CN203559792U - Drill tower structure of drilling rig - Google Patents

Drill tower structure of drilling rig Download PDF

Info

Publication number
CN203559792U
CN203559792U CN201320610553.XU CN201320610553U CN203559792U CN 203559792 U CN203559792 U CN 203559792U CN 201320610553 U CN201320610553 U CN 201320610553U CN 203559792 U CN203559792 U CN 203559792U
Authority
CN
China
Prior art keywords
mainmast
rig
sub
strut bar
main mast
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201320610553.XU
Other languages
Chinese (zh)
Inventor
邱华
彭儒金
戴圣海
刘志
赵彦军
肖燕波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Changsha Exploration Machinery Factory
Original Assignee
Changsha Exploration Machinery Factory
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Changsha Exploration Machinery Factory filed Critical Changsha Exploration Machinery Factory
Priority to CN201320610553.XU priority Critical patent/CN203559792U/en
Application granted granted Critical
Publication of CN203559792U publication Critical patent/CN203559792U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

A drill tower structure of a drilling rig comprises a main mast (4) arranged perpendicular to a drilling rig underframe (7), as well as a left auxiliary brace and a right auxiliary brace both obliquely propped against the main mast through an upper splint (2), wherein the main mast is designed to be a stair structure, and is divided into an upper main mast (9) and a lower main mast (11); the top of the upper main mast is connected with a crown block (1) through a connection plate (8); the lower main mast (11) is designed to be gantry-shaped according to the shape and dimension of the drilling rig, and is inserted into the center of an ear plate hole in the underframe (7); the lower main mast is tightly propped against a limiting beam on a frame (20) of the drilling rig, and is fixed through a pressing plate and pressing bolts of the frame; the upper joints of the left auxiliary brace and the right auxiliary brace are fixedly connected with an upper splinter of the main mast. The drill tower structure can reduce the preliminary time before drilling to the maximum degree, so as to increase mounting efficiency and reduce potential safety hazard.

