CN203514342U - Corrosion resistant precast pile for gas insulated substation (GIS) device foundation in transformer substation in salt lake area - Google Patents

Corrosion resistant precast pile for gas insulated substation (GIS) device foundation in transformer substation in salt lake area Download PDF

Info

Publication number
CN203514342U
CN203514342U CN201320648734.1U CN201320648734U CN203514342U CN 203514342 U CN203514342 U CN 203514342U CN 201320648734 U CN201320648734 U CN 201320648734U CN 203514342 U CN203514342 U CN 203514342U
Authority
CN
China
Prior art keywords
pile
salt lake
gis
lake area
precast pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN201320648734.1U
Other languages
Chinese (zh)
Inventor
王鹏
高伟斌
陈凌云
郭琳
扈燕博
任永军
祁成
张妍芳
耿继芳
杨倩
王新红
杜秀娟
耿秀兰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xining Ning Guang Engineering Consulting Co Ltd
Shaanxi Electric Power Design Institute
Original Assignee
Xining Ning Guang Engineering Consulting Co Ltd
Shaanxi Electric Power Design Institute
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xining Ning Guang Engineering Consulting Co Ltd, Shaanxi Electric Power Design Institute filed Critical Xining Ning Guang Engineering Consulting Co Ltd
Priority to CN201320648734.1U priority Critical patent/CN203514342U/en
Application granted granted Critical
Publication of CN203514342U publication Critical patent/CN203514342U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Abstract

The utility model relates to the technical field of power transmission and transformation and specifically relates to a precast pile for foundation treatment for a gas insulated substation (GIS) device in a transformer substation in a salt lake area. A glass reinforced plastic corrosion resistant layer coats an outer surface of the reinforced concrete precast pile and is bonded to the reinforced concrete precast pile. According to the corrosion resistant precast pile, the glass reinforced plastic corrosion resistant layer with high corrosion resistance and waterproof features coats an original reinforced concrete pile foundation, so that the purpose of corrosion resistance of a pile body is achieved. By means of the construction way of the precast pile, difficulties of construction due to underground water are well solved. According to the corrosion resistant precast pile for the gas insulated substation (GIS) device foundation in the transformer substation in the salt lake area, unit costs of the pile body and construction technology process modes are low, and the precast pile can be widely applied to foundation treatment of large devices in the transformer substation in the salt lake area.

