CN203624916U - Well logging pulley - Google Patents

Well logging pulley Download PDF

Info

Publication number
CN203624916U
CN203624916U CN201320797318.8U CN201320797318U CN203624916U CN 203624916 U CN203624916 U CN 203624916U CN 201320797318 U CN201320797318 U CN 201320797318U CN 203624916 U CN203624916 U CN 203624916U
Authority
CN
China
Prior art keywords
cable
cell body
main frame
pulley
wheel assembly
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201320797318.8U
Other languages
Chinese (zh)
Inventor
龚光勇
张炳军
周扬
孙志忠
康国珍
杨大千
王生战
许琦
刘继红
扈勇
吴少威
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China National Petroleum Corp
China Petroleum Logging Co Ltd
Original Assignee
China National Petroleum Corp
China Petroleum Logging Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China National Petroleum Corp, China Petroleum Logging Co Ltd filed Critical China National Petroleum Corp
Priority to CN201320797318.8U priority Critical patent/CN203624916U/en
Application granted granted Critical
Publication of CN203624916U publication Critical patent/CN203624916U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Laying Of Electric Cables Or Lines Outside (AREA)

Abstract

The utility model discloses a well logging pulley including a joint, a main body frame, a wheel assembly provided with a first groove body and a second groove body, and a suspension ring, the top of the main body frame is connected with an elevator apparatus of a drilling crew via the joint, the bottom of the main body frame is connected with the suspension ring, the wheel assembly is arranged at the hollow part in the middle of the main body frame via a center shaft, the first groove body is arranged on the outer periphery of the wheel assembly to be used for the operation of a hard cable, and the second groove body is arranged at the bottom of the first groove body to be used for the operation of a conventional cable. The well logging pulley allows cables in any diameter to smoothly pass through by arranging the first groove body and the second groove body on the wheel assembly, when a hank of cable is combined by cables in different diameter, the hank of cable also can pass through smoothly, so that different construction requirements on the logging of a horizontal well and an inclined shaft can be met.

