CN203404908U - Air conditioner system - Google Patents

Air conditioner system Download PDF

Info

Publication number
CN203404908U
CN203404908U CN201320503617.6U CN201320503617U CN203404908U CN 203404908 U CN203404908 U CN 203404908U CN 201320503617 U CN201320503617 U CN 201320503617U CN 203404908 U CN203404908 U CN 203404908U
Authority
CN
China
Prior art keywords
valve
indoor heat
exchanger rig
communicated
heat exchange
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201320503617.6U
Other languages
Chinese (zh)
Inventor
梁永醒
丘永青
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
TCL Air Conditioner Zhongshan Co Ltd
Original Assignee
TCL Air Conditioner Zhongshan Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by TCL Air Conditioner Zhongshan Co Ltd filed Critical TCL Air Conditioner Zhongshan Co Ltd
Priority to CN201320503617.6U priority Critical patent/CN203404908U/en
Application granted granted Critical
Publication of CN203404908U publication Critical patent/CN203404908U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Compression-Type Refrigeration Machines With Reversible Cycles (AREA)

Abstract

The utility model discloses an air conditioner system. The air conditioner system comprises a compressor, a plurality of indoor heat exchange devices and converter valves which correspond to the indoor heat exchange devices one to one, the first end of each converter valve is communicated with a refrigerant outlet of the compressor, the second end of each converter valve is communicated with the first end of the corresponding indoor heat exchange device, the third end of each converter valve is communicated with a refrigerant inlet of the compressor, and the second ends of the indoor heat exchange devices are communicated. The air conditioner system can achieve refrigeration and heating simultaneously; after one indoor heat exchange device in the air conditioner system is switched on in one mode, the other indoor heat exchange devices can be switched on in other modes, and therefore an improvement to the utilization rate of an air-conditioner indoor unit is facilitated.

