CN203628284U - Pressure adjusting apparatus for natural gas supplying of natural gas boiler - Google Patents
Pressure adjusting apparatus for natural gas supplying of natural gas boiler Download PDFInfo
- Publication number
- CN203628284U CN203628284U CN201320805076.2U CN201320805076U CN203628284U CN 203628284 U CN203628284 U CN 203628284U CN 201320805076 U CN201320805076 U CN 201320805076U CN 203628284 U CN203628284 U CN 203628284U
- Authority
- CN
- China
- Prior art keywords
- pressure
- natural gas
- pipeline
- pressure adjusting
- inlet
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Feeding And Controlling Fuel (AREA)
Abstract
A pressure adjusting apparatus for natural gas supplying of a natural gas boiler is formed by two paratactic pressure adjusting pipelines, an inlet pressure gage and an outlet pressure gage, wherein each pressure adjusting pipeline comprises an inlet ball valve, a pressure adjuster and an outlet ball valve; the inlet ball valve, the pressure adjuster and the outlet ball valve are in a serial connection via pipelines; the inlet pressure gage and the outlet pressure gage are respectively arranged on an air inlet pipeline in front of the pressure adjusting pipeline and an air outlet pipeline of the back of the pressure adjusting pipeline; and the air inlet pipeline and the air outlet pipeline are arranged side by side. The pressure adjusting apparatus for natural gas supplying of the natural gas boiler is advantageous in that the two paratactic pressure adjusting pipelines in the pressure adjusting apparatus operate one-on-one; when the pressure adjusters of the pressure adjusting pipelines during operation break down, the fore-and-aft ball valves can be shut down; fore-and-aft ball valves of a spare pipeline are opened, so natural gas is provided; and maintenance of the pressure adjusters are facilitated, so safe natural gas supplying of the natural gas boiler is effectively guaranteed.
Description
(1) technical field
The utility model relates to natural gas pressure regulating device, particularly a kind of regulator for natural gas boiler air feed
(2) background technique
Along with rapid development of economy, the situation day take oil as the energy is becoming tight.Boiler no longer only depends on coal, wet goods fuel, and rock gas becomes rapidly main flow fuel as the new energy of cleanliness without any pollution.But because the pressure of pipe natural gas generally all can be higher than the required pressure of boiler burning rock gas, this just need to drop to the pressure of pipe natural gas the regulator of a kind of rock gas of the required pressure of boiler burning.
(3) model utility content
The purpose of this utility model is for above-mentioned existing problems, provide that a kind of flow setting is simple, compact structure, easy to use, invest little, for ease of maintenaince operation and the safe and reliable regulator for natural gas boiler air feed.
The technical solution of the utility model:
A kind of regulator for natural gas boiler air feed, formed by two pressure regulation pipelines arranged side by side and inlet pressure gauge and delivery gauge, each pressure regulation pipeline comprise inlet ball valve, pressure governor and vent ball valve and by pipeline be connected in series, inlet pressure gauge and delivery gauge are arranged at respectively the admission line before pressure regulation pipeline arranged side by side and outlet pipe below on.
The utility model has the advantages that: it is capable that a received shipment is opened in two pressure regulation pipelines employings one arranged side by side in this regulator, in the time that the pressure governor of operating pressure regulation pipeline breaks down, can close the ball valve of its front and back, then open the ball valve air feed of front and back, road for subsequent use, can conveniently carry out the maintenance of fault pressure governor, can effectively guarantee the safe way of natural gas boiler simultaneously.
(4) accompanying drawing explanation
Accompanying drawing is this regulator schematic diagram for natural gas boiler air feed.
In figure: 1. inlet ball valve 2. pressure governor HSR 3. vent ball valves
4. inlet pressure gauge 5. delivery gauges
(5) embodiment
Embodiment:
A kind of regulator for natural gas boiler air feed, formed by two pressure regulation pipelines arranged side by side and inlet pressure gauge 4 and delivery gauge 5, each pressure regulation pipeline comprise inlet ball valve 1, pressure governor 2 and vent ball valve 3 and by pipeline be connected in series, inlet pressure gauge 4 and delivery gauge 5 are arranged at respectively the admission line before pressure regulation pipeline arranged side by side and outlet pipe below on.
In this embodiment, the model of importing and exporting ball valve is Q41F-25C DN25; The model of pressure governor is HSR DN25PN16; Inlet pressure gauge model is Y100 0-0.6MPa, and delivery gauge model is Y100 0-10KPa.
When this regulator operation, first slowly open the inlet ball valve of the pressure regulation pipeline using, regulate the pressure of pressure governor, open the vent ball valve after pressure governor, observe manometric reading, make outlet pressure adjust to the required pressure of boiler; In the time using the pressure governor on road to break down, the ball valve of closing its front and back, slowly opens the inlet ball valve on road for subsequent use.
