pressing pin assembly 2c4, and the secondary pressing pin assembly 2c4 is installed on the secondary beam 2c3 lower end, the upper end of the secondary beam 2c3 is connected to the telescopic end of the secondary electric cylinder 2c1, and the cylinder part of the secondary electric cylinder 2c1 is installed on the mounting frame 2a through the secondary positioning guide plate 2c2 superior. A plurality of the secondary press needle assemblies 2c4 share one electric cylinder through the secondary beam 2c3, further reducing the number of electric cylinders, further reducing the cost and having a compact structure and a small volume.

如图17所示,该二次接线组件2c的具体动作过程如下(参见图15、图16和图27):As shown in Figure 17, the specific action process of the secondary wiring assembly 2c is as follows (see Figure 15, Figure 16 and Figure 27):

二次接线过程:互感器移动到位后,所述二次电缸2c1驱动所述二次横梁2c3向下运动,从而带动所述二次压针总成2c4压向互感器的二次端子,完成二次接线。Secondary wiring process: after the transformer is moved in place, the secondary electric cylinder 2c1 drives the secondary beam 2c3 to move downward, thereby driving the secondary pressing pin assembly 2c4 to press against the secondary terminal of the transformer, completing Secondary wiring.

二次拆线过程:检定完毕后,所述二次电缸2c1驱动所述二次横梁2c3向上运动,从而带动所述二次压针总成2c4上移至初始位置,完成二次拆线。Secondary stitch removal process: After the verification is completed, the secondary electric cylinder 2c1 drives the secondary beam 2c3 to move upward, thereby driving the secondary pressing needle assembly 2c4 to move upward to the initial position, and completes the second stitch removal.

所述穿心组件2d包括铺设在所述测试台1上的轨道2d1、滑动安装在所述轨道2d1上的滑杆2d2、驱动所述滑杆2d2在所述轨道2d1上滑动的滑杆电机2d3、沿所述轨道2d1纵向均匀布置的穿心杆滑架2d4和滑动安装在所述穿心杆滑架2d4上的穿心杆2d5,所述穿心杆2d5一端与所述滑杆2d2相连。多个穿心杆2d5通过所述滑杆2d2同用一个电机,减少了电机的数量,进一步的降低了成本且结构紧凑、体积小。本实施例中所述穿心杆2d5的数量为3根,所述滑杆电机2d3安装在所述测试台1上对应位于中间的穿心杆2d5下方的位置。The core assembly 2d includes a track 2d1 laid on the test bench 1, a slide bar 2d2 slidably installed on the track 2d1, a slide bar motor 2d3 that drives the slide bar 2d2 to slide on the track 2d1 , a through-rod carriage 2d4 evenly arranged longitudinally along the track 2d1 and a through-rod 2d5 slidably mounted on the through-rod carriage 2d4, and one end of the through-rod 2d5 is connected to the slide rod 2d2. A plurality of through-hole rods 2d5 use the same motor through the slide rod 2d2, which reduces the number of motors, further reduces the cost, and has a compact structure and a small volume. In this embodiment, the number of the piercing rods 2d5 is three, and the sliding rod motor 2d3 is installed on the test bench 1 corresponding to the position below the central piercing rod 2d5.

如图1所示,该穿心组件2d的具体动作过程如下(参见图28):As shown in Figure 1, the specific action process of the threading assembly 2d is as follows (see Figure 28):

互感器移动到位后,所述滑杆电机2d3驱动所述滑杆2d2向互感器方向移动,从而带动所述穿心杆2d5穿过待检的互感器,完成穿心动作;检定完毕后,所述滑杆电机2d3驱动所述滑杆2d2退回,从而带动所述穿心杆2d5退回至初始位置即可。After the transformer is moved in place, the sliding rod motor 2d3 drives the sliding rod 2d2 to move toward the transformer, thereby driving the piercing rod 2d5 to pass through the transformer to be tested to complete the piercing action; after the verification is completed, the The sliding rod motor 2d3 drives the sliding rod 2d2 back, so as to drive the through-core rod 2d5 back to the initial position.

上述一次横梁2b3的数量和所述二次横梁2c3的数量分别与所述穿心杆2d5的数量一致。通过采用配套设置多个所述一次横梁2b3、二次横梁2c3和穿心杆2d5的技术方案,使本检定线能同时检定多排互感器,从而提高了本检定线的效率。单根所述一次横梁2b3上一次接头总成2b6的数量和单根所述二次横梁2c3上二次压针总成2c4的数量相互配套,且至少为一套。通过在单根所述一次横梁2b3和单根所述二次横梁2c3上分别设置配套的多个一次接头总成2b6和多个二次压针总成2c4,这样,本检定线每排可同时检定多个互感器,进一步地提高了本检定线的效率。The quantity of the primary beam 2b3 and the quantity of the secondary beam 2c3 are respectively consistent with the quantity of the through rod 2d5. By adopting the technical scheme of arranging a plurality of primary beams 2b3, secondary beams 2c3 and piercing rods 2d5, the verification line can simultaneously verify multiple rows of transformers, thereby improving the efficiency of the verification line. The quantity of the primary joint assembly 2b6 on the single primary beam 2b3 and the quantity of the secondary pressing needle assembly 2c4 on the single secondary beam 2c3 are matched with each other, and there is at least one set. By respectively setting a plurality of supporting primary joint assemblies 2b6 and a plurality of secondary pressing pin assemblies 2c4 on the single described primary beam 2b3 and the single described secondary beam 2c3, like this, each row of this verification line can simultaneously Verification of multiple transformers further improves the efficiency of this verification line.