Description

Air-conditioning system
Technical field
The utility model relates to appliance field, particularly a kind of air-conditioning system.
Background technology
Along with the development of air-conditioning technical, DC frequency converting air-conditioner reaches its maturity technically, has also obtained user's approval on market, has come into gradually huge numbers of families.And in Modern Urban Development, in order to make building attractive in appearance, more and more to the installation restriction of air-conditioning products off-premises station, the installation site of reducing off-premises station is one of them, therefore commercial small central air conditioning direct-current variable-frequency multi-connection air-conditioning products application is more and more wider.
The advantage of direct-current variable-frequency multi-connection air-conditioning is that off-premises station only has the synthetic external system of one or more compression, and electric expansion valve is used in throttling, and two stop valves are installed, and can connect indefinite interior machine, and the quantity of interior machine is relevant to off-premises station ability logarithm, is therefore called multi-joint; Product can be according to the output of the outer frequency-changeable compressors of ability need conditioning chamber such as interior machine start quantity, design temperature, and reach the not comfort level of chummery.
Existing direct-current variable is two-pipe substantially.When many indoor sets are used simultaneously, there will be the problem of two kinds of pattern phases mutual interference.Whether the scheme solving is at present, while setting each indoor set unlatching, first to detect it and occur conflicting with the pattern of the First indoor set of having opened, and if any conflict, indoor set to be opened is placed in to holding state or take heating mode as mode of priority unlatching.When having indoor set first to be opened with heating mode, when looking on the bright side of things refrigeration, dehumidification mode, other indoor sets just do not start, also can only open heating mode or standby, this has had a strong impact on the utilization rate of combined air conditioners indoor set.
Utility model content
Main purpose of the present utility model, for a kind of air-conditioning system is provided, is intended to realize combined air conditioners indoor set and can heats again in refrigeration, thereby improves the utilization rate of indoor apparatus of air conditioner.
To achieve these goals, the utility model proposes a kind of air-conditioning system, this air-conditioning system comprises compressor, a plurality of indoor heat-exchanger rigs, with the converter valve one to one of indoor heat-exchanger rig described in each, described in each, the first end of converter valve and the refrigerant exit of described compressor are communicated with, described in each, the second end of converter valve is communicated with the first end of corresponding indoor heat-exchanger rig, described in each, the 3rd end of converter valve is communicated with the refrigerant entrance of described compressor, and described in each, the second end of indoor heat-exchanger rig is interconnected.
Preferably, also comprise oil eliminator, the refrigerant exit of described compressor is communicated with the first end of converter valve described in each through described oil eliminator, and the oil revolving end of described oil eliminator is communicated with the refrigerant entrance of described compressor.
Preferably, described compressor is frequency-changeable compressor.
Preferably, also comprise and the first check valve one to one of converter valve described in each, described in each, the refrigerant entrance of the first check valve is communicated with the refrigerant exit of described compressor, and described in each, the refrigerant exit of the first check valve is communicated with the first end of corresponding converter valve.
Preferably, also comprise at least one outdoor heat exchange device, with the interchangeable valve one to one of outdoor heat exchange device described in each, described in each, the first end of interchangeable valve and the refrigerant exit of described compressor are communicated with, described in each, the second end of interchangeable valve is communicated with the first end of corresponding outdoor heat exchange device, described in each, the 3rd end of interchangeable valve is communicated with the refrigerant entrance of described compressor, described in each, the second end of outdoor heat exchange device is interconnected, and described in each, the second end of outdoor heat exchange device is all communicated with the second end of indoor heat-exchanger rig described in each.
Preferably, also comprise and the second check valve one to one of interchangeable valve described in each, described in each, the refrigerant entrance of the second check valve is communicated with the refrigerant exit of described compressor, and described in each, the refrigerant exit of the second check valve is communicated with the first end of corresponding interchangeable valve.
Preferably, also comprise and indoor heat-exchanger rig described in each and/or outdoor heat exchange device electric expansion valve one to one described in each, described in each indoor heat-exchanger rig and/or described in each first end of outdoor heat exchange device and one end of corresponding electric expansion valve be communicated with, described in each, the other end of electric expansion valve is interconnected.
Preferably, also comprise controller, described controller and converter valve described in each and/or described in each interchangeable valve be electrically connected to respectively and control converter valve described in each and/or the valve event of interchangeable valve described in each; Described controller is also electrically connected to respectively and controls the valve event of electric expansion valve described in each with electric expansion valve described in each.
