CN203445537U - Cable erecting mechanism used for limiting device of steel bar straightening and cutting machine - Google Patents
Cable erecting mechanism used for limiting device of steel bar straightening and cutting machine Download PDFInfo
- Publication number
- CN203445537U CN203445537U CN201320448920.0U CN201320448920U CN203445537U CN 203445537 U CN203445537 U CN 203445537U CN 201320448920 U CN201320448920 U CN 201320448920U CN 203445537 U CN203445537 U CN 203445537U
- Authority
- CN
- China
- Prior art keywords
- cutting machine
- cable
- bar straightening
- concrete
- horizontal case
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The utility model discloses a cable erecting mechanism used for a limiting device of a steel bar straightening and cutting machine. The cable erecting mechanism comprises two supporting columns and a suspension component which is suspended between the two supporting columns, wherein the suspension component is a rope or wire and is horizontal distributed, and the two supporting columns are vertically arranged; the suspension component is provided with a plurality of pendants which are distributed from left to right and are used for erecting cables, wherein the plurality of pendants are of the same structure, and a cable is a connecting cable which is connected between the limiting device of the steel bar straightening and cutting machine and a control device of the steel bar straightening and cutting machine; at least three pendants exist; each pendant comprises a horizontal sleeve which is mounted on the pendant and a cable through tube which is tightly fixed on the outer side of the horizontal sleeve, wherein the cable through tube and the horizontal sleeve are arranged in parallel; and the cable passes through the cable through tubes inside the plurality of pendants which are distributed from left to right. The cable erecting mechanism of the utility model is advantageous in simple structure, convenient processing, manufacture and installation, simple operation and excellent use effect, and can assist in solving the problem of ground touching of the cable of the limiting device of the steel bar straightening and cutting machine.
Description
Technical field
The utility model belongs to erecting cable technical field of construction, especially relates to a kind of concrete-bar straightening-cutting machine stop cable erecting device.
Background technology
Concrete-bar straightening-cutting machine is one of steel bar processing machinery, is 14 millimeters of following reinforcing bars, and eliminates rust for straightening and cut-out diameter.Stop is one of concrete-bar straightening-cutting machine chief component parts, and it is directly connected to the reinforcing bar crudy of concrete-bar straightening-cutting machine, between the control device of stop and concrete-bar straightening-cutting machine, by cable, is connected.Nowadays, in actual use procedure, be connected in cable between stop and the control device problem that mops floor commonplace, generally cable is all arbitrarily scattered on the ground, because the cable length being connected between stop and control device is longer, thereby occupation of land space is larger, to practice of construction, causes larger inconvenience, and be arbitrarily scattered in the reinforcing bar that ground cable very easily processed and damage by pressure, thereby have larger potential safety hazard.To sum up, nowadays lack a kind of simple in structure, processing and fabricating and concrete-bar straightening-cutting machine stop cable erecting device easy for installation and easy to use, result of use is good, the cable that can effectively the solve concrete-bar straightening-cutting machine stop problem that mops floor.
Utility model content
Technical problem to be solved in the utility model is for above-mentioned deficiency of the prior art, a kind of concrete-bar straightening-cutting machine stop cable erecting device is provided, it is simple in structure, processing and fabricating and easy for installation and use easy and simple to handle, result of use good, the cable that can effectively the solve concrete-bar straightening-cutting machine stop problem that mops floor.
For solving the problems of the technologies described above, the technical solution adopted in the utility model is: a kind of concrete-bar straightening-cutting machine stop cable erecting device, it is characterized in that: comprise two support columns and hang on two suspenders between described support column, described suspender is rope or wire, described suspender is level and is all not less than 1.2m to laying and its suspension height apart from ground, two described support columns are all vertically to laying, and the two ends, left and right of described suspender are separately fixed on two described support columns; On described suspender, be provided with from left to right a plurality of Suspensions that cable is set up, the structure of a plurality of described Suspensions is all identical, and described cable is the stube cable being connected between the stop of concrete-bar straightening-cutting machine and the control device of concrete-bar straightening-cutting machine; The quantity of described Suspension is no less than 3; Described Suspension comprises horizontal case and the fastening penetration pipe that is fixed on horizontal case outside being sleeved on described suspender, and described penetration pipe is parallel laying with horizontal case; Described cable passes in the penetration pipe from a plurality of described Suspensions from left to right; Described horizontal case and penetration pipe are pvc pipe.
Above-mentioned concrete-bar straightening-cutting machine stop cable erecting device, is characterized in that: described penetration pipe be laid in horizontal case under and the two be laid on same vertical plane.
Above-mentioned concrete-bar straightening-cutting machine stop cable erecting device, is characterized in that: the length of described horizontal case and penetration pipe is all not more than 20cm.
Above-mentioned concrete-bar straightening-cutting machine stop cable erecting device, is characterized in that: the quantity of described Suspension is 5~10.
Above-mentioned concrete-bar straightening-cutting machine stop cable erecting device, is characterized in that: all penetration pipes in a plurality of described Suspensions are all laid on same level line.
Above-mentioned concrete-bar straightening-cutting machine stop cable erecting device, is characterized in that: described horizontal case and penetration pipe are circular casing.
Above-mentioned concrete-bar straightening-cutting machine stop cable erecting device, is characterized in that: the length of described horizontal case and penetration pipe is 5cm~15cm.
Above-mentioned concrete-bar straightening-cutting machine stop cable erecting device, is characterized in that: the length of described horizontal case and penetration pipe is identical, and the left end of described horizontal case is mutually concordant with the left end of penetration pipe.
Above-mentioned concrete-bar straightening-cutting machine stop cable erecting device, is characterized in that: described support column is steel pipe or steel reinforcement cage.
The utility model compared with prior art has the following advantages:
1, simple in structure, reasonable in design and processing and fabricating and installation laying convenience.
2, use easy and simple to handle, result of use good and use value is high, the cable that can effectively the solve concrete-bar straightening-cutting machine stop problem that mops floor, and guarantee job site Electrical Safety.
In sum, the utility model is simple in structure, processing and fabricating and easy for installation and use easy and simple to handle, result of use good, the cable that can effectively the solve concrete-bar straightening-cutting machine stop problem that mops floor.
Below by drawings and Examples, the technical solution of the utility model is described in further detail.
Accompanying drawing explanation
Fig. 1 is use state reference map of the present utility model.
Fig. 2 is the local enlarged diagram at A place in Fig. 1.
Description of reference numerals:
1-support column; 2-wire; 3-Suspension;
3-1-horizontal case; 3-2-penetration pipe; 4-cable;
5-concrete-bar straightening-cutting machine; 6-stop.
Embodiment
As shown in Figure 1 and Figure 2, the utility model comprises two support columns 1 and hangs on two suspenders between described support column 1, described suspender is rope or wire 2, described suspender is level and is all not less than 1.2m to laying and its suspension height apart from ground, two described support columns 1 are all vertically to laying, and the two ends, left and right of described suspender are separately fixed on two described support columns 1.On described suspender, be provided with from left to right a plurality of Suspensions that cable 4 is set up 3, the structure of a plurality of described Suspensions 3 is all identical, and described cable 4 is for being connected in the stube cable between the stop 6 of concrete-bar straightening-cutting machine 5 and the control device of concrete-bar straightening-cutting machine 5.The quantity of described Suspension 3 is no less than 3.Described Suspension 3 comprises horizontal case 3-1 and the fastening penetration pipe 3-2 that is fixed on horizontal case 3-1 outside being sleeved on described suspender, and described penetration pipe 3-2 is parallel laying with horizontal case 3-1.Described cable 4 passes in the penetration pipe 3-2 from a plurality of described Suspensions 3 from left to right.Described horizontal case 3-1 and penetration pipe 3-2 are pvc pipe.
In the present embodiment, described penetration pipe 3-2 be laid in horizontal case 3-1 under and the two be laid on same vertical plane.
During actual processing and fabricating, the length of described horizontal case 3-1 and penetration pipe 3-2 is all not more than 20cm.In the present embodiment, the length of described horizontal case 3-1 and penetration pipe 3-2 is 5cm~15cm.Specifically add man-hour, can according to actual needs, the length of horizontal case 3-1 and penetration pipe 3-2 be adjusted accordingly.
The quantity of described Suspension 3 is 5~10.In the present embodiment, the quantity of described Suspension 3 is 8.During actual use, can according to specific needs, the quantity of described Suspension 3 be adjusted accordingly.
In the present embodiment, all penetration pipe 3-2 in a plurality of described Suspensions 3 are all laid on same level line.
In the present embodiment, described horizontal case 3-1 and penetration pipe 3-2 are circular casing.
In the present embodiment, described horizontal case 3-1 is identical with the length of penetration pipe 3-2, and the left end of described horizontal case 3-1 is mutually concordant with the left end of penetration pipe 3-2.
During practice of construction, described support column 1 is steel pipe or steel reinforcement cage.In the present embodiment, described support column 1 is steel reinforcement cage, and described steel reinforcement cage is the job site steel reinforcement cage body that colligation completes.
The above; it is only preferred embodiment of the present utility model; not the utility model is imposed any restrictions; every any simple modification of above embodiment being done according to the utility model technical spirit, change and equivalent structure change, and all still belong in the protection range of technical solutions of the utility model.
Claims (9)
1. a concrete-bar straightening-cutting machine stop cable erecting device, it is characterized in that: comprise two support columns (1) and hang on the suspender between two described support columns (1), described suspender is rope or wire (2), described suspender is level and is all not less than 1.2m to laying and its suspension height apart from ground, two described support columns (1) are all vertically to laying, and the two ends, left and right of described suspender are separately fixed on two described support columns (1); On described suspender, be provided with from left to right a plurality of Suspensions (3) that cable (4) is set up, the structure of a plurality of described Suspensions (3) is all identical, and described cable (4) is for being connected in the stube cable between the stop (6) of concrete-bar straightening-cutting machine (5) and the control device of concrete-bar straightening-cutting machine (5); The quantity of described Suspension (3) is no less than 3; Described Suspension (3) comprises horizontal case (3-1) and the fastening penetration pipe (3-2) that is fixed on horizontal case (3-1) outside being sleeved on described suspender, and described penetration pipe (3-2) is parallel laying with horizontal case (3-1); Described cable (4) passes in the penetration pipe (3-2) from a plurality of described Suspensions (3) from left to right; Described horizontal case (3-1) and penetration pipe (3-2) are pvc pipe.
2. according to concrete-bar straightening-cutting machine stop cable erecting device claimed in claim 1, it is characterized in that: described penetration pipe (3-2) be laid in horizontal case (3-1) under and the two be laid on same vertical plane.
3. according to the concrete-bar straightening-cutting machine stop cable erecting device described in claim 1 or 2, it is characterized in that: the length of described horizontal case (3-1) and penetration pipe (3-2) is all not more than 20cm.
4. according to the concrete-bar straightening-cutting machine stop cable erecting device described in claim 1 or 2, it is characterized in that: the quantity of described Suspension (3) is 5~10.
5. according to concrete-bar straightening-cutting machine stop cable erecting device claimed in claim 2, it is characterized in that: all penetration pipes (3-2) in a plurality of described Suspensions (3) are all laid on same level line.
6. according to the concrete-bar straightening-cutting machine stop cable erecting device described in claim 1 or 2, it is characterized in that: described horizontal case (3-1) and penetration pipe (3-2) are circular casing.
7. according to concrete-bar straightening-cutting machine stop cable erecting device claimed in claim 3, it is characterized in that: the length of described horizontal case (3-1) and penetration pipe (3-2) is 5cm~15cm.
8. according to the concrete-bar straightening-cutting machine stop cable erecting device described in claim 1 or 2, it is characterized in that: described horizontal case (3-1) is identical with the length of penetration pipe (3-2), and the left end of described horizontal case (3-1) is mutually concordant with the left end of penetration pipe (3-2).
9. according to the concrete-bar straightening-cutting machine stop cable erecting device described in claim 1 or 2, it is characterized in that: described support column (1) is steel pipe or steel reinforcement cage.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201320448920.0U CN203445537U (en) | 2013-07-25 | 2013-07-25 | Cable erecting mechanism used for limiting device of steel bar straightening and cutting machine |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201320448920.0U CN203445537U (en) | 2013-07-25 | 2013-07-25 | Cable erecting mechanism used for limiting device of steel bar straightening and cutting machine |
Publications (1)
Publication Number | Publication Date |
---|---|
CN203445537U true CN203445537U (en) | 2014-02-19 |
Family
ID=50096556
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201320448920.0U Expired - Fee Related CN203445537U (en) | 2013-07-25 | 2013-07-25 | Cable erecting mechanism used for limiting device of steel bar straightening and cutting machine |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN203445537U (en) |
-
2013
- 2013-07-25 CN CN201320448920.0U patent/CN203445537U/en not_active Expired - Fee Related
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN204343644U (en) | A kind of Novel hanging basket fastening devices for curtain wall construction | |
CN205029274U (en) | Fixed bolster that faces cable | |
CN204879075U (en) | Installation device of sack tuber pipe | |
CN203445537U (en) | Cable erecting mechanism used for limiting device of steel bar straightening and cutting machine | |
CN211846878U (en) | Split mounting type cage device | |
CN204592562U (en) | A kind of suspention suppot hanger of duct | |
CN204299157U (en) | The mounted lifting device in attached lifting scaffold side | |
CN204266607U (en) | A kind of high-voltage line protective frame | |
CN205472340U (en) | People's passageway on instrument formula tower crane | |
CN203932942U (en) | A kind of drag chain bracket system | |
CN203782575U (en) | Stay cable hanging and tension construction device | |
CN203794430U (en) | Lifting appliance for binding vertical reinforcing steel bars | |
CN203987849U (en) | Lifting column towing chain device | |
CN202519960U (en) | Overhung type scaffold | |
CN204662914U (en) | A kind of scaffold for building | |
CN203555690U (en) | Fence-sitting suspension bracket | |
CN202231397U (en) | Tool type cable mobile hanging bridge | |
CN203976285U (en) | With the matching used allocated radio lifting of two electric poles guide chain | |
CN204139571U (en) | Straddle block formula hitch | |
CN103287721A (en) | Steel tube support | |
CN204624982U (en) | The vertical overhead hoist of a kind of tubing | |
CN204199728U (en) | Highrise building regularization horizontal protective device | |
CN205397923U (en) | Hanging device for construction | |
CN203248839U (en) | Crow bar for direct burial type water pipe abutting connector adjusting | |
CN205189394U (en) | Outer wall operation device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20140219 Termination date: 20170725 |