上述测试台1上对应所述穿心组件2d穿心端的位置设有用于支撑所述穿心杆2d5的第一穿心杆支撑组件2e,所述第一穿心杆支撑组件2e包括支撑支架2e1和支撑气爪2e2,所述支撑气爪2e2通过所述支撑支架2e1安装在所述测试台1上对应所述穿心组件2d穿心端的位置。所述安装架2a与所述测试台1相对的一侧设有支撑台4,所述支撑台4上设有用于支撑所述穿心杆2d5的第二穿心杆支撑组件2f,所述第二穿心杆支撑组件2f包括相互配合的支撑框架2f1和支撑气缸2f2,所述支撑框架2f1安装在所述支撑台4上对应所述穿心组件2d穿心端的位置,所述支撑气缸2f2竖直安装在所述支撑框架2f1内。所述支撑台4和所述测试台1分别布置在所述安装架2a的两侧,且所述支撑台4与所述测试台1为整体式结构,这样进一步地缩小了本检定线的体积。The position corresponding to the piercing end of the piercing assembly 2d on the test bench 1 is provided with a first piercing rod support assembly 2e for supporting the piercing rod 2d5, and the first piercing rod support assembly 2e includes a support bracket 2e1 and a supporting air gripper 2e2, the supporting air gripper 2e2 is installed on the test bench 1 at a position corresponding to the through-center end of the through-core assembly 2d through the support bracket 2e1. The side of the installation frame 2a opposite to the test bench 1 is provided with a support platform 4, and the support platform 4 is provided with a second piercing rod support assembly 2f for supporting the piercing rod 2d5. The two through-hole rod support assemblies 2f include a supporting frame 2f1 and a supporting cylinder 2f2 that cooperate with each other. directly installed in the support frame 2f1. The support platform 4 and the test platform 1 are respectively arranged on both sides of the mounting frame 2a, and the support platform 4 and the test platform 1 are of an integral structure, which further reduces the volume of the test line .

通过加设的所述第一穿心杆支撑组件2e和第二穿心杆支撑组件2f能有效地避免所述穿心杆2d5弯曲变形。The addition of the first through-rod support assembly 2e and the second through-rod support assembly 2f can effectively prevent bending deformation of the through-rod 2d5.

如图28所示,该第一穿心杆支撑组件2e和第二穿心杆支撑组件2f的具体动作过程如下(参见图1、图2、图5和图6):As shown in Fig. 28, the specific action process of the first piercing rod support assembly 2e and the second piercing rod support assembly 2f is as follows (see Fig. 1, Fig. 2, Fig. 5 and Fig. 6):

当所述穿心组件2d完成穿心动作后,所述支撑气爪2e2和支撑气缸2f2分别动作将所述穿心杆2d5两端分别夹紧即可;当检定完毕后,所述支撑气爪2e2和支撑气缸2f2先将所述穿心杆2d5松开,然后所述穿心组件2d再完成退回动作。After the core-through component 2d completes the core-through action, the support air claw 2e2 and the support cylinder 2f2 act separately to clamp the two ends of the core-through rod 2d5 respectively; when the verification is completed, the support air claw 2e2 and supporting cylinder 2f2 first release the through-hole rod 2d5, and then the through-hole assembly 2d completes the retraction action.

上述可升降定位支撑台总成3b2包括定位底板3b2a、竖直安装在所述定位底板3b2a上的电动定位销3b2b和安装在所述电动定位销3b2b伸缩端上的互感器托盘支撑台3b2c,所述电动定位销3b2b处于回缩状态时,所述互感器托盘支撑台3b2c位于所述倍速链3a2下方,所述电动定位销3b2b处于伸出状态时,所述互感器托盘支撑台3b2c位于所述倍速链3a2上方。所述互感器托盘支撑台3b2c上设有用于控制所述运输电机3a3运转的传感器3b4。The liftable positioning support platform assembly 3b2 includes a positioning base plate 3b2a, an electric positioning pin 3b2b vertically installed on the positioning base plate 3b2a, and a transformer tray supporting platform 3b2c installed on the telescopic end of the electric positioning pin 3b2b. When the electric positioning pin 3b2b is in the retracted state, the transformer tray support platform 3b2c is located under the double-speed chain 3a2, and when the electric positioning pin 3b2b is in the extended state, the transformer tray support platform 3b2c is located at the Double speed chain 3a2 above. A sensor 3b4 for controlling the operation of the transport motor 3a3 is provided on the transformer tray supporting platform 3b2c.

通过加设的传感器3b4可使互感器托盘5准确地移动到所述互感器托盘支撑台3b2c上。所述传感器3b4为接近开关,所述接近开关通过挡停板3b5安装在所述互感器托盘支撑台3b2c上。The transformer tray 5 can be accurately moved onto the transformer tray supporting platform 3b2c through the added sensor 3b4. The sensor 3b4 is a proximity switch, and the proximity switch is installed on the transformer tray support platform 3b2c through a stop plate 3b5.

