CN203557682U - Improved sizing box for production of pipe - Google Patents

Improved sizing box for production of pipe Download PDF

Info

Publication number
CN203557682U
CN203557682U CN201320674252.3U CN201320674252U CN203557682U CN 203557682 U CN203557682 U CN 203557682U CN 201320674252 U CN201320674252 U CN 201320674252U CN 203557682 U CN203557682 U CN 203557682U
Authority
CN
China
Prior art keywords
water inlet
water
inlet pipe
pipe
calibration sleeve
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN201320674252.3U
Other languages
Chinese (zh)
Inventor
万宝清
张久如
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tangshan Changhong Plastic Products Co Ltd
Original Assignee
Tangshan Changhong Plastic Products Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tangshan Changhong Plastic Products Co Ltd filed Critical Tangshan Changhong Plastic Products Co Ltd
Priority to CN201320674252.3U priority Critical patent/CN203557682U/en
Application granted granted Critical
Publication of CN203557682U publication Critical patent/CN203557682U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Extrusion Moulding Of Plastics Or The Like (AREA)

Abstract

The utility model discloses an improved sizing box for production of a pipe. The improved sizing box structurally comprises a box body and a main water inlet pipe, wherein a sizing sleeve is arranged in the box body; first water inlet pipes are arranged on the both sides of the sizing sleeve; water outlets of the first water inlet pipes are higher than the upper edge of the sizing sleeve; silica gel rings are arranged at connectors of the first water inlet pipes and the box body; a box body bracket is arranged on the outer side of the box body; a water distributor is arranged on the box body bracket; an exhausting pipe is arranged at the top of the water distributor; a plurality of water outlets are arranged below the exhausting pipe; the second water inlet pipe is connected with the water outlets; the other end of the second water inlet pipe is uniformly connected with the end part of the sizing sleeve; a water collection plate is arranged in the front of the box body; an outlet of the exhausting pipe is formed in the water collection plate; the main water inlet pipe is connected to the first water inlet pipes and the water distributor respectively; a connector of the main water inlet pipe and the water distributor is located at the top of the water distributor. The improved sizing box provided by the utility model can be used for improving the defects in prior art and improving the cooling and sizing yield of the tubular product.