Description

The anticorrosion preformed pile of a kind of Salt Lake Area GIS of transformer station equipment Foundations
Technical field
The utility model relates to and send power transformation technical field, specifically relates to a kind of GIS of Salt Lake Area transformer station equipment Foundations preformed pile that adopts preformed pile to carry out ground processing for the GIS of Salt Lake Area transformer station equipment.
Background technology
Its geological conditions of West of Qinghai Province Salt Lake Area is comparatively special, and foundation soil is salinized soil, has the features such as low bearing capacity, corrosivity be strong; Underground water is higher, and there is severe corrosive, therefore general employing of this area's foundation treatment mode, wrap up in body broken stone pile, cobble and change and the processing mode such as fill out, but body broken stone pile unit price is higher owing to wrapping up in, in transformer station, ground disposal cost is less conventionally, and therefore aspect application in substations, cost performance is lower, cobble changes to be filled out because underground water is higher, Dewatering measure difficulty, is difficult to guarantee cushion construction quality, therefore in this area, is necessary the novel foundation treatment mode of research application.
West of Qinghai Province power grid construction scale continues to increase, Qinghai-Tibet networking, blue or green new networking project complex geologic conditions along the line, and many places are in salinized soil (salt lake, corrosion swampy area).Because construction of structures in transformer station comparatively disperses, ground is processed and is adopted the rear expense of full wafer processing higher, therefore also inapplicable in transformer station, especially in station, some special electric fixturess require high to the bearing capacity of foundation soil and differential settlement, therefore for solving base stabilization and the safety problem of transformer station's construction of structures, in conjunction with existing processing experience and engineering practice, study the application of anticorrosion preformed pile in construction of structures basis, swampy area, salt lake, determine anticorrosion way and construction technology.
Summary of the invention
The technical problems to be solved in the utility model is the deficiency existing for prior art, provides a kind of Salt Lake Area GIS of transformer station equipment Foundations anticorrosion preformed pile.
A kind of Salt Lake Area of the utility model anticorrosion preformed pile of the GIS of transformer station equipment Foundations is achieved by following technical proposals: the anticorrosion preformed pile of a kind of Salt Lake Area GIS of transformer station equipment Foundations comprises precast reinforced concrete piles, Corrosion Protection of Fiber Reinforced Plastics layer, and described Corrosion Protection of Fiber Reinforced Plastics layer is wrapped in precast reinforced concrete piles external surface and is connected with precast reinforced concrete piles is bonding.
A kind of Salt Lake Area of the utility model anticorrosion preformed pile of the GIS of transformer station equipment Foundations has following beneficial effect compared with prior art: a kind of Salt Lake Area of the utility model GIS of transformer station equipment Foundations preformed pile has been coated one deck Corrosion Protection of Fiber Reinforced Plastics layer on former concrete pile foundation, and its advantage is 1. to have solved pile body Anticorrosion; Because Salt Lake Area foundation soil and underground water all have severe corrosive, and groundwater table is higher, common concrete precast pile is also inapplicable in this area, therefore, the utility model has been coated the Corrosion Protection of Fiber Reinforced Plastics layer that one deck has stronger corrosion resistance and water proofing property characteristic on former concrete pile foundation, has solved well pile body corrosion-resistant problem.
By the experience at Salt Lake Area similar engineering, this material of glass fiber reinforced plastic has stronger corrosion resistance and water proofing property, and this material and preformed pile body bonding firmly, should not come off, therefore as preformed pile outer anticorrosion be material preferably; By improving the concrete intensity of pile body body, also can increase substantially the resistance to corrosion of pile body simultaneously.
2. the anticorrosion construction of prefabricated piles technique of the GIS of the utility model Salt Lake Area transformer station equipment Foundations; Because Salt Lake Area groundwater table is higher, surface soil layer bearing capacity is lower, large-scale sinking apparatus is easily absorbed in, thereby cause comparatively difficulty of pile sinking work, the feature that is therefore composite foundation in conjunction with this processing mode, the construction technology that preformed pile is processed is adjusted, first in former foundation ditch bottom, hardcore bed is set, and then carry out pile sinking work, because cone-shaped is made in the anticorrosion preformed pile of the utility model bottom, pile sinking is easy to.After pile sinking work completes, again top bed course is processed and is encased inside bituminous concrete, the solution that the utility model form of construction work is good underground water to the difficulty that causes of construction.
3. the anticorrosion preformed pile processing mode of the utility model cost performance is higher; Because Salt Lake Area ground prior art processing mode is general, adopts and wrap up in body broken stone pile, through measuring and calculating, the anticorrosion preformed pile engineering of the GIS of Salt Lake Area transformer station equipment Foundations is wrapped up in approximately 1,300 ten thousand yuan of body broken stone pile construction costs as what adopt original technology, and the GIS of transformer station equipment Foundations anticorrosion construction of prefabricated piles journey in the utility model Salt Lake Area adopts and wraps up in after body preformed pile approximately 3,500,000 yuan of construction costs, therefore this processing mode has larger investment advantage, and cost performance is higher.