Description

Rig rig structure
Technical field
The utility model relates to engineering driller, particularly rig rig structure.
Background technology
Boring tower is the visual plant of probing work, and it is mainly used to lay overhead traveling crane, hangs hook equipment etc., so as to reach rapidly, lifting hanging drilling tool, sleeve pipe and put drilling tool easily.
The boring tower of rig is mainly dimetric vertical structure at present, as shown in Figure 1 and Figure 2.Mast 2 ' after two front masts 1 ' that this boring tower mainly comprises that mutual support relies on and two, and front mast 1 ' and rear mast 2 ' not perpendicular to the ground, the bottom of front mast 1 ' and rear mast 2 ' is connected and fixed by rig body transom 10 '.This front mast 1 ' and rear mast 2 ' are divided into upper and lower two-section, and wherein portion is bolted with box cupling 6 ' respectively.The bottom installing wheel 9 ' of rear mast 2 ', the middle part of this rear mast 2 is provided with middle girder 4 ', on this middle girder 4 ', lays trailer traction hook 3 ', when rig fell, can pass through trailer traction trailer traction hook 3 ', make wheel 9 ' in ground running simultaneously, realize rig travel condition.The crown center installing overhead traveling crane 11 ' of this front mast 1 ' and rear mast 2 ', two the first leading blocks are set on overhead traveling crane 11 ', rear mast 2 ' is installing the second leading block 7 ' above, not only provide the guiding of wire rope, and arranging of the second leading block 7 ' can prevent wire rope play.For increasing boring tower rigidity, forward and backward mast 1 ', 2 ' middle part connect side connecting rod 8 '.Movable foot pedal 5 ' is also installed, so that the upper and lower boring tower of operator on front mast 1 '.
Steel pipe four turrets of take are example, because forward and backward mast 1 ', 2 ' is installed in the central axis both sides of overhead traveling crane 11 ', as shown in Figure 3, according to installation guide, require four masts to be toppled over to put before perpendicular tower being "X" shape, and this will take more work area.Secondly, before and after this rig structure, mast is divided into upper and lower two-section, can not lean on the tractive force of hoist directly to put in place while not only playing tower, must be aided with artificial help, and because four masts all have certain angle with vertical direction, creep into and trip-out process stability and safety poor.In addition, forward and backward mast 1 ', 2 ' is not all perpendicular to rig underframe, and operator exists certain potential safety hazard by the upper and lower boring tower of movable foot pedal 5 '.
Summary of the invention
In order to overcome the perpendicular existing deficiency of tower of existing steel pipe four turrets, the utility model provides a kind of novel rig rig structure, and it can at utmost reduce the time before probing, improves installation exercise efficiency, alleviates potential safety hazard.
For solving the problems of the technologies described above, the technical scheme that the utility model adopts is: a kind of rig rig structure, and it comprises the mainmast arranging perpendicular to rig underframe and passes through the left and right sub-strut bar of train wheel bridge diagonal brace on mainmast; This mainmast is designed to stair type, and is divided into mainmast and lower mainmast, and the top of upper mainmast is connected with overhead traveling crane by joint cover, and lower mainmast is designed to flame according to rig appearance and size; This lower mainmast inserts the lug plate holes center of underframe, and this lower mainmast is near the spacing beam on rig mid frame, and utilizes pressing plate and hold-down bolt on mid frame to fix; The top connection of left and right sub-strut bar is firmly connected with the train wheel bridge on upper mainmast.
This lower mainmast by independently upper and lower form, by junction plate, upper and lower of lower mainmast is welded, and respectively welds two gussets in the above and below of junction plate, undercarriage position welding transverse tube.
This left and right sub-strut bar is comprised of upper and lower sub-strut bar respectively, and upper and lower sub-strut bar is with bolts by box cupling.
Between twice sub-strut bars, utilize U-shaped screw to be connected with middle girder, draw hook is installed on middle girder, the bottom assembling wheels of twice sub-strut bars and the anchor ear lower sub-strut bar being connected with rig underframe when advancing.
On this middle girder, be provided with a pair of for the fixing leading block of wire rope when the perpendicular tower.
The rig underframe both sides welding support bar of described rig rig structure.
With existing steel pipe four pin boring tower comparisons, the beneficial effect that the utility model has is: one, more existing steel pipe quadrangular boring tower erects tower schematic diagram (Fig. 3), during the perpendicular tower of the utility model boring tower, first erect mainmast, vertical sub-strut bar, as shown in Figure 6, can make the floor space of the front preparation of perpendicular tower reduce by half again.Its two, mainmast is designed to stair type, on mainmast, is welded with many stulls, replaces original movable leg pedal, the upper and lower boring tower of auxiliary operation workman, significantly improves processing safety.Its three, during the utility model boring tower design mainmast, take into full account rack construction, lower mainmast is designed to gantry shape, guaranteeing under constitutionally stable prerequisite, adopting junction plate and gusset to make the stair type structure of the supreme mainmast of its structural transition, making boring tower overall structure compacter.Its four, the utility model boring tower bracing frame divides primary and secondary, is divided into mainmast and sub-strut bar.Mainmast is vertical with underframe, and overhead traveling crane and mainmast are " T " font.Mainmast abuts against the spacing Liang Chu of mid frame, with hold-down bolt, is fixed on rig vertical plane, makes the stressed better of whole boring tower, has also increased the stability of whole boring tower.
Accompanying drawing explanation
Fig. 1 is existing four pin boring tower assembly structure figures.
Fig. 2 is the right view of Fig. 1.