如图18所示,所述传输装置3的具体动作过程如下(参见图19、图20、图21、图22和图23):As shown in Figure 18, the specific action process of the transmission device 3 is as follows (see Figure 19, Figure 20, Figure 21, Figure 22 and Figure 23):

首先,所述倍速链传输机构3a将待检的互感器托盘5从上步工位(如仓库等)向所述接拆线工位运输,当所述待检的互感器托盘5触碰到所述挡停板3b5上的接近开关时,所述倍速链传输机构3a停止动作,此时,所述待检的互感器托盘5位于所述可升降定位支撑台总成3b2正上方;然后,所述电动定位销3b2b伸出,将所述待检的互感器托盘5向上顶,直至所述待检的互感器托盘5从所述倍速链传输机构3a上脱离;接着,所述定位电机3b3将所述待检的互感器托盘5从所述初始工位准确移至所述奇数排互感器检定工位,本检定线便对所述待检的互感器托盘5上的奇数排互感器进行检定和标记;所述奇数排互感器检定和标记完毕后,所述定位电机3b3将所述检定完奇数排的互感器托盘5从所述奇数排互感器检定工位准确移至所述偶数排互感器检定工位,本检定线便对所述互感器托盘5上的偶数排互感器进行检定和标记;所述互感器托盘5上的所有互感器检定和标记完毕后,所述定位电机3b3将检定完毕后的互感器托盘5准确退回至所述初始工位;再接着,所述电动定位销3b2b回缩,使所述检定完毕后的互感器托盘5向下运动,直至所述检定完毕后的互感器托盘5落在所述倍速链传输机构3a上;最后,所述倍速链传输机构3a将所述检定完毕后的互感器托盘5退回所述上步工位即可。First, the double-speed chain transmission mechanism 3a transports the transformer tray 5 to be inspected from the previous station (such as a warehouse, etc.) to the connection and disassembly station. When the transformer tray 5 to be inspected touches When the proximity switch on the stop plate 3b5 is stopped, the double-speed chain transmission mechanism 3a stops, and at this time, the transformer tray 5 to be checked is located directly above the liftable positioning support platform assembly 3b2; then, The electric positioning pin 3b2b is stretched out, and the transformer tray 5 to be checked is pushed upward until the transformer tray 5 to be checked is disengaged from the double-speed chain transmission mechanism 3a; then, the positioning motor 3b3 Accurately move the transformer tray 5 to be inspected from the initial station to the inspection station of the odd-numbered transformers, and this inspection line will perform a test on the odd-numbered transformers on the transformer tray 5 to be inspected. Verification and marking: after the verification and marking of the odd-numbered row of transformers is completed, the positioning motor 3b3 will accurately move the verified odd-numbered transformer tray 5 from the odd-numbered row transformer verification station to the even-numbered row Transformer verification station, this verification line will verify and mark the even-numbered transformers on the transformer tray 5; after all the transformers on the transformer tray 5 have been verified and marked, the positioning motor 3b3 Accurately return the transformer tray 5 after the verification to the initial position; then, retract the electric positioning pin 3b2b, so that the transformer tray 5 after the verification is moved downward until the verification is completed The final transformer tray 5 falls on the double-speed chain transmission mechanism 3a; finally, the double-speed chain transmission mechanism 3a returns the verified transformer tray 5 to the upper step station.

本检定线的工作流程如下:The workflow of this verification line is as follows:

1、对于母排式互感器,其检定实验只需进行一次接拆线和二次接拆线,具体流程为:1. For the busbar type transformer, the verification experiment only needs to be connected and disconnected once and connected and disconnected twice. The specific process is:

首先,所述倍速链传输机构3a将待检的互感器托盘5从上步工位(如仓库等)向所述接拆线工位运输,当所述待检的互感器托盘5触碰到所述挡停板3b5上的接近开关时,所述倍速链传输机构3a停止动作,此时,所述待检的互感器托盘5位于所述可升降定位支撑台总成3b2正上方;然后,所述电动定位销3b2b伸出,将所述待检的互感器托盘5向上顶,直至所述待检的互感器托盘5从所述倍速链传输机构3a上脱离;接着,所述定位电机3b3将所述待检的互感器托盘5从所述初始工位准确移至所述奇数排互感器检定工位;紧接着,所述一次接线组件2b和所述二次接线组件2c对所述待检的互感器托盘5上的奇数排互感器分别进行一次接线和二次接线;接线完毕后,本检定线便可对所述奇数排互感器分别进行绝缘电阻测量、工频耐压试验、二次绕组匝间绝缘强度试验、磁饱和裕度测量和基本误差测量,并将合格产品和不合格产品分别标记出来;检定完毕后,所述一次接线组件2b和所述二次接线组件2c便对所述奇数排互感器分别进行一次拆线和二次拆线;拆线完毕后,所述定位电机3b3将所述检定完奇数排的互感器托盘5从所述奇数排互感器检定工位准确移至所述偶数排互感器检定工位;紧接着,所述一次接线组件2b和所述二次接线组件2c便对所述互感器托盘5上的偶数排互感器分别进行一次接线和二次接线;接线完毕后,本检定线便可对所述偶数排互感器分别进行绝缘电阻测量、工频耐压试验、二次绕组匝间绝缘强度试验、磁饱和裕度测量和基本误差测量,并将合格产品和不合格产品分别标记出来;所述互感器托盘5上的所有互感器检定和标记完毕后,所述定位电机3b3将检定完毕后的互感器托盘5准确退回至所述初始工位;再接着,所述电动定位销3b2b回缩,使所述检定完毕后的互感器托盘5向下运动,直至所述检定完毕后的互感器托盘5落在所述倍速链传输机构3a上;最后,所述倍速链传输机构3a将所述检定完毕后的互感器托盘5退回所述上步工位即可。First, the double-speed chain transmission mechanism 3a transports the transformer tray 5 to be inspected from the previous station (such as a warehouse, etc.) to the connection and disassembly station. When the transformer tray 5 to be inspected touches When the proximity switch on the stop plate 3b5 is stopped, the double-speed chain transmission mechanism 3a stops, and at this time, the transformer tray 5 to be checked is located directly above the liftable positioning support platform assembly 3b2; then, The electric positioning pin 3b2b is stretched out, and the transformer tray 5 to be checked is pushed upward until the transformer tray 5 to be checked is disengaged from the double-speed chain transmission mechanism 3a; then, the positioning motor 3b3 Accurately move the transformer tray 5 to be inspected from the initial station to the odd-numbered transformer inspection station; then, the primary wiring assembly 2b and the secondary wiring assembly 2c The odd-numbered row transformers on the transformer tray 5 to be inspected are respectively subjected to primary wiring and secondary wiring; Secondary winding turn-to-turn insulation strength test, magnetic saturation margin measurement and basic error measurement, and mark qualified products and unqualified products respectively; after verification, the primary wiring assembly 2b and the secondary wiring assembly 2c are The odd-numbered row transformers are respectively subjected to a first-time disassembly and a second disassembly; after the disassembly is completed, the positioning motor 3b3 moves the verified odd-numbered transformer trays 5 from the odd-numbered row transformer verification station to accurately Move to the transformer verification station of the even row; then, the primary wiring assembly 2b and the secondary wiring assembly 2c perform primary wiring and secondary wiring of the even row transformers on the transformer tray 5 respectively. Wiring; After the wiring is completed, this verification line can respectively perform insulation resistance measurement, power frequency withstand voltage test, secondary winding turn-to-turn insulation strength test, magnetic saturation margin measurement and basic error measurement on the even-numbered row transformers, and Mark qualified products and unqualified products respectively; after all the transformers on the transformer tray 5 have been verified and marked, the positioning motor 3b3 will accurately return the verified transformer tray 5 to the initial station Then, the electric positioning pin 3b2b is retracted, so that the transformer tray 5 after the verification is completed moves downward until the transformer tray 5 after the verification is completed falls on the double-speed chain transmission mechanism 3a; Finally, the double-speed chain transmission mechanism 3a returns the transformer tray 5 after the verification to the upper station.

2、对于穿心式互感器,其检定实验只需进行二次接拆线和穿心,具体流程为:2. For the core-through transformer, the verification experiment only needs to be connected and disconnected twice and through the core. The specific process is as follows:

首先,所述倍速链传输机构3a将待检的互感器托盘5从上步工位(如仓库等)向所述接拆线工位运输,当所述待检的互感器托盘5触碰到所述挡停板3b5上的接近开关时,所述倍速链传输机构3a停止动作,此时,所述待检的互感器托盘5位于所述可升降定位支撑台总成3b2正上方;然后,所述电动定位销3b2b伸出,将所述待检的互感器托盘5向上顶,直至所述待检的互感器托盘5从所述倍速链传输机构3a上脱离;接着,所述定位电机3b3将所述待检的互感器托盘5从所述初始工位准确移至所述奇数排互感器检定工位;紧接着,所述二次接线组件2c便对所述待检的互感器托盘5上的奇数排互感器进行二次接线;接线完毕后,所述穿心组件2d便对所述奇数排互感器进行穿心;穿心完毕后,本检定线便可对所述待检的互感器托盘5上的奇数排互感器分别进行绝缘电阻测量、工频耐压试验、二次绕组匝间绝缘强度试验、磁饱和裕度测量和基本误差测量,并将合格产品和不合格产品分别标记出来;检定完毕后,所述二次接线组件2c和所述穿心组件2d对所述奇数排互感器分别进行二次拆线和退回动作;拆线和退回完毕后,所述定位电机3b3将所述检定完奇数排的互感器托盘5从所述奇数排互感器检定工位准确移至所述偶数排互感器检定工位;紧接着,所述二次接线组件2c便对所述互感器托盘5上的偶数排互感器二次接线;接线完毕后,所述穿心组件2d便对所述偶数排互感器进行穿心;穿心完毕后,本检定线便可对所述偶数排互感器分别进行绝缘电阻测量、工频耐压试验、二次绕组匝间绝缘强度试验、磁饱和裕度测量和基本误差测量,并将合格产品和不合格产品分别标记出来;所述互感器托盘5上的所有互感器检定和标记完毕后,所述定位电机3b3将检定完毕后的互感器托盘5准确退回至所述初始工位;再接着,所述电动定位销3b2b回缩,使所述检定完毕后的互感器托盘5向下运动,直至所述检定完毕后的互感器托盘5落在所述倍速链传输机构3a上;最后,所述倍速链传输机构3a将所述检定完毕后的互感器托盘5退回所述上步工位即可。First, the double-speed chain transmission mechanism 3a transports the transformer tray 5 to be inspected from the previous station (such as a warehouse, etc.) to the connection and disassembly station. When the transformer tray 5 to be inspected touches When the proximity switch on the stop plate 3b5 is stopped, the double-speed chain transmission mechanism 3a stops, and at this time, the transformer tray 5 to be checked is located directly above the liftable positioning support platform assembly 3b2; then, The electric positioning pin 3b2b is stretched out, and the transformer tray 5 to be checked is pushed upward until the transformer tray 5 to be checked is disengaged from the double-speed chain transmission mechanism 3a; then, the positioning motor 3b3 Accurately move the transformer tray 5 to be inspected from the initial station to the inspection station of the odd-numbered transformer transformer; The odd-numbered rows of transformers above are connected for the second time; after the wiring is completed, the thread-through component 2d will pass through the odd-numbered rows of transformers; The odd-numbered row transformers on the transformer tray 5 are respectively subjected to insulation resistance measurement, power frequency withstand voltage test, secondary winding turn-to-turn dielectric strength test, magnetic saturation margin measurement and basic error measurement, and qualified products and unqualified products are marked separately come out; after the verification is completed, the secondary wiring assembly 2c and the through-core assembly 2d perform secondary unwiring and retracting actions on the odd-numbered transformers respectively; after unwiring and returning are completed, the positioning motor 3b3 will The transformer trays 5 of the odd-numbered rows are accurately moved from the odd-numbered transformer inspection station to the even-numbered transformer inspection station after the verification is completed; then, the secondary wiring assembly 2c performs the inspection of the transformer The secondary wiring of the even-numbered row transformers on the tray 5; after the wiring is completed, the thread-through component 2d will pass through the even-numbered row transformers; Insulation resistance measurement, power frequency withstand voltage test, secondary winding turn-to-turn insulation strength test, magnetic saturation margin measurement and basic error measurement are respectively carried out on the transformer, and qualified products and unqualified products are marked respectively; the transformer tray 5 After the verification and marking of all the transformers on the board are completed, the positioning motor 3b3 will accurately return the transformer tray 5 after the verification to the initial station; then, the electric positioning pin 3b2b retracts to make the verification The completed transformer tray 5 moves downward until the verified transformer tray 5 falls on the double-speed chain transmission mechanism 3a; finally, the double-speed chain transmission mechanism 3a transfers the verified mutual inductor The device tray 5 is returned to the described last step station to get final product.