Description

A kind of improved tubing production sizing tank
Technical field
The utility model relates to a kind of TPO tubing production equipment, especially a kind of improved tubing production sizing tank.
Background technology
In TPO tubing production process, the tubing by extruder moulding will be used sizing tank cooling and shaping.There is unreasonable structure in existing sizing tank, easily occurs the problem of defect in tubing cooling procedure.
Utility model content
The technical problems to be solved in the utility model is to provide a kind of improved tubing production sizing tank, can solve the deficiencies in the prior art, has improved the yield of tubing cooling and shaping.
For solving the problems of the technologies described above, technical solution adopted in the utility model is as follows.
A kind of improved tubing production sizing tank, structure comprises casing, is provided with calibration sleeve in casing, and the both sides of calibration sleeve are respectively arranged with first water inlet pipe, the delivery port of the first water inlet pipe is higher than the upper edge of calibration sleeve, and the interface of the first water inlet pipe and casing is provided with silica gel ring; Casing arranged outside has antinose-dive leg, on antinose-dive leg, be provided with water knockout drum, water knockout drum top is provided with blast pipe, blast pipe below is provided with several delivery ports, on delivery port, be connected with the second water inlet pipe, the other end of the second water inlet pipe is evenly connected to the end of calibration sleeve, casing the place ahead is provided with drip tray, the outlet of blast pipe is arranged in drip tray, in structure, also comprise a water inlet manifold, water inlet manifold is connected to respectively the first water inlet pipe and water knockout drum, the top of the interface of water inlet manifold and water knockout drum in water knockout drum.
As preferably, the structure of described calibration sleeve comprises three support bars, is vertically installed with several video discs on support bar, and the inner side of video disc is provided with loop bracket.
As preferably, on described water inlet manifold, be provided with y-type filter.
The beneficial effect that adopts technique scheme to bring is: it is cooling that the utility model is used two cover water inlet pipes to carry out the tubing in casing, and cooling effectiveness is high.The blast pipe that water knockout drum top arranges can be discharged the bubble existing in cooling water, the below of the second water inlet pipe in blast pipe, make to enter not bubbles of cooling water in calibration sleeve from the second water inlet pipe, the delivery port of the first water inlet pipe is higher than the upper edge of calibration sleeve, can make bubble in cooling water directly float up to the water surface and without the tubing in calibration sleeve, avoid tubing to occur the defect of " water spot ".Drip tray can be collected a small amount of cooling water flowing out from blast pipe.Silica gel ring has improved the sealing of casing and the first water inlet pipe.The second water inlet pipe is evenly connected to the end of calibration sleeve, can improve the flow uniformity of cooling water in calibration sleeve, guarantees the uniformity of cooling effect.Calibration sleeve, for disc-type designs, has improved exchange rate.Loop bracket has improved the uniformity of tubing suffered support force in calibration sleeve, has improved product quality.Y-type filter can filter out the impurity particle in cooling water.
Accompanying drawing explanation
Fig. 1 is the schematic diagram of a specific embodiment of the utility model.
Fig. 2 is the schematic diagram of calibration sleeve in specific embodiment of the utility model.
In figure: 1, casing; 2, calibration sleeve; 3, the first water inlet pipe; 4, silica gel ring; 5, antinose-dive leg; 6, water knockout drum; 7, blast pipe; 8, delivery port; 9, the second water inlet pipe; 10, drip tray; 11, water inlet manifold; 12, support bar; 13, video disc; 14, loop bracket; 15, y-type filter.
The specific embodiment
With reference to Fig. 1-2, structure of the present utility model comprises casing 1, is provided with calibration sleeve 2 in casing 1, and the both sides of calibration sleeve 2 are respectively arranged with first water inlet pipe 3, the delivery port of the first water inlet pipe 3 is higher than the upper edge of calibration sleeve 2, and the first water inlet pipe 3 is provided with silica gel ring 4 with the interface of casing 1, casing 1 arranged outside has antinose-dive leg 5, on antinose-dive leg 5, be provided with water knockout drum 6, water knockout drum top is provided with blast pipe 7, blast pipe 7 belows are provided with several delivery ports 8, on delivery port 8, be connected with the second water inlet pipe 9, the other end of the second water inlet pipe 9 is evenly connected to the end of calibration sleeve 2, casing 1 the place ahead is provided with drip tray 10, the outlet of blast pipe 7 is arranged in drip tray 10, in structure, also comprise a water inlet manifold 11, water inlet manifold 11 is connected to respectively the first water inlet pipe 3 and water knockout drum 6, the top of the interface of water inlet manifold 11 and water knockout drum 6 in water knockout drum 6.
Structure that it should be noted that described calibration sleeve 2 comprises three support bars 12, is vertically installed with several video discs 13 on support bar 12, and the inner side of video disc 13 is provided with loop bracket 14.
In addition, on described water inlet manifold 11, be provided with y-type filter 15.
Operation principle of the present utility model is: it is cooling that the utility model is used two cover water inlet pipes to carry out the tubing in casing 1, and cooling effectiveness is high.The blast pipe 7 that water knockout drum 6 tops arrange can be discharged the bubble existing in cooling water, the second below of water inlet pipe 9 in blast pipe 7, make to enter not bubbles of cooling water in calibration sleeve 2 from the second water inlet pipe 9, the delivery port of the first water inlet pipe 3 is higher than the upper edge of calibration sleeve 2, can make bubble in cooling water directly float up to the water surface and without the tubing in calibration sleeve 2, avoid tubing to occur the defect of " water spot ".Drip tray 10 can be collected a small amount of cooling water flowing out from blast pipe 7.Silica gel ring 4 has improved the sealing of casing 1 and the first water inlet pipe 3.The second water inlet pipe 9 is evenly connected to the end of calibration sleeve 2, can improve the flow uniformity of cooling water in calibration sleeve 2, guarantees the uniformity of cooling effect.Calibration sleeve 2, for disc-type designs, has improved exchange rate.Loop bracket 14 has improved the uniformity of tubing at calibration sleeve 2 interior suffered support forces, has improved product quality.Y-type filter 15 can filter out the impurity particle in cooling water.
More than show and described basic principle of the present utility model and principal character and advantage of the present utility model.The technical staff of the industry should understand; the utility model is not restricted to the described embodiments; that in above-described embodiment and description, describes just illustrates principle of the present utility model; do not departing under the prerequisite of the utility model spirit and scope; the utility model also has various changes and modifications, and these changes and improvements all fall within the scope of claimed the utility model.The claimed scope of the utility model is defined by appending claims and equivalent thereof.