Preferably, also comprise the first stop valve, the second stop valve, the 3rd stop valve; One end of described the first stop valve is communicated with the second end of outdoor heat exchange device described in each, and the other end of described the first stop valve is communicated with the second end of indoor heat-exchanger rig described in each; One end of described the second stop valve is communicated with the first end of described compressor, the other end with corresponding described in each first end of the converter valve of indoor heat-exchanger rig be communicated with; One end of described the 3rd stop valve with corresponding described in each the 3rd end of the interchangeable valve of outdoor heat exchange device be communicated with, the other end of described the 3rd stop valve is communicated with the refrigerant entrance of described compressor.
The utility model air-conditioning system is delivered to corresponding indoor heat-exchanger rig by converter valve by the refrigerant of compressor output, now this indoor heat-exchanger rig is done condenser use, heat, and the low temperature liquid refrigerant forming after indoor heat-exchanger rig heat exchange is delivered to other one or more indoor heat-exchanger rig, doing refrigerant to other indoor heat-exchanger rigs uses, now other indoor heat-exchanger rigs are done evaporimeter use, freeze, the refrigerant of finally by the converter valve corresponding with indoor heat-exchanger rig, indoor heat-exchanger rig being discharged is transmitted back to compressor, thereby realized the indoor heat-exchanger rig of a part in interconnective many indoor heat-exchanger rigs when heating, the indoor heat-exchanger rig of a part can also freeze, and then improved the utilization rate of indoor heat-exchanger rig.
Accompanying drawing explanation
Fig. 1 is the structural representation of the utility model air-conditioning system one embodiment;
Fig. 2 is the structural representation of another embodiment of the utility model air-conditioning system.
The realization of the utility model object, functional characteristics and advantage, in connection with embodiment, are described further with reference to accompanying drawing.
The specific embodiment
Should be appreciated that specific embodiment described herein is only in order to explain the utility model, and be not used in restriction the utility model.
The utility model proposes a kind of design philosophy of air-conditioning system, this air-conditioning system comprises compressor, a plurality of indoor heat-exchanger rigs, with the converter valve one to one of indoor heat-exchanger rig described in each, described in each, the first end of converter valve and the refrigerant exit of described compressor are communicated with, described in each, the second end of converter valve is communicated with the first end of corresponding indoor heat-exchanger rig, described in each, the 3rd end of converter valve is communicated with the refrigerant entrance of described compressor, and described in each, the second end of indoor heat-exchanger rig is interconnected.This air-conditioning system is delivered to corresponding indoor heat-exchanger rig by converter valve by the refrigerant of compressor output and heats, the low temperature liquid refrigerant that again this indoor heat-exchanger rig is heated to rear formation is delivered to other indoor heat-exchanger rigs and freezes, thereby realized the indoor heat-exchanger rig of a part in interconnective many indoor heat-exchanger rigs when heating, the indoor heat-exchanger rig of another part can also freeze, and then has improved the utilization rate of indoor heat-exchanger rig.
In order better to illustrate, below in conjunction with Fig. 1, the present embodiment is described in detail the implementation process of the utility model thought.
With reference to Fig. 1, Fig. 1 is the structural representation of the utility model air-conditioning system one embodiment.
The present embodiment be take the first indoor heat-exchanger rig 10 in Fig. 1 and first converter valve 30, the second indoor heat-exchanger rig 20 corresponding with the first indoor heat-exchanger rig 10 and the present embodiment is specifically described as example with the second converter valve 40 corresponding to the second indoor heat-exchanger rig 20.
In the present embodiment, compressor 100 has refrigerant exit A1 and refrigerant entrance A2, the first converter valve 30 and the second converter valve 40 have respectively first end a, the second end b and the 3rd end c, and the first indoor heat-exchanger rig 10 and the second indoor heat-exchanger rig 20 have respectively first end B1 and the second end B2.Wherein, the first indoor heat-exchanger rig 10 and the second indoor heat-exchanger rig 20 are for being arranged on indoor heat-exchanger rig, and this first indoor heat-exchanger rig 10 and the second indoor heat-exchanger rig 20 both can have been made condenser and use, and can make again evaporimeter and use.Should be understood that, the first indoor heat-exchanger rig 10 and the second indoor heat-exchanger rig 20 in the present embodiment also comprise respectively DC fan 200.The first converter valve 30 and the second converter valve 40 are for being provided with the triple valve of electromagnetic valve, when electromagnetic valve is not opened, between the first end a of the first converter valve 30 and the second converter valve 40 and the second end b, be normally closed (closed cut-off) state, between the second end b of the first converter valve 30 and the second converter valve 40 and the 3rd end c for often opening (conducting) state; When electromagnetic valve is opened, between the first end a of the first converter valve 30 and the second converter valve 40 and the second end b, be folding conducting state, between the second end b of the first converter valve 30 and the second converter valve 40 and the 3rd end c, be closed cut-off state.
The air-conditioning system of the present embodiment also exemplifies following a kind of operational mode and illustrates the feasibility that the utility model thought is implemented:
Operation stroke when the air-conditioning system of the present embodiment realizes running refrigerating pattern and heating mode is simultaneously: the refrigerant ejecting from the refrigerant exit A1 of compressor 100 only enters from the first end a of the first converter valve 30, control after the first converter valve 30 conductings, refrigerant flows out from the second end b of the first converter valve 30, and enter from the first end B1 of the first indoor heat-exchanger rig 10, refrigerant goes out from the second end B2 of the first indoor heat-exchanger rig 10 after the first indoor heat-exchanger rig 10 heat exchange; From the first indoor heat-exchanger rig 10 refrigerant out, from the second end B2 of the second indoor heat-exchanger rig 20, enter, after the second indoor heat-exchanger rig 20 heat exchange, refrigerant goes out from the first end B1 of the second heat-exchanger rig 20, then from the second end b of the second converter valve 40, enter, from the 3rd end c of the second converter valve 40, go out, then get back to compressor 100 from the refrigerant entrance A2 of compressor 100.The first indoor heat-exchanger rig 10 is now as condenser operation, and the second heat-exchanger rig 20 is as evaporimeter operation, and when realizing an indoor heat-exchanger rig and freeze, another can heat.The flow direction of its cold-producing medium can simply be expressed as: the refrigerant entrance A2 of the 3rd end c → compressor 100 of the second end b → the second converter valve 40 of indoor heat-exchanger rig 20 → the second converter valve 40 of the indoor heat-exchanger rig 10 → the second of the second end b → the first of first end a → the first converter valve 30 of refrigerant exit A1 → the first converter valve 30 of compressor 100.Should be understood that, the first indoor heat-exchanger rig 10 and the second indoor heat-exchanger rig 20 are just distinguished the difference of two indoor heat-exchanger rigs herein, and not limiting the first indoor heat-exchanger rig 10 can only heat, and the second indoor heat-exchanger rig 20 can only freeze.
Further, with reference to Fig. 1, in order to reduce the lubricating oil of taking out of with the refrigerant of compressor 100 discharges, enter into refrigerant pipe impact refrigeration, heating effect, the air-conditioning system of the present embodiment also comprises oil eliminator 50, the refrigerant exit A1 of described compressor 100 is communicated with the first end a of converter valve described in each through described oil eliminator 50, the oil revolving end D1 of described oil eliminator 50 is communicated with the refrigerant entrance A2 of described compressor 100.The lubricating oil that this oil eliminator 50 is discharged the refrigerant exit A1 from compressor 100 is separated and is transferred out compressor 100 and uses from refrigerant, has not only improved refrigeration, the heating effect of air-conditioning system, also helps cost-saving.
Further, with reference to Fig. 1, in order to improve the control accuracy of refrigerant output, described compressor 100 is frequency-changeable compressor.
Further, with reference to Fig. 1, for the refrigerant of the converter valve that prevents from flowing through is from the second end b of converter valve to the valve leak between first end a and be back to compressor 100, also comprise and the first check valve 300 one to one of converter valve described in each, described in each, the refrigerant entrance of the first check valve 300 and the refrigerant exit A1 of described compressor 100 are communicated with, and described in each, the refrigerant exit of the first check valve 300 is communicated with the first end a of corresponding converter valve.
Further, the air-conditioning system of the present embodiment also comprises at least one outdoor heat exchange device, with the interchangeable valve one to one of outdoor heat exchange device described in each, described in each, the first end of interchangeable valve and the refrigerant exit of described compressor are communicated with, described in each, the second end of interchangeable valve is communicated with the first end of corresponding outdoor heat exchange device, described in each, the 3rd end of interchangeable valve is communicated with the refrigerant entrance of described compressor, described in each, the second end of outdoor heat exchange device is interconnected, and described in each, the second end of outdoor heat exchange device is all communicated with the second end of indoor heat-exchanger rig described in each.
In order better to illustrate, below in conjunction with Fig. 2, the present embodiment is described in detail the implementation process of the present embodiment.
With reference to Fig. 2, Fig. 2 is the structural representation of another embodiment of the utility model air-conditioning system.
The present embodiment is with two outdoor heat exchange devices in Fig. 2, two indoor heat-exchanger rigs describe the present embodiment, particularly, with the first outdoor heat exchange device 60 and the first interchangeable valve 70 corresponding with the first outdoor heat exchange device 60, the second outdoor heat exchange device 80 and the second interchangeable valve 90 corresponding with the second outdoor heat exchange device 80, the first indoor heat-exchanger rig 10 and first converter valve 30 corresponding with the first indoor heat-exchanger rig 10, the second indoor heat-exchanger rig 20 and second converter valve 40 corresponding with the second indoor heat-exchanger rig 20 are specifically described the present embodiment for example.
In the present embodiment, the first outdoor heat exchange device 60 and the second outdoor heat exchange device 80 have respectively first end C1 and the second end C2, the structure of the first interchangeable valve 70 and the second interchangeable valve 90 is the same with the structure of above-mentioned the first converter valve 30, has first end a, the second end b and the 3rd end c.The first outdoor heat exchange device 60 and the second outdoor heat exchange device 80 are for being positioned at outdoor heat-exchanger rig, and this first outdoor heat exchange device 60 and the second outdoor heat exchange device 80 both can have been made condenser and use, and can make again evaporimeter and use.Should be understood that, the first outdoor heat exchange device 60 in the present embodiment with the second outdoor heat exchange device 80 with above-mentioned the first indoor heat-exchanger rig 10 and the same DC fan 200 that also comprises of the second indoor heat-exchanger rig 20.The first interchangeable valve 70 in the present embodiment and the conducting principle of the second interchangeable valve 90 can, with reference to the conducting principle of above-mentioned the first converter valve 30 and the second converter valve 40, repeat no more herein.
