CN203530346U - Cooling-tower-free high temperature slag water-quenching condensing system - Google Patents

Cooling-tower-free high temperature slag water-quenching condensing system Download PDF

Info

Publication number
CN203530346U
CN203530346U CN201320681254.5U CN201320681254U CN203530346U CN 203530346 U CN203530346 U CN 203530346U CN 201320681254 U CN201320681254 U CN 201320681254U CN 203530346 U CN203530346 U CN 203530346U
Authority
CN
China
Prior art keywords
water
condensation
condensing
high temperature
tower
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn - After Issue
Application number
CN201320681254.5U
Other languages
Chinese (zh)
Inventor
王卫东
刘俭
方音
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Shagang Group Co Ltd
Original Assignee
Jiangsu Shagang Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Shagang Group Co Ltd filed Critical Jiangsu Shagang Group Co Ltd
Priority to CN201320681254.5U priority Critical patent/CN203530346U/en
Application granted granted Critical
Publication of CN203530346U publication Critical patent/CN203530346U/en
Anticipated expiration legal-status Critical
Withdrawn - After Issue legal-status Critical Current

Links

Images

Abstract

The utility model discloses a-cooling-tower-free high temperature slag water-quenching condensing system which mainly comprises a condensing unit comprising a condensing tower (5) and a condensing nozzle (6), a condensed water collecting tank (4), a water tank (10) and the like. The operation process comprises the following steps: conducting granulation on high temperature slag to produce a slag water mixture (1), enabling water vapor (3) to enter the condensing tower (5) when the slag water mixture passes through a granulation tank (2), spraying and condensing the water vapor by using the condensing nozzle (6), enabling the condensed water vapor to automatically flow to the independent water tank (10) through the condensed water collecting tank (4), then using a condensing water supply pump (8) to convey the condensed water in the water tank (10) to the condensing nozzle (6), and spraying and condensing the water vapor entering the condensing tower (5). Through the utilization of the design of the cooling-tower-free high temperature slag water-quenching condensing system, the water vapor is condensed and recovered and the condensed water is recycled without the help of forced air cooling, an excellent condensing effect is achieved, and the problem that the condensed water contains the slag is not caused.