本检定线通过采用将所述一次接线组件2b和二次接线组件2c安装在同一安装架2a上,并将所述穿心组件2d安装在测试台1上的技术方案,解决了现有技术中需配置两个测试台而导致的占地面积大的问题;本检定线进行绝缘电阻测量、工频耐压试验、二次绕组匝间绝缘强度试验、磁饱和裕度测量和基本误差测量时,只需进行一次接、拆线,工序简单;通过采用将所述互感器托盘定位机构3b设置奇数排互感器检定工位和偶数排互感器检定工位的技术方案,增大了本检定线一次可检定的互感器数,从而提高了本检定线的效率;通过所述双端压紧杆2b5连接两个所述接头总成2b6,这样一个气爪2b4上就可安装2对所述接头总成2b6,即相邻两气爪2b4之间就可压紧一个互感器,从而减少了气爪2b4的数量,降低了成本,而且多个气爪2b4通过所述一次横梁2b3共用一个电缸,减少电缸的数量,进一步的降低了成本且结构紧凑、体积小;多个所述二次压针总成2c4通过所述二次横梁2c3共用一个电缸,进一步地减少电缸的数量,进一步的降低了成本且结构紧凑、体积小;多个穿心杆2d5通过所述滑杆2d2同用一个电机,减少了电机的数量,进一步的降低了成本且结构紧凑、体积小;通过采用配套设置多个所述一次横梁2b3、二次横梁2c3和穿心杆2d5的技术方案,使本检定线能同时检定多排互感器,从而提高了本检定线的效率;通过在单根所述一次横梁2b3和单根所述二次横梁2c3上分别设置配套的多个一次接头总成2b6和多个二次压针总成2c4,这样,本检定线每排可同时检定多个互感器,进一步地提高了本检定线的效率。通过加设的传感器3b4可使互感器托盘准确地移动到所述互感器托盘支撑台3b2c上;通过将所述定位电机3b3设计为伺服电机,这样,该伺服电机可准确的控制所述可升降定位支撑台总成3b2的移动位置,从而可准确地控制互感器托盘5上的奇数排互感器和偶数排互感器依次移动到所述接拆线工位上,从而增大了本检定线一次可检定的互感器数,进步一地提高了本检定线的效率。This test line solves the problems in the prior art by adopting the technical solution of installing the primary wiring assembly 2b and the secondary wiring assembly 2c on the same mounting frame 2a, and installing the through-core assembly 2d on the test bench 1. The problem of large floor area caused by the need to configure two test benches; when this verification line is used for insulation resistance measurement, power frequency withstand voltage test, secondary winding inter-turn insulation strength test, magnetic saturation margin measurement and basic error measurement, It only needs to be connected and disconnected once, and the process is simple; by adopting the technical scheme of setting the transformer tray positioning mechanism 3b in odd rows and even rows of transformer verification stations, the verification line is increased once. The number of transformers that can be verified, thereby improving the efficiency of the verification line; the two joint assemblies 2b6 are connected through the double-ended pressing rod 2b5, so that two pairs of the joint assemblies can be installed on one air gripper 2b4 2b6, that is, a transformer can be pressed between two adjacent air claws 2b4, thereby reducing the number of air claws 2b4 and reducing the cost, and multiple air claws 2b4 share one electric cylinder through the primary beam 2b3, Reducing the number of electric cylinders further reduces the cost and is compact in structure and small in size; multiple secondary press needle assemblies 2c4 share one electric cylinder through the secondary crossbeam 2c3, further reducing the number of electric cylinders and further reducing the number of electric cylinders. The cost is reduced, the structure is compact, and the volume is small; multiple through-hole rods 2d5 use the same motor through the slide rod 2d2, which reduces the number of motors, further reduces the cost, and has a compact structure and small volume; by adopting matching settings The technical scheme of a plurality of said primary beams 2b3, secondary beams 2c3 and through-core rods 2d5 enables this verification line to simultaneously verify multiple rows of transformers, thereby improving the efficiency of this verification line; 2b3 and the single secondary beam 2c3 are respectively provided with a plurality of supporting primary joint assemblies 2b6 and a plurality of secondary pressing needle assemblies 2c4, so that each row of the verification line can simultaneously verify a plurality of transformers, and further The efficiency of this test line is improved. Through the additional sensor 3b4, the transformer tray can be accurately moved onto the transformer tray support platform 3b2c; by designing the positioning motor 3b3 as a servo motor, the servo motor can accurately control the liftable Locate the moving position of the support platform assembly 3b2, so that the odd-numbered transformers and even-numbered transformers on the transformer tray 5 can be accurately controlled to move to the connecting and dismantling stations in turn, thereby increasing the calibration line once. The number of transformers that can be verified has greatly improved the efficiency of this verification line.

