CN203464752U - Double-joint electrode water-cooled holder of corundum smelting furnace - Google Patents

Double-joint electrode water-cooled holder of corundum smelting furnace Download PDF

Info

Publication number
CN203464752U
CN203464752U CN201320555751.0U CN201320555751U CN203464752U CN 203464752 U CN203464752 U CN 203464752U CN 201320555751 U CN201320555751 U CN 201320555751U CN 203464752 U CN203464752 U CN 203464752U
Authority
CN
China
Prior art keywords
holder
welded
box hat
steel
support arm
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201320555751.0U
Other languages
Chinese (zh)
Inventor
陈宏亲
陈英超
陈晓
梁跃华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhengzhou City Wide Intelligence Plant Equipment Co Ltd
Original Assignee
Zhengzhou City Wide Intelligence Plant Equipment Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhengzhou City Wide Intelligence Plant Equipment Co Ltd filed Critical Zhengzhou City Wide Intelligence Plant Equipment Co Ltd
Priority to CN201320555751.0U priority Critical patent/CN203464752U/en
Application granted granted Critical
Publication of CN203464752U publication Critical patent/CN203464752U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Vertical, Hearth, Or Arc Furnaces (AREA)

Abstract

The utility model relates to a double-joint electrode water-cooled holder of a corundum smelting furnace. The double-joint electrode water-cooled holder of the corundum smelting furnace consists of a holder steel body housing and a double-joint holder copper inner wall which are welded into a closed cavity structure by a copper steel composite welding method, wherein the double-joint holder copper inner wall, the welded steel housing, the end parts of two steel plates with butted end parts, the side walls of the steel housing and inner supporting arms are commonly welded into a closed cavity structure. When the corundum smelting furnace works, flowing water is injected into a water inlet pipe arranged at one end of one of the steel housing side walls and flows out of a water outlet pipe along water guide holes formed in the inner supporting arms to take away heat generated by the arc-shaped conductive contact end during operation, so that the temperature of the arc-shaped conductive contact end during operation ranges from 50 and 70 DEG C, electricity consumption is reduced, the aim of saving electricity is fulfilled, and the defects in the prior art are overcome.

