CN203635453U - Thermal-cold cycling system of paint airing room of furniture factory - Google Patents
Thermal-cold cycling system of paint airing room of furniture factory Download PDFInfo
- Publication number
- CN203635453U CN203635453U CN201320869629.0U CN201320869629U CN203635453U CN 203635453 U CN203635453 U CN 203635453U CN 201320869629 U CN201320869629 U CN 201320869629U CN 203635453 U CN203635453 U CN 203635453U
- Authority
- CN
- China
- Prior art keywords
- boiler
- paint
- room
- heat exchange
- refrigeration machine
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Drying Of Solid Materials (AREA)
Abstract
The utility model relates to a thermal-cold cycling system of a paint airing room of a furniture factory. The thermal-cold cycling system comprises heat exchange pipelines and a boiler, wherein the heat exchange pipelines are arranged inside the paint airing room, the boiler is located outside the paint airing room, the heat exchange pipelines are distributed in a staggered mode and communicated, and the heat exchange pipelines are connected with the boiler to form a cycling channel. The cycling system further comprises a refrigerator, and the refrigeration is connected with the boiler in series. When the paint airing room needs to be heated, the refrigerator and the boiler are disconnected, the boiler is heated, and hot water in the boiler dissipates heat to the paint airing room through the heat exchange pipelines. When the paint airing room needs to be cooled, the refrigerator and the boiler are communicated, cold water generated by the refrigerator flows into the heat exchange pipelines through the boiler to cool the paint airing room. Compared with the prior art, the system is low in cost and easy to operate, production cost is lowered, and energy consumption caused by the fact that the temperature of an original paint drying room is adjusted through an air conditioner is saved.
Description
Technical field
The utility model relates to a kind of cooling and heating circulation system, especially relates to a kind of Furniture Factory paint and dries room cooling and heating circulation system.
Background technology
The furniture, the sheet material etc. that in Furniture Factory, had just sprayed paint all need to be placed on paint and dry in room and dry.Paint dries the inner placement of multiple layers support in room, and furniture to be dried is placed on support, by exchange heat such as hot blasts, the paint of furniture surface is dried.Dry the specific temperature of needs owing to drying paint in room, generally between 10~15 ℃, most paint dries laying heat exchange pipeline in room at present, pipeline is connected with boiler, winter, open boiler, the hot water in boiler circulates in heat exchange pipeline, by the heat of hot water, paint is dried to room and heats up.When summer, because indoor temperature is very high, generally adopt air-conditioning to dry room cooling to paint, while adopting air-conditioning, dry room and be closed state, atmosphere draught-free, paint to dry effect poor, and open for a long time air-conditioning, waste energy on the one hand, unclean environmental protection, causes the increase of cost, on the other hand, air-conditioning damages drying in room very easily, and service life is very short, the third aspect, dry atmosphere draught-free in room, paint smell can not leave, contaminated air.
Utility model content
The purpose of this utility model be exactly provide in order to overcome the defect that above-mentioned prior art exists a kind of simple in structure, cost is low, the Furniture Factory of good effect of heat exchange paint dries room cooling and heating circulation system.
The purpose of this utility model can be achieved through the following technical solutions:
A kind of Furniture Factory paint dries room cooling and heating circulation system, comprise being laid in to paint to dry the heat exchange pipeline of inside, room and be positioned at paint and dry the boiler of outside, room, described heat exchange pipeline is laid staggeredly, and interconnect between heat exchange pipeline, and be connected with boiler, form circulation canal, the described circulatory system also comprises refrigeration machine, and refrigeration machine is connected with boiler; When paint is dried to room heated condition, refrigeration machine and boiler disconnect, and when paint is dried to room cooling state, refrigeration machine is communicated with boiler.
Between described refrigeration machine and boiler, be connected by pipeline, pipeline is provided with controls the switch valve that refrigeration machine is communicated with or disconnects with boiler.
Pipeline between refrigeration machine and boiler is provided with the pressure gauge of controlling internal pipe pressure.
Pipeline between refrigeration machine and boiler is provided with the delivery pump that makes cold water for delivery of refrigeration machine.