The air-conditioning system of the present embodiment exemplifies the feasibility that following operational mode illustrates the present embodiment:
The first outdoor heat exchange device 60 is opened heating mode, operation stroke when the first indoor heat-exchanger rig 10 and the second indoor heat-exchanger rig 20 are all opened refrigeration mode is: the refrigerant ejecting from the refrigerant exit A1 of compressor 100 only enters from the first end a of the first interchangeable valve 70, control after the first interchangeable valve 70 conductings, refrigerant flows out from the second end b of the first interchangeable valve 70, and enter from the first end C1 of the first outdoor heat exchange device 60, refrigerant second end C2 from the first outdoor heat exchange device 60 after the first outdoor heat exchange device 60 heat exchange goes out; From the first outdoor heat exchange device 60 refrigerant out, be divided into two-way: a road is entered from the second end B2 of the first indoor heat-exchanger rig 10, after the first indoor heat-exchanger rig 10 heat exchange, from the first end B1 of the first indoor heat-exchanger rig 20, go out, then from the second end b of the first converter valve 30, enter, from the 3rd end c of the first converter valve 30, go out, then get back to compressor 100 from the refrigerant entrance A2 of compressor 100; Another road is entered from the second end B2 of the second indoor heat-exchanger rig 20, after the second indoor heat-exchanger rig 20 heat exchange, from the first end B1 of the second indoor heat-exchanger rig 20, go out, then from the second end b of the second converter valve 40, enter, from the 3rd end c of the second converter valve 40, go out, then get back to compressor 100 from the refrigerant entrance A2 of compressor 100.The first outdoor heat exchange device 60 now moves as condenser, the first indoor heat-exchanger rig 10 and the second indoor heat-exchanger rig 20 move as evaporimeter, the flow direction of its cold-producing medium can simply be expressed as: the indoor heat-exchanger rig 10 of the second end b → the first outdoor heat exchange device 60 → the first of the interchangeable valve 70 of first end a → the first of the interchangeable valve 70 of refrigerant exit A1 → the first of compressor 100, the second end b of the second indoor heat-exchanger rig 20 → the first converter valve 30, the 3rd end c of the second end b → the first converter valve 30 of the second converter valve 40, the refrigerant entrance A2 of the 3rd end c → compressor 100 of the second converter valve 40.
The first indoor heat-exchanger rig 10 and the second indoor heat-exchanger rig 20 are all opened heating mode, and operation stroke when the first outdoor heat exchange device 60 is opened refrigeration mode is:
The refrigerant ejecting from the refrigerant exit A1 of compressor 100 is divided into two-way: a road is entered from the first end a of the first converter valve 30, control after the first converter valve 30 conductings, refrigerant flows out from the second end b of the first converter valve 30, and enter from the first end B1 of the first indoor heat-exchanger rig 10, refrigerant goes out from the second end B2 of the first indoor heat-exchanger rig 10 after the first indoor heat-exchanger rig 10 heat exchange; Another road is entered from the first end a of the second converter valve 40, control after the second converter valve 40 conductings, refrigerant flows out from the second end b of the second converter valve 40, and enter from the first end B1 of the second indoor heat-exchanger rig 20, refrigerant goes out from the second end B2 of the second indoor heat-exchanger rig 20 after the second indoor heat-exchanger rig 20 heat exchange; From refrigerant out of the first indoor heat-exchanger rig 10 with accumulate a road from the second indoor heat-exchanger rig 20 refrigerant out, and enter from the second end C2 of the first outdoor heat exchange device 60, after the first outdoor heat exchange device 60 refrigeration, from the first end C1 of the first outdoor heat exchange device 60, go out, then from the second end b of the first interchangeable valve 70, enter, from the 3rd end c of the first interchangeable valve 70, go out, then get back to compressor 100 from the refrigerant entrance A2 of compressor 100.The first indoor heat-exchanger rig 10 and the second indoor heat-exchanger rig 20 now move as condenser, the first outdoor heat exchange device 60 moves as evaporimeter, the flow direction of its cold-producing medium can simply be expressed as: from the first end a of refrigerant exit A1 → the first converter valve 30 of compressor 100, the second end b of first end a → the first converter valve 30 of the second converter valve 40, the indoor heat-exchanger rig 10 of the second end b → the first of the second converter valve 40, the refrigerant entrance A2 of the 3rd end c → compressor 100 of the interchangeable valve 70 of the second end b → the first of the interchangeable valve 70 of the second indoor heat-exchanger rig 20 → the first outdoor heat exchange device 60 → the first.
In the air-conditioning system of the present embodiment the first indoor heat-exchanger rig 10 and the second indoor heat-exchanger rig 20 wherein one open refrigeration, open while heating for one, can optionally open as required the first outdoor heat exchange device 60 or the second indoor heat-exchanger rig 80.For example, when the first indoor heat-exchanger rig 10 heats, the second indoor heat-exchanger rig 20 freezes, if during the heating power and be less than the refrigeration work consumption of the second indoor heat-exchanger rig 20 of the first indoor heat-exchanger rig 10, in order to improve refrigeration, the first outdoor heat exchange device 60 or the second indoor heat-exchanger rig 80 can be opened to heating mode, to provide more refrigerant to supply with the second indoor heat-exchanger rig 20, freeze.Wherein, when outdoor heat exchange device is many, the concrete connected mode of each outdoor heat exchange device can be with reference to the first outdoor heat exchange device 60 shown in Fig. 2 and the annexation of the second outdoor heat exchange device 80, and the annexation of the interchangeable valve corresponding with each outdoor heat exchange device equally can be with reference to the annexation with the second interchangeable valve 90 and the first interchangeable valve 70.