Description

Corundum smelting stove twin adapter electrode water-cooled holder
Technical field
The utility model relates to corundum smelting stove electrod assembly field, is specifically related to a kind of corundum smelting stove twin adapter electrode water-cooled holder; By water-cooled cooling, the holder that makes corundum smelting stove electrode in low-temperature condition, to reduce current drain, is realized the object of economize on electricity when work.
Background technology
Corundum smelting stove consumes electric energy in process of production in a large number, is genuine electric-tiger.The critical piece of traditional corundum smelting stove was divided into wall copper coin, middle copper pipe, soft copper strips, the holder etc. of connecting.As everyone knows, voltage is lower, wire is longer, resistance is larger, consumes highlyer, and the line loss of wire is also higher.Root is according to data: the contact power consumption in each hour of 5000K V A transformer is 10 degree, and every transformer calculates by 12 joints, per hour with regard to loss of electricity 120 degree.Conductive resistance is directly proportional to temperature, and by theoretical every every high once resistance difference 0.004, copper bar temperature is 120~180 ℃; Especially the holder of smelting furnace electrode, is the key joints of as easy as rolling off a log generation high temperature, and temperature during work is much larger than 180 ℃; Burn out sometimes even part of appliance; Therefore, design a kind of corundum smelting stove twin adapter electrode water-cooled holder---by water-cooled cooling, the holder that makes corundum smelting stove electrode when work in low-temperature condition, to reduce electric quantity consumption, the object that realizes economize on electricity, this has positive realistic meaning for corundum smelting industry.
Utility model content
The purpose of this utility model is to provide a kind of corundum smelting stove twin adapter electrode water-cooled holder---pass through water-cooled cooling, make holder in when work in low-temperature condition, to reduce current drain, realize the object of economize on electricity, overcome the deficiencies in the prior art and defect.
For achieving the above object, the utility model has adopted such technical scheme: a kind of corundum smelting stove twin adapter electrode water-cooled holder, is comprised of a holder steel body case and a copper inwall of twin adapter holder that adopts copper steel complex welding method to be welded into airtight cavity structure with it; It is characterized in that: described holder steel body case is comprised of a welding box hat, two box hat sidewalls, inner support arm, end docking steel plate, strengthening steel slabs; The both sides of welding box hat are welded with respectively box hat sidewall, are welded with inner support arm in structure, are prefabricated with at least two water-guiding holes on inner support arm; The two ends of one of them box hat sidewall are respectively equipped with water inlet pipe and outlet pipe;
The two ends of welding box hat respectively symmetrical end are welded with end docking steel plate, and the both sides of junction are welded with boss, and end docking steel plate is provided with at least two screws; On one of them end docking steel plate, be connected with strengthening steel slab; The copper inwall of twin adapter holder is arcuate structure, and arcuate structure is welded on the docking end of steel plate, two ends, the end along portion, inner support arm of box hat sidewall; Dock with welding box hat, two ends steel plate end, box hat sidewall along portion, inner support arm, be jointly welded into an airtight cavity body structure;
Two parallel holder terminal plates extend and are welded on the inner side of the copper inwall of twin adapter holder through the top of welding box hat, the extension of two holder terminal plates forms inner support arm.
Adopt after such structure, holder steel body case has enough intensity, and the copper inwall of twin adapter holder has good electric conductivity; Adopt the compound welding method of copper steel that the two is welded together, intensity and electric conductivity have both, and cheap for manufacturing cost, are comparatively desirable combinations.
End, box hat sidewall, the inner support arm of the copper inwall of twin adapter holder, welding box hat, two end docking steel plates are welded into an airtight cavity body structure jointly; When corundum smelting furnaceman does, the water inlet pipe arranging from one end of one of them box hat sidewall injects flowing water, flowing water is along the water-guiding hole arranging on inner support arm, from outlet pipe, flow out, the heat producing while taking away the work of arc conduction contravention, the temperature while making the work of arc conduction contravention is between 50-70 °; (conductive resistance is directly proportional to temperature) thus reduce electric quantity consumption, realize the object of economize on electricity, overcome the deficiencies in the prior art and defect.
Accompanying drawing explanation
It shown in Fig. 1, is the front view of the utility model concrete structure; Fig. 2 is the top view of Fig. 1; Fig. 3 is the cutaway view of A-A shown in Fig. 1.
The specific embodiment
Specific embodiment: as shown in the figure, described corundum smelting stove twin adapter electrode water-cooled holder, is comprised of a holder steel body case and a copper inwall 7 of the twin adapter holder that adopts copper steel complex welding method to be welded into airtight cavity structure with it;
It is characterized in that: described holder steel body case is comprised of a welding box hat 5, two box hat sidewalls 51, inner support arm 50, end docking steel plate 1, strengthening steel slabs 9; The both sides of welding box hat 5 are welded with respectively box hat sidewall 51, are welded with inner support arm 50 in structure, are prefabricated with at least two water-guiding holes 52 on inner support arm 50; The two ends of one of them box hat sidewall 51 are respectively equipped with water inlet pipe 4 and outlet pipe 8;
The two ends of welding box hat 5 respectively symmetrical end are welded with end docking steel plate 1, and the both sides of junction are welded with boss 3, and end docking steel plate 1 is provided with at least two screws 2; On one of them end docking steel plate 1, be connected with strengthening steel slab 9;
The copper inwall 7 of twin adapter holder is arcuate structure, and arcuate structure is welded on the docking end of steel plate 1, two ends, the end along portion, several inner support arms 50 of box hat sidewall 51; Dock with welding box hat 5, two ends steel plate 1 end, box hat sidewall 51 along portion, inner support arm 5, be jointly welded into the cavity body structure of a sealing;
Two parallel holder terminal plates 6 extend and are welded on the inner side of the copper inwall 7 of twin adapter holder through the top of welding box hat 5, the extension of two holder terminal plates 6 forms inner support arm 50.
The corundum smelting stove twin adapter electrode water-cooled holder exemplifying in the utility model specific embodiment, just half of holder, while specifically using, needs another holder symmetrical with it, is fixed in one end of corundum smelting stove electrode by set bolt.