Pipeline between refrigeration machine and boiler is provided with the choke valve that regulates cold water flow.
In the time that room temperature is lower, need to dry room heating to paint, now disconnect being connected of refrigeration machine and boiler by switch valve, refrigeration machine is now equivalent to inoperative, boiler is heated, hot water in boiler dries room heat radiation by heat exchange pipeline to paint, makes to obtain assigned temperature in paint drying room.In the time that room temperature is higher, need to dry room cooling to paint, now opening switch valve is communicated with refrigeration machine with boiler, boiler is not heated, now boiler is equivalent to the effect of a transfer water tank, start refrigeration machine, make the cold water that refrigeration machine makes enter in heat exchange pipeline and dry room cooling to paint by boiler.Can guarantee that by the circulatory system of the present utility model in paint drying room, temperature remains on 10~15 ℃.
Compared with prior art, the utility model is on the architecture basics in original paint drying room, by the refrigerator of connecting with boiler, make system of the present utility model to carry out cold cycling to paint drying room, system cost of the present utility model is cheap, processing ease, reduce production cost, and having saved original paint drying room uses air-conditioning to regulate the energy resource consumption of temperature, in the time using the circulatory system of the present utility model, paint drying room can seal, make paint drying room inner air flow better, further strengthen drying effect, and reduce the paint smell in baking room.
Accompanying drawing explanation
Fig. 1 is perspective view of the present utility model;
Fig. 2 is main TV structure schematic diagram of the present utility model;
Fig. 3 is plan structure schematic diagram of the present utility model.
Number in the figure: 1 is refrigeration machine, 2 for paint dries room, and 3 is boiler, and 4 is choke valve, and 5 is delivery pump, and 6 is pressure gauge, and 7 is switch valve.
The specific embodiment
Below in conjunction with the drawings and specific embodiments, the utility model is elaborated.
Embodiment
A kind of Furniture Factory paint dries room cooling and heating circulation system, as shown in FIG. 1 to 3, comprise being laid in to paint to dry the heat exchange pipeline of inside, room and be positioned at paint and dry the boiler 3 of outside, room, heat exchange pipeline is laid staggeredly, and between heat exchange pipeline, interconnect, and be connected with boiler 3, form circulation canal, the circulatory system also comprises refrigeration machine 1, and refrigeration machine 1 is connected with boiler 3.Between refrigeration machine 1 and boiler 3, be connected by pipeline, pipeline is provided with controls the switch valve 7 that refrigeration machine 1 is communicated with or disconnects with boiler 3.Delivery pump 5 and the choke valve 4 that regulates cold water flow that pipeline between refrigeration machine 1 and boiler 3 is provided with and controls the pressure gauge 6 of internal pipe pressure, makes cold water for delivery of refrigeration machine 1.
In the time that room temperature is lower, need to dry room heating to paint, now disconnect being connected of refrigeration machine 1 and boiler 3 by switch valve 7, refrigeration machine 1 is now equivalent to inoperative, boiler 3 is heated, hot water in boiler 3 dries room heat radiation by heat exchange pipeline to paint, makes to obtain assigned temperature in paint drying room 22.In the time that room temperature is higher, need to dry room cooling to paint, now opening switch valve 7 is communicated with refrigeration machine 1 with boiler 3, boiler 3 is not heated, now boiler 3 is equivalent to the effect of a transfer water tank, start refrigeration machine 1, make the cold water that refrigeration machine 1 makes enter in heat exchange pipeline and dry room cooling to paint by boiler 3.Can guarantee that by the circulatory system of the present utility model the interior temperature in paint drying room 22 remains on 10~15 ℃.
Claims (5)
1. Furniture Factory's paint dries room cooling and heating circulation system, comprise being laid in to paint to dry the heat exchange pipeline of inside, room and be positioned at paint and dry the boiler of outside, room, described heat exchange pipeline is laid staggeredly, and interconnect between heat exchange pipeline, and be connected with boiler, form circulation canal, it is characterized in that, the described circulatory system also comprises refrigeration machine, and refrigeration machine is connected with boiler; When paint is dried to room heated condition, refrigeration machine and boiler disconnect, and when paint is dried to room cooling state, refrigeration machine is communicated with boiler.