Description

Well surveying pulley
Technical field
The utility model relates to petroleum well logging technology field, particularly a kind of well surveying pulley.
Background technology
Well head pulley is the specialized equipment in well logging, perforation, side-wall coring operation.Well head pulley is the equipment for changing cable service direction, and cable is gone into the well by it, and drives it to rotate.It can support the use with other well head specialized equipments (as tension gauge etc.).It is 1.5 meters and 2.5 meters two kinds that conventional pulley generally has girth, and the cable that is applicable to diameter of the same race passes through, and limitation is large.
Utility model content
The purpose of this utility model is to provide the well surveying pulley that a kind of cable that can be used for multiple diameter passes through.
For solving the problems of the technologies described above, the utility model provides a kind of well surveying pulley, comprising: connector, main frame, be provided with wheel assembly and the suspension ring of the first cell body and the second cell body;
Described main frame top is by described connector and drill crew's elevator equipment connection, and described main frame bottom is connected with described suspension ring;
Described wheel assembly is arranged on the hollow part in the middle of described main frame by center shaft, described the first cell body is arranged on the outer circumference surface of described wheel assembly, for the operation of hard cable, described the second cell body is arranged on described the first cell body bottom, for the operation of normal cable.
Further, described well surveying pulley, also comprises:
Support, described support is arranged on the both sides of described main frame by center shaft, prevent cable job-hopping by opening support.
Further, described well surveying pulley, also comprises:
Cleaning shoe assembly, described cleaning shoe assembly is arranged on main frame inside top, and near described wheel assembly top, for the mud on cable is cleared up.
Further, described cleaning shoe assembly comprises:
Cleaning shoe and fix screw, described cleaning shoe is fixedly connected with described main frame by described fix screw.
Further, described cleaning shoe bottom section is the right angle trigonometry shape of handstand.
Further, the diameter of described the first cell body is 0.8-1.1 rice, is applicable to the hard cable operation that diameter is less than or equal to 38mm.
Further, the diameter of described the second cell body is 0.8 meter, is applicable to the normal cable operation that diameter is less than or equal to 11.8mm.
The well surveying pulley that the utility model provides, by the first cell body and the second cell body are set on wheel assembly, the cable of any diameter all can be passed through smoothly, when the hank of cable also can be passed through together time smoothly by the cable assembly of different-diameter, can meet the different construction requirements of horizontal drainhole and inclined shaft well logging.
Accompanying drawing explanation
The structural representation of the well surveying pulley that Fig. 1 provides for the utility model embodiment;
Fig. 2 is the lateral plan of well surveying pulley shown in Fig. 1;
Fig. 3 is the structural representation of I part in well surveying pulley structure shown in Fig. 2;
Structural representation when Fig. 4 is the medium-height trestle of well surveying pulley structure shown in Fig. 1 open mode.
The specific embodiment
Referring to Fig. 1-3, a kind of well surveying pulley that the utility model embodiment provides, comprises connector 1, main frame 7, support 6, cleaning shoe assembly 2, the wheel assembly 5 that is provided with the first cell body 5-1 and the second cell body 5-2 and suspension ring 8; Main frame 7 tops are by connector 1 and creep into group elevator equipment connection, and main frame 7 bottoms are connected with suspension ring 8; Wheel assembly 5 is arranged on the hollow part in the middle of main frame 7 by center shaft, and the first cell body 5-1 is arranged on the outer circumference surface of wheel assembly 5, and the diameter of the first cell body 5-1 is 0.8-1.1 rice, is applicable to the hard cable 3 that diameter is less than or equal to 38mm and moves.The preferred value of the first cell body 5-1 diameter is 1 meter, and cable can only bear sinuousness to a certain degree, when curvature hour, can reduce the service life of cable, and break-make decreasing insulating, in the time adopting the cell body of 1 rice diameter, cable can be not influenced, and service life and break-make insulating power are good.The second cell body 5-2 is arranged on the first cell body 5-1 bottom, and the diameter of the second cell body 5-2 is 0.8 meter, is applicable to the normal cable operation that diameter is less than or equal to 11.8mm.If necessary, can improve the diameter of two cell bodies.
Support 6 is arranged on the both sides of main frame 7 by center shaft, prevent cable job-hopping by opening support 6.Cleaning shoe assembly 2 is arranged on main frame 7 inside top, and near wheel assembly 5 tops, for the mud on cable is cleared up.Cleaning shoe assembly 2 comprises: cleaning shoe and fix screw, cleaning shoe is fixedly connected with main frame 7 by fix screw.Cleaning shoe bottom section is the right angle trigonometry shape of handstand, can make cleaning shoe more in exchange premium the first cell body 5-1, and actv. strikes off cable and brings the mud in the first cell body 5-1 and the second cell body 5-2 into more.
At work, hard cable 3, first by pulley, as shown in Figure 4, in the course of the work, is opened the support on pulley 6 to both direction, make the free-running operation in the first cell body 5-1 under the protection of support 6 of hard cable 3.When in hard cable 3 lower going-into-wells of certain length, its latter linked normal cable 4, by pulley, moves in the second cell body 5-2 of pulley.By the first cell body 5-1 and the second cell body 5-2 are set on wheel assembly 5, make ¢ 11.8mm normal cable 4 when by pulley, keep stable, do not swing back and forth, the hard cable 3 that diameter is larger also can steadily pass through in the first cell body 5-1, does not occur the hidden danger such as job-hop.On hard cable 3 and normal cable 4, carry in process, hard cable 3 can be attached on the first cell body 5-1 and the second cell body 5-2 of pulley with the mud that normal cable 4 is brought from well, can remove the mud on the first cell body 5-1 and the second cell body 5-2 by cleaning shoe assembly 2.
The well surveying pulley that the utility model provides, its beneficial effect is as follows:
(1) by the first cell body and the second cell body are set on wheel assembly, the cable of any diameter all can be passed through smoothly, when the hank of cable also can be passed through together time smoothly by the cable assembly of different-diameter, can in pulley, not swing back and forth, can meet the different construction requirements of horizontal drainhole and inclined shaft well logging.
(2) by increasing cleaning shoe assembly, can carry out secondary cleaning to cable, the mud being attached on cable is scraped totally.
It should be noted last that, the above specific embodiment is only unrestricted in order to the technical solution of the utility model to be described, although the utility model is had been described in detail with reference to example, those of ordinary skill in the art is to be understood that, can modify or be equal to replacement the technical solution of the utility model, and not departing from the spirit and scope of technical solutions of the utility model, it all should be encompassed in the middle of claim scope of the present utility model.