Following examples solve and regulate and control to solve the unmatched problem of indoor heat-exchanger rig power by outdoor heat exchange device.
Wherein, with the first indoor heat-exchanger rig 10 operations heat, the second indoor heat-exchanger rig 20 running refrigerating patterns illustrate, when the refrigeration work consumption of the second indoor heat-exchanger rig 20 is greater than the power that the first indoor heat-exchanger rig 10 heats, can select to open the first outdoor heat exchange device 60 or the second outdoor heat exchange device 80 and compensate the required refrigerant of the second indoor heat-exchanger rig 20 refrigeration, its operation stroke is as follows:
The refrigerant ejecting from the refrigerant exit A1 of compressor 100 first enters from the first end a of the first converter valve 30, control after the first converter valve 30 conductings, refrigerant flows out from the second end b of the first converter valve 30, and enter from the first end B1 of the first indoor heat-exchanger rig 10, refrigerant goes out from the second end B2 of the first indoor heat-exchanger rig 10 after the first indoor heat-exchanger rig 10 heat exchange; From the second end B2 of the second indoor heat-exchanger rig 20, enter, after the second indoor heat-exchanger rig 20 heat exchange, refrigerant goes out from the first end B1 of the second indoor heat-exchanger rig 20, then from the second end b of the second converter valve 40, enter, from the 3rd end c of the second converter valve 40, go out, then get back to compressor 100 from the refrigerant entrance A2 of compressor 100.
Now, when if find, the heating capacity of the first indoor heat-exchanger rig 10 can not meet the refrigerating capacity of the second indoor heat-exchanger rig 20, the present embodiment selects to open the first outdoor heat exchange device 60, the refrigerant ejecting from the refrigerant exit A1 of compressor 100 also enters from the first end a of the first interchangeable valve 70, control after the first interchangeable valve 70 conductings, refrigerant flows out from the second end b of the first interchangeable valve 70, and enter from the first end C1 of the first outdoor heat exchange device 60, refrigerant second end C2 from the first outdoor heat exchange device 60 after the first outdoor heat exchange device 60 heat exchange goes out; And flow in the capillary between the second end B2 of the first indoor heat-exchanger rig 10 and the second end B2 of the second indoor heat-exchanger rig 20, and the refrigerant flowing out with the second end B2 from the first indoor heat-exchanger rig 10 mixes, flow in the lump the second indoor heat-exchanger rig 20, for the second indoor heat-exchanger rig 20, freeze.
And when the refrigeration work consumption of the second indoor heat-exchanger rig 20 is less than the power that the first indoor heat-exchanger rig 10 heats, also can select to open the first outdoor heat exchange device 60 or the second outdoor heat exchange device 80, now need to not carry refrigerant to the first outdoor heat exchange device 60 or the second outdoor heat exchange device 80 from compressor 100, only remaining refrigerant (the first indoor heat-exchanger rig 10 heats the unnecessary refrigerant of rear discharge) after the second indoor heat-exchanger rig 20 refrigeration need be back to compressor through the first outdoor heat exchange device 60 or the second outdoor heat exchange device 80.Thereby realized by outdoor heat exchange device and regulated and controled to solve the unmatched problem of indoor heat-exchanger rig power.
When indoor heat-exchanger rig is many, for making full use of the ability of indoor heat-exchanger rig, can not need the regulation and control of outdoor heat exchange device, each indoor heat-exchanger rig of direct regulation and control just can solve the unmatched problem of each indoor heat-exchanger rig power.Three the indoor heat-exchanger rigs of for example take are example, when wherein one open refrigeration, open for one and heat, one when idle, if the indoor heat-exchanger rig power of refrigeration is greater than the power of the indoor heat-exchanger rig heating, can opens idle indoor heat-exchanger rig and carry out balance.
Control when in addition, a certain outdoor heat exchange device need to defrost is as follows:
For example, when opening in advance the first outdoor heat exchange device 60 and providing refrigerant to freeze to the first indoor heat-exchanger rig 10 or the second indoor heat-exchanger rig 20, now, if the second outdoor heat exchange device 80 need to defrost, can close the first outdoor heat exchange device 60, open the second outdoor heat exchange device 80 provides refrigerant to use to the first indoor heat-exchanger rig 10 or the second indoor heat-exchanger rig 20 simultaneously.Particularly, opening in advance the first outdoor heat exchange device 60 provides refrigerant to freeze to the first indoor heat-exchanger rig 10, and the operation stroke when switching to the second outdoor heat exchange device 80 and defrosting is: the refrigerant ejecting from the refrigerant exit A1 of compressor 100 first enters from the first end a of the first converter valve 30, control after the first converter valve 30 conductings, refrigerant flows out from the second end b of the first converter valve 30, and enter from the first end C1 of the first outdoor heat exchange device 60, refrigerant second end C2 from the first outdoor heat exchange device 60 after the first outdoor heat exchange device 60 heat exchange goes out; Then from the second end B2 of the first indoor heat-exchanger rig 10, enter, after the first indoor heat-exchanger rig 10 heat exchange, refrigerant goes out from the first end B1 of the first indoor heat-exchanger rig 10, then from the second end b of the first converter valve 30, enter, from the 3rd end c of the first converter valve 30, go out, then get back to compressor 100 from the refrigerant entrance A2 of compressor 100.