以上所述仅为本实用新型的较佳实施例,并不用以限制本实用新型,凡在本实用新型的精神和原则之内,所作的任何修改、等同替换、改进等,均应包含在本实用新型的保护范围之内。The above descriptions are only preferred embodiments of the present utility model, and are not intended to limit the present utility model. Any modifications, equivalent replacements, improvements, etc. made within the spirit and principles of the present utility model shall be included in this utility model. within the scope of protection of utility models.

Claims (7)

1.一种低压电流互感器检定装置,包括:测试台(1)和自动接拆线装置(2),其特征在于,所述自动接拆线装置(2)包括安装架(2a)、一次接线组件(2b)、二次接线组件(2c)和穿心组件(2d),所述穿心组件(2d)安装在所述测试台(1)上,所述安装架(2a)布置在所述测试台(1)侧边对应所述穿心组件(2d)穿心端的位置,所述一次接线组件(2b)和二次接线组件(2c)相互配合地分别安装在所述安装架(2a)上。1. A low-voltage current transformer verification device, comprising: a test bench (1) and an automatic connection and disconnection device (2), characterized in that the automatic connection and disconnection device (2) includes a mounting frame (2a), a primary Wiring assembly (2b), secondary wiring assembly (2c) and feedthrough assembly (2d), the feedthrough assembly (2d) is installed on the test bench (1), and the mounting frame (2a) is arranged on the The side of the test bench (1) corresponds to the position of the through-core end of the core-through assembly (2d), and the primary wiring assembly (2b) and the secondary wiring assembly (2c) are respectively installed on the mounting frame (2a) in cooperation with each other. )superior. 2.根据权利要求1所述低压电流互感器检定装置,其特征在于,所述一次接线组件(2b)包括一次电缸(2b1)、一次定位导向板(2b2)、一次横梁(2b3)、一次气爪(2b4)、双端压紧杆(2b5)和一次接头总成(2b6),所述一次接头总成(2b6)安装在所述双端压紧杆(2b5)的一端或两端,两个所述双端压紧杆(2b5)分别安装在同一所述一次气爪(2b4)的两活动端,所述一次气爪(2b4)安装在所述一次横梁(2b3)下端,所述一次横梁(2b3)上端与所述一次电缸(2b1)的伸缩端相连,所述一次电缸(2b1)的缸体部分通过所述一次定位导向板(2b2)安装在所述安装架(2a)上;2. The low-voltage current transformer verification device according to claim 1, characterized in that, the primary wiring assembly (2b) includes a primary electric cylinder (2b1), a primary positioning guide plate (2b2), a primary beam (2b3), a primary Air claw (2b4), double-ended compression rod (2b5) and primary joint assembly (2b6), the primary joint assembly (2b6) is installed at one or both ends of the double-ended compression rod (2b5), The two double-ended pressing rods (2b5) are respectively installed on the two movable ends of the same primary air claw (2b4), and the primary air claw (2b4) is installed on the lower end of the primary beam (2b3). The upper end of the primary beam (2b3) is connected to the telescopic end of the primary electric cylinder (2b1), and the cylinder part of the primary electric cylinder (2b1) is installed on the mounting frame (2a) through the primary positioning guide plate (2b2) )superior; 所述二次接线组件(2c)包括二次电缸(2c1)、二次定位导向板(2c2)、二次横梁(2c3)和二次压针总成(2c4),所述二次压针总成(2c4)安装在所述二次横梁(2c3)下端,所述二次横梁(2c3)上端与所述二次电缸(2c1)的伸缩端相连,所述二次电缸(2c1)的缸体部分通过所述二次定位导向板(2c2)安装在所述安装架(2a)上;The secondary wiring assembly (2c) includes a secondary electric cylinder (2c1), a secondary positioning guide plate (2c2), a secondary beam (2c3) and a secondary pressing pin assembly (2c4), and the secondary pressing pin The assembly (2c4) is installed at the lower end of the secondary beam (2c3), and the upper end of the secondary beam (2c3) is connected to the telescopic end of the secondary electric cylinder (2c1), and the secondary electric cylinder (2c1) The cylinder part of the cylinder is installed on the mounting frame (2a) through the secondary positioning guide plate (2c2); 所述穿心组件(2d)包括铺设在所述测试台(1)上的轨道(2d1)、滑动安装在所述轨道(2d1)上的滑杆(2d2)、驱动所述滑杆(2d2)在所述轨道(2d1)上滑动的滑杆电机(2d3)、沿所述轨道(2d1)纵向布置的穿心杆滑架(2d4)和滑动安装在所述穿心杆滑架(2d4)上的穿心杆(2d5),所述穿心杆(2d5)一端与所述滑杆(2d2)相连。The through-core assembly (2d) includes a track (2d1) laid on the test bench (1), a slide bar (2d2) slidingly installed on the track (2d1), driving the slide bar (2d2) The sliding rod motor (2d3) sliding on the rail (2d1), the through rod carriage (2d4) arranged longitudinally along the rail (2d1), and the through rod carriage (2d4) slidably installed on the through rod carriage (2d4) The through-core rod (2d5), one end of the through-center rod (2d5) is connected with the slide rod (2d2). 3.根据权利要求2所述低压电流互感器检定装置,其特征在于,所述一次横梁(2b3)的数量和所述二次横梁(2c3)的数量分别与所述穿心杆(2d5)的数量一致。3. The low-voltage current transformer verification device according to claim 2, characterized in that the number of the primary beam (2b3) and the number of the secondary beam (2c3) are respectively the same as the number of the through-hole rod (2d5) The quantity is consistent. 4.根据权利要求3所述低压电流互感器检定装置,其特征在于,单根所述一次横梁(2b3)上一次接头总成(2b6)的数量和单根所述二次横梁(2c3)上二次压针总成(2c4)的数量相互配套,且至少为一套。4. The low-voltage current transformer verification device according to claim 3, characterized in that the number of primary joint assemblies (2b6) on the single primary beam (2b3) and the number of single secondary beams (2c3) The quantity of the secondary pressing needle assembly (2c4) is matched with each other, and there is at least one set. 5.根据权利要求2所述低压电流互感器检定装置,其特征在于,所述测试台(1)上对应所述穿心组件(2d)穿心端的位置设有用于支撑所述穿心杆(2d5)的第一穿心杆支撑组件(2e),所述第一穿心杆支撑组件(2e)包括支撑支架(2e1)和支撑气爪(2e2),所述支撑气爪(2e2)通过所述支撑支架(2e1)安装在所述测试台(1)上对应所述穿心组件(2d)穿心端的位置。5. The low-voltage current transformer verification device according to claim 2, characterized in that, the position corresponding to the through-hole end of the through-through component (2d) on the test bench (1) is provided with a support for the through-through rod ( 2d5) the first piercing rod support assembly (2e), the first piercing rod support assembly (2e) includes a support bracket (2e1) and a support air claw (2e2), and the support air claw (2e2) passes through the The supporting bracket (2e1) is installed on the test bench (1) at a position corresponding to the through-hole end of the through-hole component (2d). 6.根据权利要求5所述低压电流互感器检定装置,其特征在于,所述安装架(2a)与所述测试台(1)相对的一侧设有支撑台(4),所述支撑台(4)上设有用于支撑所述穿心杆(2d5)的第二穿心杆支撑组件(2f),所述第二穿心杆支撑组件(2f)包括相互配合的支撑框架(2f1)和支撑气缸(2f2),所述支撑框架(2f1)安装在所述支撑台(4)上对应所述穿心组件(2d)穿心端的位置,所述支撑气缸(2f2)竖直安装在所述支撑框架(2f1)内。6. The low-voltage current transformer verification device according to claim 5, characterized in that, a supporting platform (4) is provided on the side of the mounting frame (2a) opposite to the testing platform (1), and the supporting platform (4) is provided with a second piercing rod support assembly (2f) for supporting the piercing rod (2d5), and the second piercing rod support assembly (2f) includes a supporting frame (2f1) and Support the cylinder (2f2), the support frame (2f1) is installed on the support table (4) at the position corresponding to the through-hole end of the through-core assembly (2d), the support cylinder (2f2) is vertically installed on the Inside the support frame (2f1). 7.根据权利要求6所述低压电流互感器检定装置,其特征在于,所述支撑台(4)和所述测试台(1)分别布置在所述安装架(2a)的两侧,且所述支撑台(4)与所述测试台(1)为整体式结构。7. The low-voltage current transformer verification device according to claim 6, characterized in that, the support platform (4) and the test platform (1) are respectively arranged on both sides of the installation frame (2a), and the The support platform (4) and the test platform (1) are integral structures.
CN201420006433.3U 2014-01-06 2014-01-06 Low-voltage current transformer calibrating device Expired - Lifetime CN203658568U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420006433.3U CN203658568U (en) 2014-01-06 2014-01-06 Low-voltage current transformer calibrating device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420006433.3U CN203658568U (en) 2014-01-06 2014-01-06 Low-voltage current transformer calibrating device

