CN203518225U - Large-air-volume coal-to-gas boiler - Google Patents

Large-air-volume coal-to-gas boiler Download PDF

Info

Publication number
CN203518225U
CN203518225U CN201320639739.8U CN201320639739U CN203518225U CN 203518225 U CN203518225 U CN 203518225U CN 201320639739 U CN201320639739 U CN 201320639739U CN 203518225 U CN203518225 U CN 203518225U
Authority
CN
China
Prior art keywords
gas
combustion chamber
coal
air
heater
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201320639739.8U
Other languages
Chinese (zh)
Inventor
王洪宇
赵腾
尹超宇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China University of Mining and Technology CUMT
Original Assignee
China University of Mining and Technology CUMT
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China University of Mining and Technology CUMT filed Critical China University of Mining and Technology CUMT
Priority to CN201320639739.8U priority Critical patent/CN203518225U/en
Application granted granted Critical
Publication of CN203518225U publication Critical patent/CN203518225U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Solid-Fuel Combustion (AREA)

Abstract

The utility model relates to a large-air-volume coal-to-gas boiler. The large-air-volume coal-to-gas boiler is provided with a barrel-shaped boiler body, wherein a dust storage box for collecting duct is arranged at the bottom of the boiler body, a primary combustion chamber, a secondary combustion chamber and a heating medium chamber are arranged in the boiler body from bottom to top, the side of the primary combustion chamber is provided with a coal inlet and an ignition port, and a gas furnace plate is fixed inside the secondary combustion chamber. The upper portion of the secondary combustion chamber is communicated with the lower portions of multiple metal pipes, the upper portions of the metal pipes are sequentially connected with a gas purifying device and a chimney, the side of the boiler body is provided with a pressure meter and a temperature digital display meter, the side of the lower portion of the boiler body is communicated with two air blowers, regulating valves for regulating air volume are arranged on air supply pipes of the air blowers, and the upper portion of the boiler body is provided with a gas output port. The large-air-volume coal-to-gas boiler is simple and convenient to operate and safe in use, and the gas yield in unit time is high. In addition, gas discharged into the atmosphere can be filtered and purified, environmental protection is facilitated, and a good opportunity is provided for development of coal-to-gas boilers for civil use.