When finding that the second outdoor heat exchange device 60 need to defrost, close the first outdoor heat exchange device 60, open the second outdoor heat exchange device 80 simultaneously and carry out high wind refrigeration, now, the refrigerant ejecting from the refrigerant exit A1 of compressor 100 only enters from the first end a of the second converter valve 30, control after the second converter valve 30 conductings, refrigerant flows out from the second end b of the second converter valve 30, and enter from the first end C1 of the second outdoor heat exchange device 80, refrigerant second end B2 from the second indoor heat-exchanger rig 80 after the second outdoor heat exchange device 80 heat exchange goes out; From the second end B2 from the first indoor heat-exchanger rig 10 then, enter again, for the first indoor heat-exchanger rig 10 refrigeration.Wherein, the second outdoor heat exchange device 80 is meeting heat radiation heat in the process of carrying out sweat cooling, thereby has realized the operation of defrosting.
Below illustrate by way of example that each indoor heat-exchanger rig of each outdoor heat exchange device freezes and the concrete distribution of heating capacity (power) (for example, outdoor heat exchange device is 2,15 every, indoor heat-exchanger rig is 6,5 every, be that outdoor heat exchange device is 30, indoor heat-exchanger rig is also 30):
When indoor heat-exchanger rig have two open heat, four open when refrigeration, according to capacity calculation mode 5*2-5*4=-10,10≤15 and for negative, now need out an outdoor heat exchange device to heat, simultaneously according to the running temperature of the outdoor heat exchange device of opening, regulate the rotating speed of fan to carry out the power match of heat-exchanger rig and outdoor heat exchange device in balance cylinder.
When indoor heat-exchanger rig have three open heat, three open when refrigeration, according to capacity calculation mode 5*3-5*3=0, now do not need out outdoor heat exchange device.If need to outdoor heat exchange device be defrosted, can open that outdoor heat exchange device that needs defrosting, and turn off three and driven the indoor heat-exchanger rig heating.
When indoor heat-exchanger rig have four open heat, two open when refrigeration, according to capacity calculation mode 5*4-5*2=10,10≤15 and for just, now only need to open an outdoor heat exchange device and freeze, according to the running temperature of the outdoor heat exchange device of opening, regulate the rotating speed of fan to carry out the power match of heat-exchanger rig and outdoor heat exchange device in balance cylinder simultaneously.
By above control, not only can economize on resources, there is the situation of phase mutual interference in each pattern that can also prevent each indoor heat-exchanger rig and each outdoor heat exchange device.
Further, with reference to Fig. 2, for the refrigerant of the interchangeable valve that prevents from flowing through is from the second end b of interchangeable valve to the valve leak between first end a and be back to compressor 100, above-mentioned air-conditioning system also comprises and the second check valve 400 one to one of interchangeable valve described in each, described in each, the refrigerant entrance of the second check valve 400 and the refrigerant exit A1 of described compressor 100 are communicated with, and described in each, the refrigerant exit of the second check valve 400 is communicated with the first end a of corresponding interchangeable valve.
Further, with reference to Fig. 1 and Fig. 2, above-mentioned air-conditioning system also comprises and indoor heat-exchanger rig described in each and/or outdoor heat exchange device electric expansion valve 500 one to one described in each, described in each indoor heat-exchanger rig and/or described in each first end of outdoor heat exchange device and one end of corresponding electric expansion valve 500 be communicated with, described in each, the other end of electric expansion valve 500 is interconnected.Electric expansion valve 500 can accurately be controlled cold medium flux, thereby realize, accurately controls evaporating temperature.
Further, with reference to Fig. 1 and Fig. 2, above-mentioned air-conditioning system also comprises controller, described controller and converter valve described in each and/or described in each interchangeable valve be electrically connected to respectively and control converter valve described in each and/or the valve event of interchangeable valve described in each; Described controller is also electrically connected to respectively and controls the valve event of electric expansion valve 500 described in each with electric expansion valve described in each 500.This controller can be single-chip microcomputer, by single-chip microcomputer is programmed, can control converter valve, interchangeable valve and electric expansion valve 500 and carry out relevant work.
Further, with reference to Fig. 2, for convenient, air-conditioning system is debugged and overhauled, the air-conditioning system of the present embodiment also comprises the first stop valve 101, the second stop valve 102, the 3rd stop valve 103; One end of described the first stop valve 101 is communicated with the second end C2 of outdoor heat exchange device described in each, and the other end of described the first stop valve 101 is communicated with the second end C2 of indoor heat-exchanger rig described in each; One end of described the second stop valve 102 is communicated with the first end A1 of described compressor 100, the other end with corresponding described in each first end a of the converter valve of indoor heat-exchanger rig be communicated with; One end of described the 3rd stop valve 103 with corresponding described in each the 3rd end c of the interchangeable valve of outdoor heat exchange device be communicated with, the other end of described the 3rd stop valve 103 is communicated with the refrigerant entrance A2 of described compressor 100.
The foregoing is only preferred embodiment of the present utility model; not thereby limit the scope of the claims of the present utility model; every equivalent structure or conversion of equivalent flow process that utilizes the utility model description and accompanying drawing content to do; or be directly or indirectly used in other relevant technical fields, be all in like manner included in scope of patent protection of the present utility model.