Description

A kind of without cooling tower high temperature furnace slag shrend condenser system
Technical field
The utility model discloses a kind of blast-furnace slag water quenching technology, particularly a kind of without cooling tower high temperature furnace slag shrend condenser system, belong to technical field of metallurgy industry.
Background technology
At present, blast-furnace slag water quenching technology is mainly comprised of red-slag channel, granulation case, shot tank (pond), dewatering drum, recycling of condensed steam system (condensing tower), water pump, cooling tower, granulation condensation cycle water pipe etc.Blast furnace slag, from flowing to granulation case front end, is sprayed water coolant rapid cooling water by granulation case and quenches into grain slag, forms slag-water slurry.Slag-water slurry is separated with water by grain slag by separating device for water with dregs, and grain slag is transported to stockyard, and water recycles after cooling.Separating device for water with dregs adopts the outer industrial water purification of system to carry out back flushing conventionally.
And for producing a large amount of water vapors in blast-furnace slag shrend process; inputted in the condensing tower on shot tank top; centralized collection after cool water shower condensation; through condensate return pump, pump into cooling tower and carry out coolingly, then by condensation working shaft, cooled water is sent into condensing tower and recycle.Most of situation is after condensation water collection, to mix with granulation water, to enter same pond, by granulation pump, condensation working shaft, cooled water is sent into granulation case respectively again after cooling and condensing tower recycles.
For example, then there is many defects in aforementioned technique:
In one, water of condensation, contain equally some thin slags, unfavorable to system operation, serious wear, nozzle and pipeline easily stop up, and are difficult to recover;
Two, condensation water supply and condensate return two-stage power, and condensation service discharge is unadjustable, and system energy consumption is higher;
Three, water system cooling power is inadequate, and in cycle operation process, water temperature rising trend is obvious, and what have even reaches more than 90 ℃, and condensation effect is poor in this case.
Utility model content
Main purpose of the present utility model is for the deficiencies in the prior art, provide a kind of without cooling tower high temperature furnace slag shrend condensation process and system, it can realize the recycle of water of condensation, reaches good condensation effect, and prevents the problems such as water of condensation slag inclusion.
For realizing above-mentioned utility model object, the utility model has adopted following technical scheme:
Without a cooling tower high temperature furnace slag shrend condenser system, comprising:
The main condensing unit being formed by condensing tower and condensation nozzle, in order to the water vapor producing in condensation process high temperature furnace slag granulating,
Hot well, in order to collect the water of condensation being formed by described water vapor condensation, and,
The independent pond arranging, the virtual height in described pond, lower than hot well, makes the water of condensation in hot well can certainly flow into pond,
And described pond is also communicated with condensation nozzle through condensation working shaft.
As one of preferred embodiment, described pond needs certain capacity, limit one working cycle water system cycle index so that condensation supply water temperature is no more than 70 ℃.
Further, described hot well is located at described condensation nozzle below.
Further, described basin bottom is communicated with condensation working shaft by pipeline valve group.
Further, this without in cooling tower high temperature furnace slag shrend condenser system without forced draught cooling arrangement is set, water of condensation is cooling can be realized in system no-load run.
Further, in described condenser system, without forced draught cooling arrangement is set, water of condensation is cooling to be realized in cooling water system no-load run.
A kind of without cooling tower high temperature furnace slag shrend condensation process; comprise: make the water vapor producing in high temperature furnace slag granulating enter condensing tower; and with the condensation of condensation nozzle spray; and certainly flow into by hot well the pond that Independent is put; then with condensation working shaft, the water of condensation in pond is inputted to condensation nozzle, to entering the water vapor of condensing tower, spray condensation.
As one of comparatively preferred embodiment, by controlling the capacity in described pond, limit one working cycle water system cycle index so that water temperature is no more than 70 ℃.
Further, described condensation nozzle is installed on condensing tower top.
Further, in this technique, enter the water vapor of condensing tower after spray condensation, first drop onto in hot well, then from flowing into the pond that Independent is put.
Further, described pond is communicated with condensation working shaft by pipeline valve group.
Further, control that in described pond, more than 80% water is at condensate system internal recycle, the water below 20% enters granulation water system.
Wherein, the aquifer yield of condensation nozzle can change and regulate with quantity of steam or water temperature.
For principle of the present utility model, be further explained below:
1, independently pond is set, and make pond virtual height lower than hot well, can make condensate return gravity flow enter pond, and by condensation working shaft, water be sent into condensing tower nozzle again, make water of condensation form circular flow, and overcome the problems such as water of condensation slag inclusion;
2, pond described above need to reach certain capacity, controls a heat operation condensate water circulatory number of times, prevents water temperature accumulation rising too much.The cooling of water of condensation is to utilize ironmaking production intermittence feature, and while stopping slagging tap, condensate water circulatory system, in no-load run, makes water temperature drop to normal temperature.
Summarize it, compared with prior art, the utility model at least tool has the following advantages:
(1) in this high temperature furnace slag shrend condenser system ,condensate unit independently arranges, and is not with slag in water, and the wearing and tearing of associated component in this system are reduced greatly, and system job rate improves, and maintenance reduces;
(2) in this high temperature furnace slag shrend condenser system ,cancel condensate return pump, reduced power consumption, simplified system;
(3) in this high temperature furnace slag shrend condensation process ,cancelled forced draft cooling, rely on single-stage power to realize systemic circulation operation, and the nozzle water yield has been adjustable, reduces power consumption;
(4) in this high temperature furnace slag shrend condensation process ,the highest water temperature of system is no more than 70 ℃, and discharge of steam is controlled, is conducive to environmental protection.
(5) in this high temperature furnace slag shrend condensation process ,in system operational process, water of condensation will increase gradually.Owing to not being with slag in water of condensation, can extract water of condensation as separating device for water with dregs backwashing water, enter granulation water system, so both saved new water consumption, can play again the effect of the equilibrium system water yield.
Accompanying drawing explanation
Fig. 1 is a kind of without cooling tower high temperature furnace slag shrend condensation process schema, wherein: 1-slag-water slurry in the utility model one preferred embodiment; 2-shot tank; 3-water vapor; 4-receiving tank; 5-condensing tower; 6-condensation nozzle; 7-pipeline valve group; 8-condensation working shaft; 9-pipeline valve group; 10-pond.
Embodiment
Below in conjunction with accompanying drawing and a preferred embodiment, the technical solution of the utility model is further described.
Related a kind of without cooling tower high temperature furnace slag shrend condenser system in the utility model one preferred embodiment, comprising:
The main condensing unit being formed by condensing tower and condensation nozzle, in order to the water vapor producing in condensation process high temperature furnace slag granulating,
Hot well, in order to collect the water of condensation being formed by described water vapor condensation, and,
The independent pond arranging, the virtual height in described pond, lower than hot well, makes the water of condensation in hot well can certainly flow into pond, is not with slag in water,
And described pond is also communicated with condensation nozzle through condensation working shaft.
Consult Fig. 1; as one of application scheme more specifically, this can mainly consist of slag-water slurry 1, shot tank 2, receiving tank 4, condensing tower 5, condensation nozzle 6, condensation working shaft 8, pond 10 and some pipeline valve groups without cooling tower high temperature furnace slag shrend condenser system.
Further; this comprises without the corresponding workflow of cooling tower high temperature furnace slag shrend condenser system: when the red pulp water that blast furnace produces is quenched the slag-water slurry 1 process shot tank 2 producing; water vapor 3 enters condensing tower 5; and with the 6 spray condensations of condensation nozzle; and certainly flowing into the pond 10 that Independent is put by hot well 4,10 bottoms, pond are connected with condensation working shaft 8 by pipeline valve group 9, and water of condensation is delivered to condensation nozzle 6; water vapor is carried out to condensation, water system circular flow.
Wherein, pond 10 need to reach certain capacity, to limit a heat operation condensate water circulatory number of times, thereby prevents water temperature accumulation rising too much.After tap cinder finishes, the empty load cycle operation of condensate system, water temperature can drop to normal temperature.
It is to be noted; above-described embodiment is only explanation technical conceive of the present utility model and feature; its object is to allow person skilled in the art can understand content of the present utility model and implement according to this; can not limit protection domain of the present utility model with this; all equivalences of doing according to the utility model spirit change or revise, within all should being encompassed in protection domain of the present utility model.