4. because Salt Lake Area lacks conventional building material, solved the problem that lacks conventional building material after therefore adopting the anticorrosion preformed pile of the utility model, and the transportation of anticorrosion preformed pile more for convenience.
Adopt after the anticorrosion precast concrete pile of the utility model, improved the bearing capacity of foundation soil; Adopt after glass fiber reinforced plastic parcel, solved pile body corrosion-resistant problem.Relatively comprehensive, the anticorrosion preformed pile pile body of a kind of Salt Lake Area of the utility model GIS of transformer station equipment Foundations and construction technology processing mode unit price are low, can be widely used in the based process of Salt Lake Area transformer station main equipment.
Accompanying drawing explanation
A kind of Salt Lake Area of the utility model anticorrosion preformed pile of the GIS of transformer station equipment Foundations has following accompanying drawing:
Fig. 1 is the anticorrosion preformed pile pile body structure of a kind of Salt Lake Area of the utility model GIS of transformer station equipment Foundations schematic diagram;
Fig. 2 is the anticorrosion preformed pile mounting structure of a kind of Salt Lake Area of the utility model GIS of transformer station equipment Foundations schematic diagram;
Fig. 3 is the anticorrosion preformed pile 110kVGIS of a kind of Salt Lake Area of the utility model GIS of transformer station equipment Foundations arrangement of pile foundation structural representation;
Fig. 4 is the anticorrosion preformed pile 330kVGIS of a kind of Salt Lake Area of the utility model GIS of transformer station equipment Foundations arrangement of pile foundation structural representation.
Wherein: 1, reinforced concrete pile; 2, Corrosion Protection of Fiber Reinforced Plastics layer; 3, hardcore bed; 4, bituminous concrete; 5, GIS basis; 6, powder soil horizon.
The specific embodiment
Below in conjunction with drawings and Examples, a kind of Salt Lake Area of technical scheme utility model anticorrosion precast pile technique scheme of the GIS of transformer station equipment Foundations is further described.
As Figure 1-Figure 4, a kind of Salt Lake Area of the utility model anticorrosion preformed pile of the GIS of transformer station equipment Foundations comprises precast reinforced concrete piles 1, Corrosion Protection of Fiber Reinforced Plastics layer 2, and described Corrosion Protection of Fiber Reinforced Plastics layer 2 is wrapped in precast reinforced concrete piles 1 external surface and is connected with precast reinforced concrete piles 1 is bonding.
Described precast reinforced concrete piles 1 sinks to three layers of powder soil horizon 6, and top lower floor is hardcore bed 3, and upper strata, top is bituminous concrete 4, and top is GIS basis 5.
Embodiment 1.
A kind of Salt Lake Area of the utility model anticorrosion preformed pile of the GIS of transformer station equipment Foundations comprises precast reinforced concrete piles 1, Corrosion Protection of Fiber Reinforced Plastics layer 2, and described Corrosion Protection of Fiber Reinforced Plastics layer 2 is wrapped in precast reinforced concrete piles 1 external surface and is connected with precast reinforced concrete piles 1 is bonding.Cone-shaped is made in the bottom of precast reinforced concrete piles 1 and Corrosion Protection of Fiber Reinforced Plastics layer 2.As shown in Figure 1.
The GIS of transformer station equipment Foundations anticorrosion preformed pile in a kind of Salt Lake Area of the utility model is when construction, first in former foundation ditch bottom, hardcore bed 3 is set, and then carry out pile sinking work, be about to the anticorrosion preformed pile of the utility model and be pressed into or ram powder soil horizon 6, after pile sinking work completes, on upper strata, the utility model anticorrosion preformed pile top, be encased inside bituminous concrete 4, top is GIS basis 5.As shown in Figure 2.
A kind of Salt Lake Area of the utility model anticorrosion preformed pile of the GIS of transformer station equipment Foundations is applied to 110kVGIS arrangement of pile foundation as shown in Figure 3.
Embodiment 2.
A kind of Salt Lake Area of the utility model anticorrosion preformed pile of the GIS of transformer station equipment Foundations comprises precast reinforced concrete piles 1, Corrosion Protection of Fiber Reinforced Plastics layer 2, and described Corrosion Protection of Fiber Reinforced Plastics layer 2 is wrapped in precast reinforced concrete piles 1 external surface and is connected with precast reinforced concrete piles 1 is bonding.Cone-shaped is made in the bottom of precast reinforced concrete piles 1 and Corrosion Protection of Fiber Reinforced Plastics layer 2.As shown in Figure 1.
The GIS of transformer station equipment Foundations anticorrosion preformed pile in a kind of Salt Lake Area of the utility model is when construction, first in former foundation ditch bottom, hardcore bed 3 is set, and then carry out pile sinking work, be about to the anticorrosion preformed pile of the utility model and be pressed into or ram powder soil horizon 6, after pile sinking work completes, on upper strata, the utility model anticorrosion preformed pile top, be encased inside bituminous concrete 4, top is GIS basis 5.As shown in Figure 2.
A kind of Salt Lake Area of the utility model anticorrosion preformed pile of the GIS of transformer station equipment Foundations is applied to 330kVGIS arrangement of pile foundation as shown in Figure 4.