Claims (7)

1. a well surveying pulley, is characterized in that, comprising:
Connector, main frame, be provided with wheel assembly and the suspension ring of the first cell body and the second cell body;
Described main frame top is by described connector and drill crew's elevator equipment connection, and described main frame bottom is connected with described suspension ring;
Described wheel assembly is arranged on the hollow part in the middle of described main frame by center shaft, described the first cell body is arranged on the outer circumference surface of described wheel assembly, for the operation of hard cable, described the second cell body is arranged on described the first cell body bottom, for the operation of normal cable.
2. well surveying pulley as claimed in claim 1, is characterized in that, also comprises:
Support, described support is arranged on the both sides of described main frame by center shaft, prevent cable job-hopping by opening support.
3. well surveying pulley as claimed in claim 1, is characterized in that, also comprises:
Cleaning shoe assembly, described cleaning shoe assembly is arranged on main frame inside top, and near described wheel assembly top, for the mud on cable is cleared up.
4. well surveying pulley as claimed in claim 3, is characterized in that, described cleaning shoe assembly comprises:
Cleaning shoe and fix screw, described cleaning shoe is fixedly connected with described main frame by described fix screw.
5. well surveying pulley as claimed in claim 4, is characterized in that:
Described cleaning shoe bottom section is the right angle trigonometry shape of handstand.
6. well surveying pulley as claimed in claim 1, is characterized in that:
The diameter of described the first cell body is 0.8-1.1 rice, is applicable to the hard cable operation that diameter is less than or equal to 38mm.
7. well surveying pulley as claimed in claim 1, is characterized in that:
The diameter of described the second cell body is 0.8 meter, is applicable to the normal cable operation that diameter is less than or equal to 11.8mm.
CN201320797318.8U 2013-12-05 2013-12-05 Well logging pulley Expired - Fee Related CN203624916U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201320797318.8U CN203624916U (en) 2013-12-05 2013-12-05 Well logging pulley

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201320797318.8U CN203624916U (en) 2013-12-05 2013-12-05 Well logging pulley

Publications (1)

Publication Number Publication Date
CN203624916U true CN203624916U (en) 2014-06-04

Family

ID=50811410

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201320797318.8U Expired - Fee Related CN203624916U (en) 2013-12-05 2013-12-05 Well logging pulley

Country Status (1)

Country Link
CN (1) CN203624916U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113464077A (en) * 2021-07-06 2021-10-01 江苏腾龙石化机械有限公司 Multifunctional petroleum wellhead

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113464077A (en) * 2021-07-06 2021-10-01 江苏腾龙石化机械有限公司 Multifunctional petroleum wellhead

Similar Documents

Publication Publication Date Title
CN207434976U (en) A kind of communication construction is ascended a height auxiliary device
CN203765634U (en) Structurally improved robot
CN203624916U (en) Well logging pulley
CN204308677U (en) With the angle steel automatic drilling device of turning of drilling rod bucker
CN201711563U (en) Tool for drilling holes in narrow place
CN203685051U (en) Universal support bar based on portable drilling machine mast
CN104308796A (en) Portable assembling and disassembling stand for downhole tool
CN202338328U (en) Sheet type centering device with controllable size of external diameter
CN209129547U (en) A kind of drill pipe for hard rocks structure with Telescopic protection hood
CN201206435Y (en) Following rack for rotary drill rig
CN204536037U (en) A kind of electronic brill
CN206327553U (en) A kind of screen type ship side pushes away capping apparatus
CN204135982U (en) A kind of portable assembling and disassembling stand for downhole tool
CN206076895U (en) A kind of extra large cable centralized positioning clamp traction apparatuss
CN204415682U (en) A kind of twin-well frame drilling ship
CN204663503U (en) Coal bed gas spinning hydraulic jet cave making tool
CN204877260U (en) Dig rig unit head soon and dig rig soon
CN204123274U (en) A kind of double-ended grinding machine is with the cooling device of swivel joint
CN104295230B (en) Submersible drilling machine
CN106894763A (en) A kind of oil and gas exploration and Work robot
CN207110990U (en) One kind weighing apparatus moment of torsion drilling speed instrument
CN205004462U (en) High -efficient ground connection borer
CN206144485U (en) Centralizer interfacing apparatus
CN206148714U (en) Connect interfacing apparatus
CN207265555U (en) A kind of gate cable laying coaster

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20140604

Termination date: 20211205