Claims (3)

1. an improved tubing production sizing tank, it is characterized in that: structure comprises casing (1), in casing (1), be provided with calibration sleeve (2), the both sides of calibration sleeve (2) are respectively arranged with first water inlet pipe (3), the delivery port of the first water inlet pipe (3) is higher than the upper edge of calibration sleeve (2), and the first water inlet pipe (3) is provided with silica gel ring (4) with the interface of casing (1), casing (1) arranged outside has antinose-dive leg (5), on antinose-dive leg (5), be provided with water knockout drum (6), water knockout drum top is provided with blast pipe (7), blast pipe (7) below is provided with several delivery ports (8), on delivery port (8), be connected with the second water inlet pipe (9), the other end of the second water inlet pipe (9) is evenly connected to the end of calibration sleeve (2), casing (1) the place ahead is provided with drip tray (10), the outlet of blast pipe (7) is arranged in drip tray (10), in structure, also comprise a water inlet manifold (11), water inlet manifold (11) is connected to respectively the first water inlet pipe (3) and water knockout drum (6), the top of the interface of water inlet manifold (11) and water knockout drum (6) in water knockout drum (6).
2. improved tubing production sizing tank according to claim 1, it is characterized in that: the structure of described calibration sleeve (2) comprises three support bars (12), on support bar (12), be vertically installed with several video discs (13), the inner side of video disc (13) is provided with loop bracket (14).
3. improved tubing production sizing tank according to claim 1, is characterized in that: on described water inlet manifold (11), be provided with y-type filter (15).
CN201320674252.3U 2013-10-18 2013-10-18 Improved sizing box for production of pipe Expired - Lifetime CN203557682U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201320674252.3U CN203557682U (en) 2013-10-18 2013-10-18 Improved sizing box for production of pipe

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201320674252.3U CN203557682U (en) 2013-10-18 2013-10-18 Improved sizing box for production of pipe

Publications (1)

Publication Number Publication Date
CN203557682U true CN203557682U (en) 2014-04-23

Family

ID=50507421

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201320674252.3U Expired - Lifetime CN203557682U (en) 2013-10-18 2013-10-18 Improved sizing box for production of pipe

Country Status (1)

Country Link
CN (1) CN203557682U (en)

Similar Documents

Publication Publication Date Title
CN202492486U (en) Nitrogen-leading deoxidization purifying device used for producing cation polyacrylamide colloid
CN203890052U (en) Hydrogen production device
CN203557682U (en) Improved sizing box for production of pipe
CN203076253U (en) Air cylinder gasket cleaning water circulation device
CN204975216U (en) Modified impeller the gating system model
CN204022555U (en) A kind of novel anaerobic reactor
CN214820684U (en) Water guide device for sizing sleeve of vacuum sizing box
CN206355949U (en) A kind of surge tank produced for herbaceous plant beverage
CN202878625U (en) Circulating cooling device
CN202156912U (en) Multi-channel liquid distributor
CN102383203B (en) Energy-saving type spinning die head for spinning box
CN204340137U (en) A kind of mould of plastics dedicated cooling system
CN202208097U (en) Mold cavity water cooling cycling structure
CN203371703U (en) Combined type cooling system
CN202247041U (en) Energy-saving type spinning die head for spinning box
CN204799117U (en) Horizontal milipore filter cleaning system
CN205741314U (en) Manifold melt canal structure
CN213856033U (en) Heated photosensitive material plate washing device
CN205310773U (en) Give pipe cooling water supply device
CN211012578U (en) Device for improving heat exchange effect of dimethyl sulfoxide condenser
CN203782019U (en) Molten tin bath temperature equalization device
CN202762138U (en) Sparger for simulated moving bed separation technology
CN203637041U (en) Cooling system capable of simultaneously cooling two molds
CN211637489U (en) Steel wire washing unit
CN203401655U (en) Water circulation system of PET production line

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20140423