Description

Wind Volume coal becomes gas boiler
Technical field
the utility model relates to a kind of coal and becomes gas boiler, especially uses the Wind Volume coal that safety, hygienic environment-protecting and unit interval gas production are many to become gas boiler.
Background technology
china be a rich coal resources country.The reserves row third place in the world of coal, the output of coal is the first in the world, as developing country, within foreseeable period, Chinese development be take coal and is that main energy general layout can not change, therefore, how abundant coal is cheaply realized to the utilization of Environmental Safety, become the key subjects of China's economic construction.
at present, knownly take the civil boiler that coal is fuel and not only burn insufficient, cost is high, and in the unit interval, gas production is few, cannot meet the demand of simultaneously using compared with multi-user, in addition, existing coal becomes gas boiler easily to airborne release dust and sulfide gas, contaminated environment, is unfavorable for environmental protection, has directly restricted the development of civil boiler and has promoted the use of.
Utility model content
in order to solve existing coal, become the few problem of gas production in insufficient and unit interval of gas boiler burning, the utility model provides a kind of Wind Volume coal to become gas boiler, it is not only easy and simple to handle that this Wind Volume coal becomes gas boiler, use safety, in unit interval, gas production is many, and can the gas being discharged in atmosphere be filtered and be purified, being beneficial to environmental protection, the development that becomes gas boiler for civil coal provides excellent opportunity.
the utility model solves the technical scheme that its technical problem adopts: this Wind Volume coal becomes the body of heater that gas boiler is provided with a cartridge type, the bottom of body of heater is provided with the dust-collecting box of collecting dust, in body of heater, be provided with from the bottom up primary zone, secondary combustion chamber and heating agent chamber, primary zone, secondary combustion chamber and heating agent chamber are separated by the metallic plate of good heat conductivity, metallic plate central authorities between primary zone and secondary combustion chamber are provided with passage, the side of primary zone is provided with coal feed point and lighting-up tuyere, the indoor 1-3 of being fixed with of second-time burning the combustion gas stone or metal plate for standing a stove on as a precaution against fire being arranged in parallel up and down, the top of secondary combustion chamber is connected with many bottoms with metal tube, metal tube top is connected with gas cleaning plant and chimney successively, the side of body of heater is provided with pressure and takes into account temperature digital display meter, can monitor at any time and show the pressure and temperature of gas in body of heater, the side, below of body of heater is connected with two air blasts, thereby meet Wind Volume requirement, the ajutage of air blast is provided with the control valve that regulates air output, the top of body of heater is provided with gas delivery port.While using boiler, coal is sent into primary zone from coal feed point, and by lighting-up tuyere, coal is lighted, the coal of burning can produce coal gas, rises to combustion gas stone or metal plate for standing a stove on as a precaution against fire, at the gas furnace fire of making an inventory, this fire is the heating of metal tube and metallic plate, from the cool breeze that blows into two air blasts in heating agent chamber after scorching hot metallic plate and metal tube heat up, from gas delivery port, export, the gas producing during gas-fired enters gas cleaning plant by the tube chamber of metal tube, then by chimney, discharges boiler.
the beneficial effects of the utility model are that it is not only easy and simple to handle that this Wind Volume coal becomes gas boiler, uses safety, in unit interval, gas production is many, and can the gas being discharged in atmosphere be filtered and be purified, being beneficial to environmental protection, the development that becomes gas boiler for civil coal provides excellent opportunity.
Accompanying drawing explanation
below in conjunction with drawings and Examples, the utility model is described in further detail.
fig. 1 is structural principle schematic diagram of the present utility model.
in Fig. 1,1. heating agent chamber, 2. metal tube, 3. secondary combustion chamber, 4. combustion gas stone or metal plate for standing a stove on as a precaution against fire, 5. coal feed point, 6. lighting-up tuyere, 7. primary zone, 8. dust-collecting box, 9. control valve, 10. air blast, 11. pressure gauges, 12. temperature digital display meters, 13. bodies of heater, 14. gas delivery ports, 15. chimneys, 16. gas cleaning plants.
The specific embodiment
in Fig. 1, this Wind Volume coal becomes the body of heater 13 that gas boiler is provided with a cartridge type, the bottom of body of heater 13 is provided with the dust-collecting box 8 of collecting dust, in body of heater 13, be provided with from the bottom up primary zone 7, secondary combustion chamber 3 and heating agent chamber 1, primary zone 7, secondary combustion chamber 3 and heating agent chamber 1 are separated by the metallic plate of good heat conductivity, metallic plate central authorities between primary zone 7 and secondary combustion chamber 3 are provided with passage, the side of primary zone 7 is provided with coal feed point 5 and lighting-up tuyere 6, in secondary combustion chamber 3, be fixed with 1-3 the combustion gas stone or metal plate for standing a stove on as a precaution against fire 4 being arranged in parallel up and down, the top of secondary combustion chamber 3 is connected with many bottoms with metal tube 2, metal tube 2 tops are connected with gas cleaning plant 16 and chimney 15 successively, the side of body of heater 13 is provided with pressure gauge 11 and temperature digital display meter 12, can monitor at any time and show the pressure and temperature of body of heater 13 interior gases, the side, below of body of heater 13 is connected with two air blasts 10, thereby meet Wind Volume requirement, the ajutage of air blast 10 is provided with the control valve 9 that regulates air output, the top of body of heater 13 is provided with gas delivery port 14.While using boiler, coal is sent into primary zone 7 from coal feed point 5, and by lighting-up tuyere 6, coal is lighted, the coal of burning can produce coal gas, rise to combustion gas stone or metal plate for standing a stove on as a precaution against fire 4, in 4 igniting of combustion gas stone or metal plate for standing a stove on as a precaution against fire, this fire is by metal tube 2 and metallic plate heating, from the cool breeze that blows into two air blasts 10 in heating agent chamber 1 after scorching hot metallic plate and metal tube 2 heat up, from gas delivery port 14 outputs, the gas producing during gas-fired enters gas cleaning plant 16 by the tube chamber of metal tube 2, then by chimney 15, discharges boiler.