Fig. 3 is the perpendicular tower schematic diagrames of existing four pin rig structures.
Fig. 4 is the utility model rig structure schematic diagram.
Fig. 5 is the right view of Fig. 4.
Fig. 6 is the perpendicular tower schematic diagram of the utility model boring tower.
The specific embodiment
As shown in Fig. 4-Fig. 5, the utility model rig rig structure comprises that, perpendicular to the mainmast 4 of rig underframe 7 settings with by the left and right sub-strut bar 3 of train wheel bridge 2 diagonal braces on mainmast 4, this sub-strut bar 3 is less than 90 degree with the angle of underframe 7.
This mainmast 4 is designed to stair type, and is divided into mainmast 9 and lower mainmast 11, between upper and lower mainmast 9,11, by duplex box cupling 25, connects.Upper mainmast 9 is welded through stull water pipe by two rock core steel pipes, and the top of upper mainmast 9 is connected with overhead traveling crane 1 by joint cover 8.Overhead traveling crane 1 is equipped with two pulleys, for wire rope provides winding, and play the guiding role for wire rope.Lower mainmast 11 is designed to flame according to rig appearance and size, consider its processing technology, and lower mainmast 11 is designed to group welding piece.This lower mainmast 11 by independently upper and lower form, by junction plate 13, upper and lower of lower mainmast 11 is welded.Meanwhile, in the above and below of junction plate 13, respectively weld two gussets 14, undercarriage position welding transverse tube 18, to strengthen the stability of mainmast 4 upper and lower supports.The otic placode 21Kong center that this lower mainmast 11 inserts underframe 7, and this lower mainmast 11 is near the spacing beam on rig mid frame 20, and utilize pressing plate and hold-down bolt on mid frame 20 to be fixed.
Left and right sub-strut bar 3 is comprised of upper and lower sub-strut bar 10,19 respectively, and upper and lower sub-strut bar 10,19 is with bolts by box cupling 17.The top connection of left and right upper sub-strut bar 10 is firmly connected with the train wheel bridge 2 on upper mainmast 9.Between left and right lower sub-strut bar, utilize U-shaped screw to be connected with middle girder 12, draw hook 16 and a pair of leading block 5 are installed on middle girder 12, this can prevent wire rope play to leading block 5 when erecting tower.The bottom assembling wheels 15 of left and right lower sub-strut bar 19 and the anchor ear 6 being connected with rig underframe 7 when advancing, wheel 15 can be converted to travel condition by rig in conjunction with the draw hook 16 on middle girder 12 after putting tower.
Below perpendicular tower-like condition of the present utility model is specifically described:
Rig, before entering work-yard, need to be arranged work-yard.According to place situation, at rig putting position, complete sleeper.After place to be onstructed arranges, rig is dragged to construction plant, according to position, aperture, is well placed rig.That with instruments such as cushion block, belts, unclamps lower sub-strut bar 19 and underframe 7 is connected anchor ear 6, and rig and underframe 7 levels are put on sleeper.
As shown in Figure 6, vertical rod 22 is inserted to rising of rig mid frame 20 rear sides and pull out in a hole, check whether the pulley rising in bridge 23 of vertical rod 22 upper ends installs firm and flexible rotating.Upper and lower mainmast 9,11 is connected by duplex box cupling 25, and upper mainmast 9 tops are fixing overhead traveling crane 1 by joint cover 8 and bolt.After having been walked around to pulley in bridge 23, two pulleys on overhead traveling crane 1, wire rope is fixed on mainmast 4.During perpendicular tower, a bridge 23 can be lineoutofservice signal pull provides guiding.The mainmast connecting 4 is assigned on the hole bearing pin of rig underframe place otic placode 21 again.Lay down pressing plate and hold-down bolt on mid frame 20, so that perpendicular tower simultaneously.
One end of wire rope is snapped in the card rope hole in hoist drum, start diesel engine, speed change handgrip is adjusted at a slow speed, transfer handgrip is adjusted to elevator position, clutch closes, regulate band-type brake handle, make hoist drum with suitable speed rotation, guarantee that wire rope is wrapped in hoist drum in an orderly manner.Then the wire rope other end has been walked around to the pulley in bridge, two pulleys on overhead traveling crane successively, be pulled to transverse tube 18 places of mainmast 4, with rigging shackle, wire rope has been fixed.
During perpendicular tower, again start hoist, wire rope is wound on reel gradually, mainmast 4 slowly rises under the pulling force of wire rope.Meanwhile, near overhead traveling crane 1, arrange operator to assist certain altitude is lifted in the upper end of mainmast 4, make perpendicular tower more smooth and easy.When mainmast 4 is close to after the spacing beam at mid frame 20 places, with pressing plate and hold-down bolt, be fixed.Two upper sub-strut bars 10 insert respectively sub-strut bar 19 twice, and utilize screw rod fastening by box cupling 17, then manually slowly lift, and are pushed into and cross the position vertical with underframe 7, lean on mainmast 4.Operator, by the transverse tube 18 on mainmast 4, climbs to pylon top, and the train wheel bridge 2 use bolts of upper sub-strut bar 10 and upper mainmast 9 are connected.Finally, according to the situation after boring tower assembling, at underframe both sides welding support bar, and set up a diagonal brace to vertical rod, the stability while being more conducive to guarantee boring tower work.
When probing end-of-job, putting tower, to be converted to rig travel condition step as follows: first dismantle the miscellaneous part except lower sub-strut bar (comprising middle girder part) 19, vertical rod 22 and a bridge 23 in boring tower.Then, lower sub-strut bar 19 is pressed, use belt together with underframe 7 bolts, is raised lower sub-strut bar 19 lower sub-strut bar 19, at underframe, places the suitably cushion block of height for 7 times.Depress down again sub-strut bar 19, take out belt, lower sub-strut bar 19 and the little axle of underframe 7 is tight by anchor ear 6 bolts, both are connected.Can pass through trailer traction draw hook 16, by wheel 15, at ground running, and rig is converted to travel condition.