Claims (5)

1. without a cooling tower high temperature furnace slag shrend condenser system, comprising:
The condensing unit mainly being formed by condensing tower (5) and condensation nozzle (6), in order to the water vapor (3) producing in condensation process high temperature furnace slag granulating,
Hot well (4), in order to collect the water of condensation being formed by described water vapor (3) condensation;
It is characterized in that, it also comprises:
The independent pond (10) arranging, the virtual height of described pond (10), lower than hot well (4), makes the water of condensation in hot well (4) can certainly flow into pond (10),
And described pond (10) are also communicated with condensation nozzle (6) through condensation working shaft (8).
2. according to claim 1ly without cooling tower high temperature furnace slag shrend condenser system, it is characterized in that, described pond needs certain capacity, limit one working cycle water system cycle index so that condensation supply water temperature is no more than 70 ℃.
3. according to claim 1ly without cooling tower high temperature furnace slag shrend condenser system, it is characterized in that, described condensation nozzle (6) is installed on condensing tower (5) top.
4. according to claim 1ly without cooling tower high temperature furnace slag shrend condenser system, it is characterized in that, described hot well (4) is located at described condensation nozzle (6) below.
5. according to claim 1ly without cooling tower high temperature furnace slag shrend condenser system, it is characterized in that, described pond (10) are communicated with condensation working shaft (8) by pipeline valve group (9).
CN201320681254.5U 2013-10-30 2013-10-30 Cooling-tower-free high temperature slag water-quenching condensing system Withdrawn - After Issue CN203530346U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201320681254.5U CN203530346U (en) 2013-10-30 2013-10-30 Cooling-tower-free high temperature slag water-quenching condensing system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201320681254.5U CN203530346U (en) 2013-10-30 2013-10-30 Cooling-tower-free high temperature slag water-quenching condensing system

