CN203598912U - Inlet air duct for coal mill - Google Patents

Inlet air duct for coal mill Download PDF

Info

Publication number
CN203598912U
CN203598912U CN201320695217.XU CN201320695217U CN203598912U CN 203598912 U CN203598912 U CN 203598912U CN 201320695217 U CN201320695217 U CN 201320695217U CN 203598912 U CN203598912 U CN 203598912U
Authority
CN
China
Prior art keywords
air duct
coal
air channel
deflector
inlet
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201320695217.XU
Other languages
Chinese (zh)
Inventor
李海送
陈雪峰
王力强
刘进峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
International Lv Si Of Jiangsu Datang Port Power Generation Corp Ltd
Original Assignee
International Lv Si Of Jiangsu Datang Port Power Generation Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by International Lv Si Of Jiangsu Datang Port Power Generation Corp Ltd filed Critical International Lv Si Of Jiangsu Datang Port Power Generation Corp Ltd
Priority to CN201320695217.XU priority Critical patent/CN203598912U/en
Application granted granted Critical
Publication of CN203598912U publication Critical patent/CN203598912U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Crushing And Grinding (AREA)

Abstract

The utility model relates to an inlet air duct for a coal mill. The inlet air duct comprises a primary air duct, wherein the primary air duct is provided with a plurality of first guide plates which are arranged at certain intervals at an inlet segment in front of a scraper chamber of the coal mill; the rotating direction of a scraper in the scraper chamber is accordant with the guiding directions of the first guide plates; a dead corner formed at the inlet segment of the primary air duct in a direction opposite to the rotating direction of the scraper is enclosed by arranging second guide plates and a plurality of steel plates assembled together with the second guide plates; and the guiding directions of the second guide plates are accordant with those of the first guide plates. By adopting the inlet air duct, the phenomenon of burnout of the inlet air duct of the coal mill due to piling and spontaneous combustion of pebble coal at the inlet of the air duct can be avoided effectively. The inlet air duct for the coal mill has the advantages of small investment on reconstruction, easiness in construction, quick response and great benefit.

Description

Coal pulverizer inlet air channel
Technical field
The utility model relates to the field of boiler coal-ash preparation system, particularly a kind of coal pulverizer inlet air channel.
Background technology
Current coal supply anxiety, power plant's power ature of coal is difficult to be fundamentally improved in a short time, and for reducing costs, fire coal is mixed and is burnt till as inevitable.Pulverized coal preparation system is coal-fired unit direct-firing, configuration medium-speed pulverizer, and in the time using the higher coal of fugitive constituent, Ignition Phenomena easily burns in coal pulverizer inlet air channel.
For example, certain boiler milling system is direct-firing, 6 respectively corresponding 6 HP-1003/Dyn intermediate-speed bowl mills of belt coal feeder; Use when design coal 5 use 1 for subsequent use, use while checking coal 6 all to come into operation.On every coal pulverizer, there are four airducts that qualified coal dust is delivered to burner hearth four walls, an airduct of drawing on A, B, C, D, E, F mill A, B, C, D, E, the F layer of corresponding burner hearth respectively; An airduct temperature design of coal pulverizer outlet is 76-90 ℃.But in the time using the higher coal of fugitive constituent, not in time, pebble coal is easily piled up and spontaneous combustion at coal pulverizer inlet air channel place, scaling loss coal pulverizer inlet air channel for as large in pebble coal amount and discharge.
Find by analysis, as shown in Figure 1, air channel 1 of coal pulverizer is designed with some spaced apart deflectors 3 entering before coal pulverizer scraper plate chamber 2, the direction (shown in arrow 4) that scraper plate rotates is consistent with the guiding of deflector 3, but the opposite direction of rotating at air channel entrance scraper plate can form dead angle 5.When using the coal that fugitive constituent is higher, and pebble coal amount is when large, and pebble coal enters dead angle 5 under the effect of scraper plate, along with the increase of accumulating amount, as now primary air flow is relatively little, pebble coal will enter an air channel and deposit, and then generation spontaneous combustion, air channel entrance of scaling loss coal pulverizer.
Utility model content
The purpose of this utility model is to provide a kind of coal pulverizer inlet air channel, by local flow improvement is carried out in an air channel, avoid occurring betiding in the time using the higher coal of fugitive constituent the burning Ignition Phenomena in coal pulverizer inlet air channel, being particularly useful for pulverized coal preparation system is coal-fired unit direct-firing, configuration medium-speed pulverizer.
In order to achieve the above object, the technical solution of the utility model is to provide a kind of coal pulverizer inlet air channel, it comprises air channel one time, this air channel is at the entrance entering before the scraper plate chamber of coal pulverizer, be provided with some spaced apart the first deflectors, the direction that the indoor scraper plate of described scraper plate rotates is consistent with the guiding of described the first deflector; By the second deflector and some steel plates of assembling are with it set, by be in an air channel this entrance, be formed at scraper plate and rotate the sealing of reciprocal dead angle; The guiding of described the second deflector is consistent with the guiding of described the first deflector.
Preferably, all shut along short transverse assembled the second deflector and steel plate at described dead angle.
Preferably, the distance between described the second deflector and with it adjacent the first deflector, and spacing between any two adjacent the first deflectors is identical or different.
Preferably, the thickness δ=5mm of described steel plate, or δ=10mm.
Compared with prior art, the advantage in coal pulverizer inlet described in the utility model air channel is, by a newly-increased deflector and the steel plate of assembly and connection with it, porch, air channel is formed to scraper plate and rotates the sealing of reciprocal dead angle, thereby avoid pebble coal etc. to pile up spontaneous combustion and the phenomenon in scaling loss coal pulverizer inlet air channel occurs at air channel entrance.Less investment, easily construction, instant effect, the income of the utility model to coal pulverizer inlet transformation of air duct is large.
Accompanying drawing explanation
Fig. 1 is the structural representation in existing coal pulverizer inlet air channel;
Fig. 2 is the structural representation in coal pulverizer inlet described in the utility model air channel.
The specific embodiment
As shown in Figure 2, the utility model provides a kind of coal pulverizer inlet air channel, wherein air channel 1 is designed with several spaced apart the first deflectors 31 entering before coal pulverizer scraper plate chamber 2, and the direction (shown in arrow 4) that scraper plate chamber 2 inside strakes rotate is consistent with the guiding of these the first deflectors 31.In the utility model, pass through the some steel plates 6 of assembling and a second newly-increased deflector 32, to be in air channel entrance, and be formed at scraper plate and rotate reciprocal dead angle sealing (sealing place is expressed as to 7), thereby using the coal that fugitive constituent is higher, for example, when pebble coal, fire coal is not easy to pile up in 1 porch, air channel of coal pulverizer, thereby avoids occurring the phenomenon in spontaneous combustion scaling loss coal pulverizer inlet air channel.
Specifically, the second newly-increased deflector 32 is just arranged at the dead angle place of air channel 1 entrance of coal pulverizer, and its guiding is consistent with the guiding of other the first deflectors 31.In different application examples, the distance between the second deflector 32 and with it adjacent the first deflector 31, and spacing between any two adjacent the first deflectors 31 is identical or different.
Except described the second deflector 32, remaining some steel plate 6(thickness δ=5mm for dead angle area, or δ=10mm) shut, reflux to eliminate a wind, and stop pebble coal to be piled up at this.When construction, dead angle will all be shut along short transverse, and the necessary full weld of weld seam, prevents that coal dust from entering the confined space inside of shutting, and causes spontaneous combustion of pulverized coal.
It is coal-fired unit direct-firing, configuration medium-speed pulverizer that the utility model is particularly useful for pulverized coal preparation system.Transformation can utilize while stopping mill maintenance and implement, and also can in the time of unit maintenance, carry out.Less investment, easily construction, instant effect, the income of the utility model to coal pulverizer inlet transformation of air duct is large.
Although content of the present utility model has been done detailed introduction by above preferred embodiment, will be appreciated that above-mentioned description should not be considered to restriction of the present utility model.Read after foregoing those skilled in the art, for multiple modification of the present utility model and substitute will be all apparent.Therefore, protection domain of the present utility model should be limited to the appended claims.