Claims (5)

1. a rig rig structure, is characterized in that comprising the mainmast (4) arranging perpendicular to rig underframe (7) and passes through the left and right sub-strut bar (3) of train wheel bridge (2) diagonal brace on mainmast; This mainmast is designed to stair type, and is divided into mainmast (9) and lower mainmast (11), and the top of upper mainmast is connected with overhead traveling crane (1) by joint cover (8), and lower mainmast (11) is designed to flame according to rig appearance and size; This lower mainmast inserts the lug plate holes center of underframe (7), and this lower mainmast is near the spacing beam on rig mid frame (20), and utilizes pressing plate and hold-down bolt on mid frame to fix; The top connection of left and right sub-strut bar is firmly connected with the train wheel bridge on upper mainmast.
2. rig rig structure according to claim 1, it is characterized in that, this lower mainmast by independently upper and lower form, by junction plate (13), upper and lower of lower mainmast is welded, and in the above and below of junction plate, respectively weld two gussets, undercarriage position welding transverse tube.
3. rig rig structure according to claim 1, is characterized in that, this left and right sub-strut bar is comprised of upper and lower sub-strut bar (10,19) respectively, and upper and lower sub-strut bar is with bolts by box cupling.
4. rig rig structure according to claim 3, it is characterized in that, between twice sub-strut bars (19), utilize U-shaped screw to be connected with middle girder (12), draw hook is installed, the bottom assembling wheels of twice sub-strut bars and the anchor ear lower sub-strut bar being connected with rig underframe when advancing on middle girder.
5. rig rig structure according to claim 4, is characterized in that, is provided with a pair of for the fixing leading block of wire rope when the perpendicular tower on this middle girder.
CN201320610553.XU 2013-09-30 2013-09-30 Drill tower structure of drilling rig Expired - Fee Related CN203559792U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201320610553.XU CN203559792U (en) 2013-09-30 2013-09-30 Drill tower structure of drilling rig

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201320610553.XU CN203559792U (en) 2013-09-30 2013-09-30 Drill tower structure of drilling rig

Publications (1)

Publication Number Publication Date
CN203559792U true CN203559792U (en) 2014-04-23

Family

ID=50509520

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201320610553.XU Expired - Fee Related CN203559792U (en) 2013-09-30 2013-09-30 Drill tower structure of drilling rig

Country Status (1)

Country Link
CN (1) CN203559792U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111927329A (en) * 2020-08-17 2020-11-13 西南石油大学 Mountain geophysical prospecting electric drilling machine front vehicle structure
CN112012654A (en) * 2020-08-26 2020-12-01 西南石油大学 Mountain geophysical prospecting electric drilling machine device

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111927329A (en) * 2020-08-17 2020-11-13 西南石油大学 Mountain geophysical prospecting electric drilling machine front vehicle structure
CN112012654A (en) * 2020-08-26 2020-12-01 西南石油大学 Mountain geophysical prospecting electric drilling machine device

Similar Documents

Publication Publication Date Title
CN106638185B (en) A kind of traveling process becomes automatically across track-laying machine and application method
CN208995928U (en) A kind of multi-functional erection crane suitable for composite beam construction
CN203559792U (en) Drill tower structure of drilling rig
CN102837705B (en) Traveling bogie in steel box
CN208202586U (en) Conduit lifting device for the perfusion of power transmission tower concrete filled steel tube high-altitude
CN202879487U (en) Transfer carriage in steel box
CN206438353U (en) A kind of traveling process becomes across track-laying machine automatically
CN204152426U (en) A kind of quick removal of home rig of hydraulic cylinder raising
CN212559194U (en) Lifting frame for finite space drilling pile
CN206429270U (en) A kind of shield machine station-crossing device
CN210558971U (en) Transport vehicle for dismantling shield construction track
CN218642333U (en) Piece dress formula loose joint tower machine standard festival
CN107420050A (en) The full-automatic workover rig of mast lift
CN203859438U (en) Multipurpose pedaling type overhead carriage
CN203334186U (en) A wheel type device for cable-stayed bridge floor press anchoring
CN103407903B (en) A kind of large-scale derrick crane peace tears the traction method of the automatic trailer system of standard knot open
CN108775153A (en) Conduit lifting device and method for the perfusion of power transmission tower concrete filled steel tube high-altitude
CN104727193B (en) Segmented railway track laying set and transportation method thereof
CN209483370U (en) It is a kind of for installing the sideslip tower wagon of subway circular tunnel upper arcuate bracket
CN107059654A (en) The compound overlength Hanging basket on front support of single cable plane and its installation method
CN204919525U (en) Strong machine that rams and combination formula top arm frame structure thereof
CN202338106U (en) Wall-body hoisting ring of cantilever discharging platform
CN201794600U (en) Quick supporting device for tunnel excavation
CN206338037U (en) A kind of well workover self-balancing derrick
CN206188260U (en) Hoist top ping lift prevents kinking device and hoist

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20140423

Termination date: 20160930

CF01 Termination of patent right due to non-payment of annual fee