Publications (1)

Publication Number Publication Date
CN203530346U true CN203530346U (en) 2014-04-09

Family

ID=50416579

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201320681254.5U Withdrawn - After Issue CN203530346U (en) 2013-10-30 2013-10-30 Cooling-tower-free high temperature slag water-quenching condensing system

Country Status (1)

Country Link
CN (1) CN203530346U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103555870A (en) * 2013-10-30 2014-02-05 江苏沙钢集团有限公司 High-temperature slag water-quenching condensation technology and high-temperature slag water-quenching condensation system free of cooling tower

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103555870A (en) * 2013-10-30 2014-02-05 江苏沙钢集团有限公司 High-temperature slag water-quenching condensation technology and high-temperature slag water-quenching condensation system free of cooling tower
CN103555870B (en) * 2013-10-30 2015-07-01 江苏沙钢集团有限公司 High-temperature slag water-quenching condensation technology and high-temperature slag water-quenching condensation system free of cooling tower

Similar Documents

Publication Publication Date Title
CN204434565U (en) With the vapourizing furnace of radiation waste pot
CN103555870B (en) High-temperature slag water-quenching condensation technology and high-temperature slag water-quenching condensation system free of cooling tower
CN109457070B (en) Steam whitening and heat energy recovery system for blast furnace water slag process
CN103557711A (en) Molten slag rapid cooling, granulation and waste heat recovery power generation system and method
CN206219613U (en) A kind of dry type blast-furnace cement sensible heat recovery system
CN203534229U (en) Power generating system for quick cooling granulating of molten slag and waste heat recovery
CN202898362U (en) Partially chilled dry pulverized coal or coal water slurry gasification system
CN103196124B (en) Slag disposing technology device by evaporating pot method
CN101476015B (en) AOD converter flue gas waste heat recovery apparatus
CN104946826B (en) A kind of metallurgical slag waste heat recovery apparatus and method
CN105063259B (en) A kind of blast furnace cinder heat reclaim unit and application method
CN107990740B (en) The equipment for utilizing blast furnace slag wind quenching granulated particles waste heat for supplying based on flash evaporation technology
CN203904370U (en) Device applied to heat recovery of slag flushing water
CN203530346U (en) Cooling-tower-free high temperature slag water-quenching condensing system
CN203530347U (en) Granulation-pump-free high temperature slag water quenching system
CN103993109A (en) Blast furnace slag waste heat recovery system and recovering control method for blast furnace slag waste heat recovery system
CN206956069U (en) A kind of blast-furnace slag heat reclamation device of heat recovery module and its composition
CN101793466A (en) Power-generating boiler capable of cooling steel products and recovering afterheat in steelmaking and steel-rolling process
CN203820804U (en) System for preheating boiler water by washing blast furnace slag water
CN204918630U (en) Slag water smoke granulating device
CN214168013U (en) Environment-friendly blast furnace slag treatment steam recovery system
CN212955028U (en) Gas deacidification heat sink
CN103525958A (en) Non-granulation-pump type high temperature slag water quenching technology and system
CN109439813B (en) Method for recovering waste heat of steam diffused by blast furnace slag flushing
CN204535432U (en) Cement plant kiln hood who knows cooling machine low-temperature flue gas residual neat recovering system

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
AV01 Patent right actively abandoned

Granted publication date: 20140409

Effective date of abandoning: 20150701

RGAV Abandon patent right to avoid regrant