Publications (1)

Publication Number Publication Date
CN203658568U true CN203658568U (en) 2014-06-18

Family

ID=50924943

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420006433.3U Expired - Lifetime CN203658568U (en) 2014-01-06 2014-01-06 Low-voltage current transformer calibrating device

Country Status (1)

Country Link
CN (1) CN203658568U (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104730383A (en) * 2015-03-12 2015-06-24 国家电网公司 Low-voltage current transformer comprehensive testing device and method
CN104950278A (en) * 2015-06-25 2015-09-30 国家电网公司 Rail-mounted positioning sliding table for transformers
CN104950277A (en) * 2015-06-25 2015-09-30 国家电网公司 Semi-automatic comprehensive detection device for low-voltage current transformer
CN105304305A (en) * 2014-07-03 2016-02-03 朱佳瑞 Semi-automatically produced voltage and current transformer and manufacturing method
CN110911148A (en) * 2019-12-20 2020-03-24 国网电力科学研究院武汉南瑞有限责任公司 An intelligent wiring device for distribution transformer based on three-dimensional image recognition
CN112051478A (en) * 2020-09-09 2020-12-08 国网电力科学研究院武汉南瑞有限责任公司 Full-automatic multifunctional testing device for high-voltage current transformer
CN112768213A (en) * 2021-02-03 2021-05-07 国网江苏省电力有限公司徐州供电分公司 Automatic connection and disconnection device for secondary side of high-voltage transformer and use method thereof

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105304305A (en) * 2014-07-03 2016-02-03 朱佳瑞 Semi-automatically produced voltage and current transformer and manufacturing method
CN104730383A (en) * 2015-03-12 2015-06-24 国家电网公司 Low-voltage current transformer comprehensive testing device and method
CN104950278A (en) * 2015-06-25 2015-09-30 国家电网公司 Rail-mounted positioning sliding table for transformers
CN104950277A (en) * 2015-06-25 2015-09-30 国家电网公司 Semi-automatic comprehensive detection device for low-voltage current transformer
CN104950277B (en) * 2015-06-25 2018-02-13 国家电网公司 A kind of low-voltage current mutual inductor semi-automation comprehensive detection device
CN110911148A (en) * 2019-12-20 2020-03-24 国网电力科学研究院武汉南瑞有限责任公司 An intelligent wiring device for distribution transformer based on three-dimensional image recognition
CN112051478A (en) * 2020-09-09 2020-12-08 国网电力科学研究院武汉南瑞有限责任公司 Full-automatic multifunctional testing device for high-voltage current transformer
CN112768213A (en) * 2021-02-03 2021-05-07 国网江苏省电力有限公司徐州供电分公司 Automatic connection and disconnection device for secondary side of high-voltage transformer and use method thereof

Similar Documents

Publication Publication Date Title
CN203658568U (en) Low-voltage current transformer calibrating device
CN103728583B (en) With the mutual inductor automation calibrating system of logistics system seamless link
CN107092003B (en) An automatic detection system for voltage transformers
CN203658404U (en) Secondary-connection component for transformer calibration
CN103713221A (en) Low-frequency transformer automatic comprehensive test machine based on GROOVY data collecting and analyzing system controlled by PLC
CN102628930A (en) Automatic detection line for mutual inductor
CN203658569U (en) Transmission device for automatic calibration of low-tension current transformers
CN203799007U (en) Mutual inductor automation detecting system in seamless connection with logistic system
CN101893696A (en) Detection device of electric energy meter
CN102305920B (en) One-time threading method of bus-type current transformer
CN211348526U (en) Semiconductor device test system
CN109225929B (en) Inductor performance automatic tester
CN203178444U (en) Relay checking platform
CN204425177U (en) A kind of general power model is guide locating device provided
CN202494765U (en) Integral tool for scanning and testing lithium ion battery
CN202548316U (en) Automatic detection line for mutual inductor
CN118641560A (en) A rigid pavement subgrade disease model detection test device
CN104198822A (en) A device for rapidly testing an amorphous magnetic ring and a testing method thereof
CN204871101U (en) Lift trailer is used in mutual -inductor examination
CN104950277B (en) A kind of low-voltage current mutual inductor semi-automation comprehensive detection device
CN206420906U (en) The fixing device and power module test frock of test module functional unit
CN110744291A (en) Full-automatic electronic component rigging equipment
CN201909841U (en) Circling-type device for automatically connecting and disconnecting terminal of electric energy meter
CN201796141U (en) Detection device of electric energy meter
CN204731398U (en) A kind of low-voltage current mutual inductor detects with 3 D stereo mechanically moving device

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20140618