Claims (1)
1. the regulator for natural gas boiler air feed, it is characterized in that: formed by two pressure regulation pipelines arranged side by side and inlet pressure gauge and delivery gauge, each pressure regulation pipeline comprise inlet ball valve, pressure governor and vent ball valve and by pipeline be connected in series, inlet pressure gauge and delivery gauge are arranged at respectively the admission line before pressure regulation pipeline arranged side by side and outlet pipe below on.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201320805076.2U CN203628284U (en) | 2013-12-06 | 2013-12-06 | Pressure adjusting apparatus for natural gas supplying of natural gas boiler |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201320805076.2U CN203628284U (en) | 2013-12-06 | 2013-12-06 | Pressure adjusting apparatus for natural gas supplying of natural gas boiler |
Publications (1)
Publication Number | Publication Date |
---|---|
CN203628284U true CN203628284U (en) | 2014-06-04 |
Family
ID=50814758
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201320805076.2U Expired - Fee Related CN203628284U (en) | 2013-12-06 | 2013-12-06 | Pressure adjusting apparatus for natural gas supplying of natural gas boiler |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN203628284U (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104989954A (en) * | 2015-07-08 | 2015-10-21 | 内蒙古包钢钢联股份有限公司 | Device and method used for cleaning jam of coking coal flow adjusting valve of CCPP set |
CN106287228A (en) * | 2015-06-05 | 2017-01-04 | 江苏腾天工业炉有限公司 | Industrial gas furnace voltage stabilizing pipe-line system |
CN109351099A (en) * | 2018-12-06 | 2019-02-19 | 江苏纵湖涂装设备产业研究院有限公司 | A kind of coating waste gas processor of adjustable exhaust gas flow |
-
2013
- 2013-12-06 CN CN201320805076.2U patent/CN203628284U/en not_active Expired - Fee Related
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106287228A (en) * | 2015-06-05 | 2017-01-04 | 江苏腾天工业炉有限公司 | Industrial gas furnace voltage stabilizing pipe-line system |
CN104989954A (en) * | 2015-07-08 | 2015-10-21 | 内蒙古包钢钢联股份有限公司 | Device and method used for cleaning jam of coking coal flow adjusting valve of CCPP set |
CN104989954B (en) * | 2015-07-08 | 2019-03-29 | 内蒙古包钢钢联股份有限公司 | For clearing up the device and method of CCPP unit coking coal flow tune valve bite |
CN109351099A (en) * | 2018-12-06 | 2019-02-19 | 江苏纵湖涂装设备产业研究院有限公司 | A kind of coating waste gas processor of adjustable exhaust gas flow |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN203628284U (en) | Pressure adjusting apparatus for natural gas supplying of natural gas boiler | |
CN204328479U (en) | A kind of Gas Pressure Regulating Equipment adopting the uninterrupted air feed of monitoring guarantee in parallel | |
CN207348904U (en) | A kind of one grade of steam loss regulating system of turbine shaft seal | |
CN204756455U (en) | A regulator for natural gas air feed | |
CN202598130U (en) | Self-gas-supplying system controlled by pressure adjusting device of compressed natural gas | |
CN205137083U (en) | A pressure regulating box for natural gas air feed | |
CN219526556U (en) | BGL gasifier nitrogen gas feed system | |
CN202580627U (en) | Liquefied natural gas feeding pry | |
CN201449321U (en) | Composite test device for pressure pulse | |
CN204328484U (en) | A kind of Gas Pressure Regulating Equipment adopting series connection monitoring | |
CN102252161A (en) | Air-temperature-type air supply device for marine natural gas engine | |
CN202692444U (en) | Improved structure for pressure difference startup device for combustion gas water heater | |
CN205858495U (en) | Burning machine inlet Distribution of Natural system | |
CN215626805U (en) | Nitrogen preparation system for power plant | |
CN202430106U (en) | Natural gas supply guaranteeing system of glass tank furnace | |
CN201650387U (en) | Device for cooling high pressure cylinder of steam turbine | |
CN107559051A (en) | A kind of one grade of steam loss regulating system of turbine shaft seal and its adjusting method | |
CN204629093U (en) | A kind of steam Small Flow Control System | |
CN204647525U (en) | The ball valve of water turbine of double locking | |
CN202611879U (en) | Combustible gas pressure boost and stabilization device for gas turbine generator | |
CN202194739U (en) | Natural gas power generation device adopting spiral separation for regulating pressure | |
CN204899989U (en) | Controlling means of extraction valve on steam turbine | |
CN113401881A (en) | Nitrogen preparation system for power plant | |
CN203906014U (en) | Steam supplying system of turbine low-pressure cylinder end shaft seal | |
CN202125727U (en) | Air temperature heat exchange type decompression device for compressed natural gas |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20140604 Termination date: 20161206 |
|
CF01 | Termination of patent right due to non-payment of annual fee |