Claims (2)

  1. The anticorrosion preformed pile of the 1.Yi Zhong Salt Lake Area GIS of transformer station equipment Foundations, comprise precast reinforced concrete piles (1), Corrosion Protection of Fiber Reinforced Plastics layer (2), it is characterized in that: described Corrosion Protection of Fiber Reinforced Plastics layer (2) be wrapped in precast reinforced concrete piles (1) external surface and with bonding connection of precast reinforced concrete piles (1).
  2. 2. the anticorrosion preformed pile of the Salt Lake Area GIS of transformer station equipment Foundations according to claim 1, it is characterized in that: described precast reinforced concrete piles (1) sinks to three layers of powder soil horizon (6), top lower floor is hardcore bed (3), upper strata, top is bituminous concrete (4), and top is GIS basis (5).
CN201320648734.1U 2013-10-22 2013-10-22 Corrosion resistant precast pile for gas insulated substation (GIS) device foundation in transformer substation in salt lake area Expired - Lifetime CN203514342U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201320648734.1U CN203514342U (en) 2013-10-22 2013-10-22 Corrosion resistant precast pile for gas insulated substation (GIS) device foundation in transformer substation in salt lake area

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201320648734.1U CN203514342U (en) 2013-10-22 2013-10-22 Corrosion resistant precast pile for gas insulated substation (GIS) device foundation in transformer substation in salt lake area

Publications (1)

Publication Number Publication Date
CN203514342U true CN203514342U (en) 2014-04-02

Family

ID=50373297

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201320648734.1U Expired - Lifetime CN203514342U (en) 2013-10-22 2013-10-22 Corrosion resistant precast pile for gas insulated substation (GIS) device foundation in transformer substation in salt lake area

Country Status (1)

Country Link
CN (1) CN203514342U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104652426A (en) * 2014-12-18 2015-05-27 青海省电力设计院 Foundation construction method of water-glass anti-corrosion pile in saline soil areas
CN110258535A (en) * 2019-07-30 2019-09-20 南京新核复合材料有限公司 A kind of ocean engineering combined type driven pile and its construction method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104652426A (en) * 2014-12-18 2015-05-27 青海省电力设计院 Foundation construction method of water-glass anti-corrosion pile in saline soil areas
CN110258535A (en) * 2019-07-30 2019-09-20 南京新核复合材料有限公司 A kind of ocean engineering combined type driven pile and its construction method

Similar Documents

Publication Publication Date Title
CN203583526U (en) Waterproof structure of peat soft soil stratum subway station
CN104569341A (en) Vacuum preloading and electroosmosis combined testing device and vacuum preloading and electroosmosis combined testing method
CN203200746U (en) High-pressure jet grouting hollow reinforced tubular pile
CN102926378A (en) Conductive composite vacuum soft soil reinforcing prepressing method
CN104099920B (en) A kind of Reinforced Foundation
CN203514260U (en) Geomembrane anchoring impervious structure
CN203514342U (en) Corrosion resistant precast pile for gas insulated substation (GIS) device foundation in transformer substation in salt lake area
CN102437437B (en) Grounding resistance reduction process method for sand/gravel area
CN103161151A (en) Construction method of high pressure jet grouting hollow strengthening tubular pile and high pressure jet grouting hollow strengthening tubular pile
CN203277668U (en) Well group grounding grid
CN203367936U (en) Cable trench
CN202850013U (en) Whole composite foundation structure for lime soil and anti-seepage membrane
CN202530351U (en) Carbon mudstone- clay layered and staggered embankment filling structure
Shen et al. The performance of super soft foundations under a modified vacuum preloading method
CN202202339U (en) Geogrid reinforced soil retaining wall of concrete module
CN102116019A (en) Method for rapidly treating soft foundation through high vacuum densification
CN208088230U (en) A kind of net dress Ke shell barricades
CN203947469U (en) Two carrying helical burr ram for building
CN204491797U (en) A kind of sports ground dmp filter stacking device
CN103259104A (en) Well group grounding net
CN107083729A (en) One kind stores permeable module and preparation method thereof
Yan et al. Environmental influence of vacuum preloading dredging project
CN203924089U (en) For the pile foundation of offshore wind farm facility
CN202925540U (en) Arrangement structure of device for processing soft soil foundation in coastal reclamation region
CN201770990U (en) Dewatering well structure in deep foundation pit

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term

Granted publication date: 20140402

CX01 Expiry of patent term