2. a kind of Furniture Factory according to claim 1 paint dries room cooling and heating circulation system, it is characterized in that, between described refrigeration machine and boiler, is connected by pipeline, and pipeline is provided with controls the switch valve that refrigeration machine is communicated with or disconnects with boiler.
3. a kind of Furniture Factory according to claim 2 paint dries room cooling and heating circulation system, it is characterized in that, the pipeline between refrigeration machine and boiler is provided with pressure gauge.
4. a kind of Furniture Factory according to claim 2 paint dries room cooling and heating circulation system, it is characterized in that, the pipeline between refrigeration machine and boiler is provided with delivery pump.
5. a kind of Furniture Factory according to claim 2 paint dries room cooling and heating circulation system, it is characterized in that, the pipeline between refrigeration machine and boiler is provided with choke valve.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201320869629.0U CN203635453U (en) | 2013-12-26 | 2013-12-26 | Thermal-cold cycling system of paint airing room of furniture factory |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201320869629.0U CN203635453U (en) | 2013-12-26 | 2013-12-26 | Thermal-cold cycling system of paint airing room of furniture factory |
Publications (1)
Publication Number | Publication Date |
---|---|
CN203635453U true CN203635453U (en) | 2014-06-11 |
Family
ID=50866735
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201320869629.0U Expired - Fee Related CN203635453U (en) | 2013-12-26 | 2013-12-26 | Thermal-cold cycling system of paint airing room of furniture factory |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN203635453U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104807248A (en) * | 2015-03-30 | 2015-07-29 | 宁波杭州湾新区祥源动力供应有限公司 | Centralized cold/ heat source system for circulating water system of workshop |
-
2013
- 2013-12-26 CN CN201320869629.0U patent/CN203635453U/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104807248A (en) * | 2015-03-30 | 2015-07-29 | 宁波杭州湾新区祥源动力供应有限公司 | Centralized cold/ heat source system for circulating water system of workshop |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107228436A (en) | A kind of air-conditioning system cold with ground based on solar energy | |
CN104818779A (en) | Ventilation heat recovery radiation external wall system | |
CN105180388A (en) | Vertical heat pipe heat recovery unit used in double seasons | |
CN204404419U (en) | Realize the combined air-conditioning system of independent temperature-humidity control | |
CN109362427B (en) | Energy-saving greenhouse constant temperature system and control method thereof | |
CN206651620U (en) | A kind of energy-saving variable-temperature mattress | |
CN203635453U (en) | Thermal-cold cycling system of paint airing room of furniture factory | |
CN105042815A (en) | Secondary heat recovery heat-tube type air conditioning system | |
CN205090501U (en) | Air conditioning unit system | |
CN205300063U (en) | Freeze -proof device for condenser | |
CN102778033B (en) | Air energy water heater | |
CN204421194U (en) | Indoor apparatus of air conditioner and air-conditioning | |
CN203572134U (en) | Energy-saving type combined home appliance | |
CN205686124U (en) | Air conditioning for automobiles cold air adjusting means | |
CN203068711U (en) | Air-conditioning coupled application system | |
CN104089350B (en) | A kind of warm and humid independent control soil natural source capillary tube air conditioning system | |
CN203928489U (en) | Air conditioner and water heater | |
CN203518099U (en) | Outdoor direct anti-freezing cold-taking device used in cold seasons | |
CN203785319U (en) | Solar energy combined integrated heating and cooling system for country | |
CN204880396U (en) | Plum rains indoor dehumidification mould proof governing system in season | |
CN204786878U (en) | Trigeminy supplies outer machine of air conditioner | |
CN205394902U (en) | Aminoplast moisture automatic control system | |
CN206207620U (en) | Embrane method solution wind formula refrigeration plant | |
CN205641675U (en) | Cold -stored multifunctional integral machine group of stoving hot water | |
CN205174630U (en) | Energy -efficient solar energy air dewetting machine system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |