CN203586830U - Calcium carbide furnace blanking pipe with reinforcing rib and calcium carbide furnace with calcium carbide furnace blanking pipe - Google Patents

Calcium carbide furnace blanking pipe with reinforcing rib and calcium carbide furnace with calcium carbide furnace blanking pipe Download PDF

Info

Publication number
CN203586830U
CN203586830U CN201320607205.7U CN201320607205U CN203586830U CN 203586830 U CN203586830 U CN 203586830U CN 201320607205 U CN201320607205 U CN 201320607205U CN 203586830 U CN203586830 U CN 203586830U
Authority
CN
China
Prior art keywords
calcium carbide
furnace
reinforcement
pipe
ceramic body
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn - After Issue
Application number
CN201320607205.7U
Other languages
Chinese (zh)
Inventor
王文战
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhengzhou Nai Dounai Material Science And Technology Ltd
Original Assignee
Zhengzhou Nai Dounai Material Science And Technology Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhengzhou Nai Dounai Material Science And Technology Ltd filed Critical Zhengzhou Nai Dounai Material Science And Technology Ltd
Priority to CN201320607205.7U priority Critical patent/CN203586830U/en
Application granted granted Critical
Publication of CN203586830U publication Critical patent/CN203586830U/en
Anticipated expiration legal-status Critical
Withdrawn - After Issue legal-status Critical Current

Links

Images

Landscapes

  • Manufacture And Refinement Of Metals (AREA)

Abstract

The utility model provides a calcium carbide furnace blanking pipe with a reinforcing rib and a calcium carbide furnace with the calcium carbide furnace blanking pipe. The calcium carbide furnace blanking pipe comprises a ceramic pipe body, and the reinforcing rib is vertically arranged on the inner wall of the ceramic pipe body. The calcium carbide furnace comprises a furnace body and electrodes vertically mounted in the furnace body, and at least three calcium carbide furnace blanking pipes surround the periphery of each electrode. The ceramic blanking pipe replaces a metal blanking pipe, the problems of burn-off and electrification of the blanking pipe are effectively avoided, an insulating layer between each blanking pipe and the furnace body is omitted, the service life of the blanking pipe is greatly prolonged, the insulating property of the blanking pipe is improved, and loss of electric energy is prevented. The calcium carbide furnace blanking pipe with the reinforcing rib and the calcium carbide furnace with the calcium carbide furnace blanking pipe have the advantages of scientific design, long service life, fine insulating property and prevention of electric energy loss.

Description

Furnace of calcium carbide tremie pipe with reinforcement and the furnace of calcium carbide with this furnace of calcium carbide tremie pipe
Technical field
The utility model relates to a kind of tremie pipe and furnace of calcium carbide, specifically, and the furnace of calcium carbide tremie pipe with reinforcement in carbon monoxide manufacturing equipment and the furnace of calcium carbide with this furnace of calcium carbide tremie pipe.
Background technology
In existing furnace of calcium carbide, have three to be the electrode that equilateral triangle is arranged, each electrode is provided with three tremie pipes around, and this tremie pipe is to be generally made by cast steel.Calcium carbide is in tremie pipe is fallen stove and at bottom of furnace body, be piled into a thick layer ofly, and three electrodes produce 2400 ℃ of above high temperature, and lower floor's calcium carbide is melted.When the calcium carbide melting is when discharged by furnace of calcium carbide discharging opening, calcium carbide layer can partly subside, and the high temperature hot gas that now has one 2200 ℃ of left and right, from the ejection of subsiding of calcium carbide layer, when this strand of hot gas is sprayed onto in described tremie pipe, can burn out tremie pipe.And can produce induction field when three electrode work, make on two tremie pipes between electrode charged, people cause the accident in order to prevent electric leakage, can insulating barrier be set in the junction of tremie pipe and body of heater, although on the tremie pipe that prevents from like this leaking electricity with electricity still caused the waste of electric energy.
In order to solve the problem of above existence, people are seeking a kind of desirable technical solution always.
Summary of the invention
The purpose of this utility model is for the deficiencies in the prior art, thereby provides a kind of design science, long service life, good insulation preformance, prevent the furnace of calcium carbide tremie pipe with reinforcement that electric energy runs off and have the furnace of calcium carbide of this furnace of calcium carbide tremie pipe.
To achieve these goals, the technical scheme that the utility model adopts is: a kind of furnace of calcium carbide tremie pipe with reinforcement, comprise body, and described body is ceramic body, on described ceramic inboard wall of tube body, is vertically provided with reinforcement.
Based on above-mentioned, a side pipe wall of the described ceramic body lower end mouth of pipe extends to form baffle plate downwards.
Based on above-mentioned, be positioned on the tube wall of the described ceramic body lower end mouth of pipe of described baffle plate both sides and be respectively equipped with side discharge gate.
Based on above-mentioned, described ceramic body inside is provided with framework of steel reinforcement, and described reinforcement is inner is respectively arranged with described baffle interior the reinforcing bar being connected with described framework of steel reinforcement.
Based on above-mentioned, described ceramic body upper pipes mouth is established edge, and described framework of steel reinforcement passes described edge and forms reinforcing bar handle.
Adopt a furnace of calcium carbide for the described furnace of calcium carbide tremie pipe with reinforcement, comprise body of heater, be vertically arranged on the electrode in described body of heater, the surrounding of each described electrode is surrounded with at least three described furnace of calcium carbide tremie pipes.
Based on above-mentioned, the described ceramic body lower end mouth of pipe extends to form baffle plate downwards away from the tube wall of described electrode one side.
Based on above-mentioned, be positioned on the tube wall of the described ceramic body lower end mouth of pipe of described baffle plate both sides and be respectively equipped with side discharge gate.
Based on above-mentioned, described ceramic body inside is provided with framework of steel reinforcement, and described reinforcement is inner is respectively arranged with described baffle interior the reinforcing bar being connected with described framework of steel reinforcement.
Based on above-mentioned, described ceramic body upper pipes mouth is established edge, and described framework of steel reinforcement passes described edge and forms reinforcing bar handle.
The relative prior art of the utility model has substantive distinguishing features and progress, specifically, the utility model utilizes ceramic tremie pipe to replace metal tremie pipe, problem and the charged problem of tremie pipe of effectively having avoided tremie pipe to be burnt, and saved the insulating barrier between described tremie pipe and described body of heater, not only greatly improved the service life of tremie pipe, and improved the insulating properties of tremie pipe, prevented the loss of electric energy.This furnace of calcium carbide tremie pipe with reinforcement has design science, long service life, good insulation preformance with the furnace of calcium carbide with this furnace of calcium carbide tremie pipe, prevents that electric energy runs off.
Accompanying drawing explanation
Fig. 1 is the structural representation of furnace of calcium carbide tremie pipe.
Fig. 2 is the structural representation of furnace of calcium carbide.
In figure: 1. ceramic body; 2. reinforcement; 3. baffle plate; 4. edge; 5. body of heater; 6. electrode; 7. side discharge gate.
The specific embodiment
Below by the specific embodiment, the technical solution of the utility model is described in further detail.
As shown in Figure 1, a kind of furnace of calcium carbide tremie pipe with reinforcement, comprise body, described body is ceramic body 1, described body adopts ceramic body to replace metal tube, problem and the charged problem of tremie pipe of effectively having avoided tremie pipe to be burnt, the service life of not only greatly having improved tremie pipe, and improved the insulating properties of tremie pipe, prevented the loss of electric energy.On described ceramic body 1 inwall, be vertically provided with reinforcement 2, available technology adopting metal tube, do not need to establish reinforcement, just because of ceramic structural strength, be not so good as metal, so the effect of described reinforcement 2 is the structural strengths that effectively improve described ceramic body 1, makes not easy fracture of described ceramic body 1.
One side pipe wall of the described ceramic body 1 lower end mouth of pipe extends to form baffle plate 3 downwards, the benefit of design is like this: due to the barrier effect of described baffle plate 3, when calcium carbide falls in body of heater and while starting to pile up along described ceramic body 1, calcium carbide can only or face mutually on the same group described ceramic body 1 one sides and pile up towards electrode one side, the calcium carbide causing to fall and break has good oneself and gathers effect, has effectively avoided calcium carbide to the problem of external diffusion and has faced mutually on the same group the few problem of calcium carbide accumulating amount between described ceramic body 1.Described reinforcement 2 bottoms extend downward on described baffle plate 3, because described baffle plate 3 is to be extended to form downwards by a side pipe wall, its structural strength is not as the intensity of whole described ceramic body 1, so described reinforcement 2 plays effective supporting role to described baffle plate 3, improves the structural strength of described baffle plate 3.
Be positioned on the tube wall of the described ceramic body 1 lower end mouth of pipe of described baffle plate 3 both sides and be respectively equipped with side discharge gate 7.The effect of described side discharge gate 7 is: when the calcium carbide at mouth of pipe place, lower end is piled up full time, calcium carbide can be discharged from the described side discharge gate 7 of both sides, calcium carbide is piled up towards facing mutually another ceramic body one side, between two described ceramic bodys that make to face mutually, also pile up and have enough calcium carbides, calcium carbide in furnace of calcium carbide is laid evenly, be conducive to heating.
Described ceramic body 1 inside is provided with framework of steel reinforcement, and described reinforcement 2 is inner is respectively arranged with described baffle plate 3 inside the reinforcing bar being connected with described framework of steel reinforcement.Because pottery is crisp and frangible, so described framework of steel reinforcement has effectively improved the structural strength of described ceramic body 1, described framework of steel reinforcement make described ceramic body 1 more durable, and described framework of steel reinforcement is positioned at described ceramic body 1 inside, so also can not produce electric leakage problem.
The described ceramic body 1 upper end mouth of pipe is established along 4, and described is ceramic edge along 4.In the prior art, the junction between tremie pipe and body of heater is provided with insulating barrier, adopts after described ceramic body 1, described along 4 and described ceramic body 1 with the effect that does not need between body of heater that insulating barrier is set again and just can play insulation.Described framework of steel reinforcement passes described along 4 and form reinforcing bar handle, ceramic structure intensity is not as metal, so in allocation and transportation, installation process, if power is directly acted on to described ceramic body 1, easily make body breakage, so design described reinforcing bar handle, effectively avoided external force to cause damage to described ceramic body 1, and conveniently aging or damaged tremie pipe pull-out furnace of calcium carbide body of heater has been changed.
As shown in Figure 2, a kind of furnace of calcium carbide that adopts the described furnace of calcium carbide tremie pipe with reinforcement, comprises body of heater 5, is vertically arranged on the electrode 6 in described body of heater 5, and the surrounding of each described electrode 6 is surrounded with at least three described furnace of calcium carbide tremie pipes.Described body adopts ceramic body to replace metal tube, and problem and the charged problem of tremie pipe of effectively having avoided tremie pipe to be burnt, not only greatly improved the service life of tremie pipe, and improved the insulating properties of tremie pipe, prevented the loss of electric energy.Because ceramic structural strength is not as metal, so the effect of described reinforcement 2 is the structural strengths that effectively improve described ceramic body 1.
The described ceramic body 1 lower end mouth of pipe extends to form baffle plate 3 downwards away from the tube wall of described electrode 6 one sides, the benefit of design is like this: due to the barrier effect of described baffle plate 3, when calcium carbide falls in described body of heater 5 and while starting to pile up along described ceramic body 1, calcium carbide can only or face mutually on the same group described ceramic body 1 one sides and pile up towards described electrode 6 one sides, the calcium carbide causing to fall and break has good oneself and gathers effect, has effectively avoided calcium carbide to the problem of external diffusion and has faced mutually on the same group the few problem of calcium carbide accumulating amount between described ceramic body 1.Described reinforcement 2 bottoms extend downward on described baffle plate 3, because described baffle plate 3 is to be extended to form downwards by a side pipe wall, its structural strength is not as the intensity of whole described ceramic body 1, so described reinforcement 2 plays effective supporting role to described baffle plate 3, improves the structural strength of described baffle plate 3.
Be positioned on the tube wall of the described ceramic body 1 lower end mouth of pipe of described baffle plate 3 both sides and be respectively equipped with side discharge gate 7.The effect of described side discharge gate 7 is: when the calcium carbide at mouth of pipe place, lower end is piled up full time, calcium carbide can be discharged from the described side discharge gate 7 of both sides, calcium carbide is piled up towards facing mutually another ceramic body one side, between two described ceramic bodys that make to face mutually, also pile up and have enough calcium carbides, calcium carbide in furnace of calcium carbide is laid evenly, be conducive to heating.
Described ceramic body 1 inside is provided with framework of steel reinforcement, and described reinforcement 2 is inner is respectively arranged with described baffle plate 3 inside the reinforcing bar being connected with described framework of steel reinforcement.Because pottery is crisp and frangible, so described framework of steel reinforcement has effectively improved the structural strength of described ceramic body 1, described framework of steel reinforcement make described ceramic body 1 more durable, and described framework of steel reinforcement is positioned at described ceramic body 1 inside, so also can not produce electric leakage problem.
The described ceramic body 1 upper end mouth of pipe is established along 4, and described is ceramic edge along 4.In the prior art, the junction between tremie pipe and described body of heater 5 is provided with insulating barrier, adopts after described ceramic body 1, described along 4 and described ceramic body 1 with the effect that does not need between described body of heater 5 that insulating barrier is set again and just can play insulation.Described framework of steel reinforcement passes described along 4 and form reinforcing bar handle, ceramic structure intensity is not as metal, so in allocation and transportation, installation process, if power is directly acted on to described ceramic body 1, easily make body breakage, so design described reinforcing bar handle, effectively avoided external force to cause damage to described ceramic body 1, and convenient aging or damaged tremie pipe is pulled out to described body of heater 5 changed.
Finally should be noted that: above embodiment is only in order to illustrate that the technical solution of the utility model is not intended to limit; Although the utility model is had been described in detail with reference to preferred embodiment, those of ordinary skill in the field are to be understood that: still can modify or part technical characterictic is equal to replacement the specific embodiment of the present utility model; And not departing from the spirit of technical solutions of the utility model, it all should be encompassed in the middle of the technical scheme scope of the utility model request protection.

Claims (10)

1. the furnace of calcium carbide tremie pipe with reinforcement, comprises body, it is characterized in that: described body is ceramic body, on described ceramic inboard wall of tube body, is vertically provided with reinforcement.
2. the furnace of calcium carbide tremie pipe with reinforcement according to claim 1, is characterized in that: a side pipe wall of the described ceramic body lower end mouth of pipe extends to form baffle plate downwards.
3. the furnace of calcium carbide tremie pipe with reinforcement according to claim 2, is characterized in that: be positioned on the tube wall of the described ceramic body lower end mouth of pipe of described baffle plate both sides and be respectively equipped with side discharge gate.
4. according to the furnace of calcium carbide tremie pipe with reinforcement described in claim 2 or 3, it is characterized in that: described ceramic body inside is provided with framework of steel reinforcement, described reinforcement is inner is respectively arranged with described baffle interior the reinforcing bar being connected with described framework of steel reinforcement.
5. the furnace of calcium carbide tremie pipe with reinforcement according to claim 4, is characterized in that: described ceramic body upper pipes mouth is established edge, and described framework of steel reinforcement passes described edge and forms reinforcing bar handle.
6. a furnace of calcium carbide that adopts the furnace of calcium carbide tremie pipe with reinforcement described in claim 1, comprises body of heater, is vertically arranged on the electrode in described body of heater, it is characterized in that: the surrounding of each described electrode is surrounded with at least three described furnace of calcium carbide tremie pipes.
7. furnace of calcium carbide according to claim 6, is characterized in that: the described ceramic body lower end mouth of pipe extends to form baffle plate downwards away from the tube wall of described electrode one side.
8. furnace of calcium carbide according to claim 7, is characterized in that: be positioned on the tube wall of the described ceramic body lower end mouth of pipe of described baffle plate both sides and be respectively equipped with side discharge gate.
9. according to the furnace of calcium carbide described in claim 7 or 8, it is characterized in that: described ceramic body inside is provided with framework of steel reinforcement, described reinforcement is inner is respectively arranged with described baffle interior the reinforcing bar being connected with described framework of steel reinforcement.
10. furnace of calcium carbide according to claim 9, is characterized in that: described ceramic body upper pipes mouth is established edge, and described framework of steel reinforcement passes described edge and forms reinforcing bar handle.
CN201320607205.7U 2013-09-30 2013-09-30 Calcium carbide furnace blanking pipe with reinforcing rib and calcium carbide furnace with calcium carbide furnace blanking pipe Withdrawn - After Issue CN203586830U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201320607205.7U CN203586830U (en) 2013-09-30 2013-09-30 Calcium carbide furnace blanking pipe with reinforcing rib and calcium carbide furnace with calcium carbide furnace blanking pipe

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201320607205.7U CN203586830U (en) 2013-09-30 2013-09-30 Calcium carbide furnace blanking pipe with reinforcing rib and calcium carbide furnace with calcium carbide furnace blanking pipe

Publications (1)

Publication Number Publication Date
CN203586830U true CN203586830U (en) 2014-05-07

Family

ID=50584738

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201320607205.7U Withdrawn - After Issue CN203586830U (en) 2013-09-30 2013-09-30 Calcium carbide furnace blanking pipe with reinforcing rib and calcium carbide furnace with calcium carbide furnace blanking pipe

Country Status (1)

Country Link
CN (1) CN203586830U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103512365A (en) * 2013-09-30 2014-01-15 郑州耐都耐材科技有限公司 Calcium carbide furnace discharging tubes with strengthening ribs and calcium carbide furnace with calcium carbide furnace discharging tubes

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103512365A (en) * 2013-09-30 2014-01-15 郑州耐都耐材科技有限公司 Calcium carbide furnace discharging tubes with strengthening ribs and calcium carbide furnace with calcium carbide furnace discharging tubes
CN103512365B (en) * 2013-09-30 2015-11-18 郑州耐都耐材科技有限公司 Furnace of calcium carbide tremie pipe with reinforcement and the furnace of calcium carbide with this furnace of calcium carbide tremie pipe

Similar Documents

Publication Publication Date Title
CN205258011U (en) Horizontal acheson graphitizing furnace
KR20120094875A (en) Preheating method and preheating apparatus of steel making ladle
CN203586830U (en) Calcium carbide furnace blanking pipe with reinforcing rib and calcium carbide furnace with calcium carbide furnace blanking pipe
CN101419020B (en) Manganese-rich slag electric furnace mounted with condensation lining
CN103512364B (en) Furnace of calcium carbide tremie pipe and the furnace of calcium carbide with this furnace of calcium carbide tremie pipe
CN203586829U (en) Calcium carbide furnace blanking pipe with partition and calcium carbide furnace with calcium carbide furnace blanking pipe
CN203586828U (en) Calcium carbide furnace blanking pipe and calcium carbide furnace with same
CN103512365B (en) Furnace of calcium carbide tremie pipe with reinforcement and the furnace of calcium carbide with this furnace of calcium carbide tremie pipe
CN103512366B (en) Furnace of calcium carbide tremie pipe with dividing plate and the furnace of calcium carbide with this furnace of calcium carbide tremie pipe
CN206369469U (en) Closed titanium slag electric furnace water cooled cover
CN214666084U (en) A scrap steel hopper for scrap steel preheats
CN205784562U (en) A kind of vacuum microwave smelting furnace
CN202339106U (en) High-loading softening heat-insulation brick for heating furnace
CN105758187A (en) Calcium carbide furnace blanking pipe provided with partition board and calcium carbide furnace provided with calcium carbide furnace blanking pipes
CN211373236U (en) But continuous production's high temperature graphitization stove
CN105758188A (en) Calcium carbide furnace blanking pipe and calcium carbide furnace provided with same
CN205590747U (en) Electric heating furnace
CN202328796U (en) Boiler plate of cast-iron boiler
CN202509120U (en) Residual copper comprehensive clearing separating furnace
CN207006868U (en) New furnace of calcium carbide blanking column
CN205043117U (en) Hot chamber machine sandwich heating crucible
CN205816794U (en) Baking of tundish device
CN100520264C (en) Furnace brickwork using metal anchor device as framework and its construction technology
CN206768167U (en) A kind of masonry construction of RH refining furnaces lower channel
CN201368676Y (en) Furnace cover of non-pressure water-cooled electric arc furnace

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
AV01 Patent right actively abandoned

Granted publication date: 20140507

Effective date of abandoning: 20151118

C25 Abandonment of patent right or utility model to avoid double patenting