Claims (4)

1. a coal pulverizer inlet air channel, it is characterized in that, comprise an air channel (1), this air channel (1) is entering the front entrance in scraper plate chamber (2) of coal pulverizer, be provided with some spaced apart the first deflectors (31), the direction that described scraper plate chamber (2) inside strake rotates is consistent with the guiding of described the first deflector (31); By the second deflector (32) and some steel plates (6) of assembling are with it set, by be in an air channel (1) this entrance, be formed at scraper plate and rotate the sealing of reciprocal dead angle; The guiding of described the second deflector (32) is consistent with the guiding of described the first deflector (31).
2. coal pulverizer inlet as claimed in claim 1 air channel, is characterized in that,
All shut along assembled the second deflector (32) of short transverse and steel plate (6) at described dead angle.
3. coal pulverizer inlet as claimed in claim 1 air channel, is characterized in that,
Distance between described the second deflector (32) and with it adjacent the first deflector (31), and spacing between any two adjacent the first deflectors (31) is identical or different.
4. coal pulverizer inlet as claimed in claim 1 air channel, is characterized in that,
Thickness δ=the 5mm of described steel plate (6), or δ=10mm.
CN201320695217.XU 2013-11-06 2013-11-06 Inlet air duct for coal mill Expired - Fee Related CN203598912U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201320695217.XU CN203598912U (en) 2013-11-06 2013-11-06 Inlet air duct for coal mill

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201320695217.XU CN203598912U (en) 2013-11-06 2013-11-06 Inlet air duct for coal mill

Publications (1)

Publication Number Publication Date
CN203598912U true CN203598912U (en) 2014-05-21

Family

ID=50711613

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201320695217.XU Expired - Fee Related CN203598912U (en) 2013-11-06 2013-11-06 Inlet air duct for coal mill

Country Status (1)

Country Link
CN (1) CN203598912U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110394231A (en) * 2019-07-19 2019-11-01 国家能源集团宁夏煤业有限责任公司 Coal pulverizer

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110394231A (en) * 2019-07-19 2019-11-01 国家能源集团宁夏煤业有限责任公司 Coal pulverizer

Similar Documents

Publication Publication Date Title
CN104180368A (en) Medium-and-low temperature hot fume powder feeding type coal powder combustion device and combustion process thereof
CN103672883A (en) Grid type swirl burner
CN203598912U (en) Inlet air duct for coal mill
CN103292342B (en) A kind of bituminous coal fired boiler that uses mixes the method for burning Xinjiang Guang Hui brown coal
CN204460265U (en) Coal dust piece-rate system in a kind of boiler milling system
CN202598507U (en) Novel steady burning tooth for lignite swirling burner
CN209084811U (en) A kind of pulverized coal preparation system that flame kernel is controllable mill dislocation pulverized coal channel arrangement system
CN204187657U (en) Point powder dust feeder and the ignition system for boiler of ignition system
CN202253598U (en) Boiler system using combustion high-moisture lignitic coal
US8789479B2 (en) Oxygen mixer for oxygen combustion boiler
CN205065771U (en) Directly blow high -efficient blast proof stove cigarette of formula coal pulverizer and mix fever device
CN204665251U (en) A kind of energy-saving efficient boiler
CN104654321A (en) Bagasse burning boiler
CN202813423U (en) Coal powder homogenizer
CN203784939U (en) Oxygen-enriched micro oil staged combustion device
CN203216268U (en) Preheating box of sintering ignition furnace
CN102313281A (en) Method for reducing nitrogen oxides generated by coal-fired boiler tertiary air combustion
CN201875730U (en) Boiler pulverizing system for the combustion of brown coal in set combined power station with smoke tower
CN205988806U (en) The fan mill arrangement system of tower 350MW super critical boiler
CN204187659U (en) Row's powder bellows and ignition system for boiler
CN203744276U (en) Boiler with bagasse as fuel
CN105805726A (en) A biomass hot water combustion furnace
CN205008025U (en) Coal pulverizer device
CN205481720U (en) Environment -protecting energy -saving boiler
CN201783383U (en) Medium-speed coal mill wind sealing device of thermal power plant

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20140521

Termination date: 20211106