Claims (1)

1. a corundum smelting stove twin adapter electrode water-cooled holder, is comprised of a holder steel body case and a copper inwall of twin adapter holder (7) that adopts copper steel complex welding method to be welded into airtight cavity structure with it;
It is characterized in that: described holder steel body case is comprised of a welding box hat (5), two box hat sidewalls (51), inner support arm (50), end docking steel plate (1), strengthening steel slab (9); The both sides of welding box hat (5) are welded with respectively box hat sidewall (51), are welded with inner support arm (50) in structure, are prefabricated with at least two water-guiding holes (52) on inner support arm (50); The two ends of one of them box hat sidewall (51) are respectively equipped with water inlet pipe (4) and outlet pipe (8);
The two ends of welding box hat (5) respectively symmetrical end are welded with end docking steel plate (1), and the both sides of junction are welded with boss (3), and end docking steel plate (1) is provided with at least two screws (2); On one of them end docking steel plate (1), be connected with strengthening steel slab (9);
The copper inwall of twin adapter holder (7) is arcuate structure, and arcuate structure is welded on the end of two end docking steel plates (1), the end along portion, inner support arm (50) of box hat sidewall (51); Dock with welding box hat (5), two ends steel plate (1) end, box hat sidewall (51) along portion, inner support arm (5), be jointly welded into the cavity body structure of a sealing;
Two parallel holder terminal plates (6) extend and are welded on the inner side of the copper inwall of twin adapter holder (7) through the top of welding box hat (5), the extension of two holder terminal plates (6) forms inner support arm (50).
CN201320555751.0U 2013-09-02 2013-09-02 Double-joint electrode water-cooled holder of corundum smelting furnace Expired - Fee Related CN203464752U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201320555751.0U CN203464752U (en) 2013-09-02 2013-09-02 Double-joint electrode water-cooled holder of corundum smelting furnace

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201320555751.0U CN203464752U (en) 2013-09-02 2013-09-02 Double-joint electrode water-cooled holder of corundum smelting furnace

Publications (1)

Publication Number Publication Date
CN203464752U true CN203464752U (en) 2014-03-05

Family

ID=50177113

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201320555751.0U Expired - Fee Related CN203464752U (en) 2013-09-02 2013-09-02 Double-joint electrode water-cooled holder of corundum smelting furnace

Country Status (1)

Country Link
CN (1) CN203464752U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104964559A (en) * 2015-06-03 2015-10-07 宁夏太阳镁业有限公司 Bottom ring for submerged arc furnace and manufacturing method for bottom ring

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104964559A (en) * 2015-06-03 2015-10-07 宁夏太阳镁业有限公司 Bottom ring for submerged arc furnace and manufacturing method for bottom ring

Similar Documents

Publication Publication Date Title
CN201313235Y (en) External circulating water-cooled lower electrode suitable for bolt and nut projection welding
CN203464752U (en) Double-joint electrode water-cooled holder of corundum smelting furnace
CN201639809U (en) Energy-saving bus of submerged arc furnace
CN102809298A (en) Water-cooled electrode device for vacuum furnace
CN201313236Y (en) Internal circulating water-cooled lower electrode suitable for bolt and nut projection welding
CN203464751U (en) Electrode water-cooled holder of corundum smelting furnace
CN202770221U (en) Vacuum furnace water cooling electrode device
CN203839637U (en) Gas-electricity integrated electrode gun connector
CN203148191U (en) Low-impedance energy-saving composite conductive transverse arm
CN103486864A (en) Double-joint electrode water-cooled gripper of corundum smelting furnace
CN205071331U (en) A water -cooling combined electrode that is used for direct current electric stove production mineral wool
CN103486865A (en) Corundum smelting furnace electrode water cooling holder
CN203464746U (en) Water-cooled cooling conductive system of corundum smelting furnace
CN205241802U (en) Negative pole rod iron for aluminium electroloysis
CN209580633U (en) A kind of area battery pole piece Kong Bo heating device
CN204539528U (en) The integrated water-cooled conductive tube of corundum stove
CN203471136U (en) Cooling water jacket for lower electrode of projection welding bolt
CN202721853U (en) Arc furnace current collection semi-ring and conductive apparatus formed thereby
CN2205063Y (en) Large size copper-aluminum transition joint
CN203625498U (en) E-shaped clamp for short circuit shunting of aluminum electrolysis cell
CN103490186A (en) Water through cable connector special for corundum smelting furnace
CN203015164U (en) Highly effective inner heat conduction type submerged arc furnace water cooling brass
CN211926495U (en) Melting furnace equipment is used in production of hypoxemia bar copper
CN202162496U (en) Water cooling system for projection welding electrode
CN203982816U (en) Double head type copper bar

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20140305

Termination date: 20140902

EXPY Termination of patent right or utility model