Claims (3)

1. wind Volume coal becomes gas boiler, this Wind Volume coal becomes the body of heater (13) that gas boiler is provided with a cartridge type, it is characterized in that, the bottom of body of heater (13) is provided with the dust-collecting box (8) of collecting dust, in body of heater (13), be provided with from the bottom up primary zone (7), secondary combustion chamber (3) and heating agent chamber (1), primary zone (7), secondary combustion chamber (3) and heating agent chamber (1) are separated by the metallic plate of good heat conductivity, metallic plate central authorities between primary zone (7) and secondary combustion chamber (3) are provided with passage, the top of secondary combustion chamber (3) is connected with the bottom of many metal tubes (2), metal tube (2) top is connected with gas cleaning plant (16) and chimney (15) successively, the side of body of heater (13) is provided with pressure gauge (11) and temperature digital display meter (12), the side, below of body of heater (13) is connected with two air blasts (10), the ajutage of air blast (10) is provided with the control valve (9) that regulates air output, the top of body of heater (13) is provided with gas delivery port (14).
2. wind Volume coal according to claim 1 becomes gas boiler, it is characterized in that, the side of described primary zone (7) is provided with coal feed point (5) and lighting-up tuyere (6).
3. wind Volume coal according to claim 1 becomes gas boiler, it is characterized in that, is fixed with 1-3 the combustion gas stone or metal plate for standing a stove on as a precaution against fire (4) being arranged in parallel up and down in described secondary combustion chamber (3).
CN201320639739.8U 2013-10-17 2013-10-17 Large-air-volume coal-to-gas boiler Expired - Fee Related CN203518225U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201320639739.8U CN203518225U (en) 2013-10-17 2013-10-17 Large-air-volume coal-to-gas boiler

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201320639739.8U CN203518225U (en) 2013-10-17 2013-10-17 Large-air-volume coal-to-gas boiler

Publications (1)

Publication Number Publication Date
CN203518225U true CN203518225U (en) 2014-04-02

Family

ID=50377151

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201320639739.8U Expired - Fee Related CN203518225U (en) 2013-10-17 2013-10-17 Large-air-volume coal-to-gas boiler

Country Status (1)

Country Link
CN (1) CN203518225U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107270531A (en) * 2017-08-08 2017-10-20 赵治荣 Environment-protection boiler and heating equipment
CN108180626A (en) * 2017-12-21 2018-06-19 陈方羽 A kind of power economized boiler based on second-time burning preheating technology

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107270531A (en) * 2017-08-08 2017-10-20 赵治荣 Environment-protection boiler and heating equipment
CN107270531B (en) * 2017-08-08 2023-08-22 赵治荣 Environment-friendly boiler and heating equipment
CN108180626A (en) * 2017-12-21 2018-06-19 陈方羽 A kind of power economized boiler based on second-time burning preheating technology

Similar Documents

Publication Publication Date Title
CN205090598U (en) Coal -fired powder boiler of vertical extreme misery tubular construction
CN103644562A (en) Combined type energy-saving biomass fuel boiler
CN204630034U (en) Coiled hot water, steam boiler
CN203518225U (en) Large-air-volume coal-to-gas boiler
CN204665226U (en) A kind of steam generator
CN201926118U (en) Heat transfer oil furnace and vortex combustor biomass all-in-one machine
CN203336816U (en) Large horizontal type boiler for recycling smoke waste heat
CN203550187U (en) Normal-pressure biomass rolling furnace bar hot-water boiler
CN203203013U (en) Biomass steam generator
CN202562026U (en) Coal-fired and gas-fired dual-purpose vertical hot-blast stove
CN202322935U (en) Economical inclined bottom heating furnace
CN202074684U (en) Water heating furnace
CN104329802A (en) Condensing boiler
CN204165228U (en) Normal-pressure hot-water boiler
CN203907605U (en) Self-preheating burner
CN201926108U (en) Biomass vertical heat-conducting oil furnace
CN203177444U (en) Numerical control boiler
CN207648798U (en) The full premix heating stove of cast aluminium formula heat exchange
CN203776011U (en) Multi-burner combustion and heating system for frying equipment
CN203571694U (en) Steam boiler
CN216481621U (en) Wall-mounted furnace heat exchange system with condensation function
CN202470430U (en) Economizer for coal burning boiler
CN102032672B (en) Biomass integrated machine consisting of heat conducing oil furnace and cyclone burner
CN103234265A (en) Biomass fuel environment-friendly energy-saving boiler and waste heat recovery method
CN102589129A (en) Energy saver of coal-fired boiler

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20140402

Termination date: 20141017