Claims (9)

1. an air-conditioning system, comprise compressor, it is characterized in that, this air-conditioning system also comprises a plurality of indoor heat-exchanger rigs, with the converter valve one to one of indoor heat-exchanger rig described in each, described in each, the first end of converter valve and the refrigerant exit of described compressor are communicated with, described in each, the second end of converter valve is communicated with the first end of corresponding indoor heat-exchanger rig, described in each, the 3rd end of converter valve is communicated with the refrigerant entrance of described compressor, and described in each, the second end of indoor heat-exchanger rig is interconnected.
2. air-conditioning system according to claim 1, it is characterized in that, also comprise oil eliminator, the refrigerant exit of described compressor is communicated with the first end of converter valve described in each through described oil eliminator, and the oil revolving end of described oil eliminator is communicated with the refrigerant entrance of described compressor.
3. air-conditioning system according to claim 2, is characterized in that, described compressor is frequency-changeable compressor.
4. air-conditioning system according to claim 1, it is characterized in that, also comprise and the first check valve one to one of converter valve described in each, described in each, the refrigerant entrance of the first check valve is communicated with the refrigerant exit of described compressor, and described in each, the refrigerant exit of the first check valve is communicated with the first end of corresponding converter valve.
5. air-conditioning system according to claim 1, it is characterized in that, also comprise at least one outdoor heat exchange device, with the interchangeable valve one to one of outdoor heat exchange device described in each, described in each, the first end of interchangeable valve and the refrigerant exit of described compressor are communicated with, described in each, the second end of interchangeable valve is communicated with the first end of corresponding outdoor heat exchange device, described in each, the 3rd end of interchangeable valve is communicated with the refrigerant entrance of described compressor, described in each, the second end of outdoor heat exchange device is interconnected, and described in each, the second end of outdoor heat exchange device is all communicated with the second end of indoor heat-exchanger rig described in each.
6. according to the air-conditioning system described in claim 5, it is characterized in that, also comprise and the second check valve one to one of interchangeable valve described in each, described in each, the refrigerant entrance of the second check valve is communicated with the refrigerant exit of described compressor, and described in each, the refrigerant exit of the second check valve is communicated with the first end of corresponding interchangeable valve.
7. according to the air-conditioning system described in any one in claim 1-6, it is characterized in that, also comprise and indoor heat-exchanger rig described in each and/or outdoor heat exchange device electric expansion valve one to one described in each, described in each indoor heat-exchanger rig and/or described in each first end of outdoor heat exchange device and one end of corresponding electric expansion valve be communicated with, described in each, the other end of electric expansion valve is interconnected.
8. air-conditioning system according to claim 7, is characterized in that, also comprises controller, described controller and converter valve described in each and/or described in each interchangeable valve be electrically connected to respectively and control converter valve described in each and/or the valve event of interchangeable valve described in each; Described controller is also electrically connected to respectively and controls the valve event of electric expansion valve described in each with electric expansion valve described in each.
9. air-conditioning system according to claim 8, is characterized in that, also comprises the first stop valve, the second stop valve, the 3rd stop valve; One end of described the first stop valve is communicated with the second end of outdoor heat exchange device described in each, and the other end of described the first stop valve is communicated with the second end of indoor heat-exchanger rig described in each; One end of described the second stop valve is communicated with the first end of described compressor, the other end with corresponding described in each first end of the converter valve of indoor heat-exchanger rig be communicated with; One end of described the 3rd stop valve with corresponding described in each the 3rd end of the interchangeable valve of outdoor heat exchange device be communicated with, the other end of described the 3rd stop valve is communicated with the refrigerant entrance of described compressor.
CN201320503617.6U 2013-08-16 2013-08-16 Air conditioner system Expired - Fee Related CN203404908U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201320503617.6U CN203404908U (en) 2013-08-16 2013-08-16 Air conditioner system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201320503617.6U CN203404908U (en) 2013-08-16 2013-08-16 Air conditioner system

Publications (1)

Publication Number Publication Date
CN203404908U true CN203404908U (en) 2014-01-22

Family

ID=49940840

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201320503617.6U Expired - Fee Related CN203404908U (en) 2013-08-16 2013-08-16 Air conditioner system

Country Status (1)

Country Link
CN (1) CN203404908U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2016101152A1 (en) * 2014-12-23 2016-06-30 Trane Air Conditioning Systems (China) Co., Ltd. Temperature regulating systems and control methods thereof
CN109340965A (en) * 2018-11-14 2019-02-15 中国铁路设计集团有限公司 A kind of condenser recovery type heat air-cooled fluorine pump machine room Special air-conditioning device

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2016101152A1 (en) * 2014-12-23 2016-06-30 Trane Air Conditioning Systems (China) Co., Ltd. Temperature regulating systems and control methods thereof
CN109340965A (en) * 2018-11-14 2019-02-15 中国铁路设计集团有限公司 A kind of condenser recovery type heat air-cooled fluorine pump machine room Special air-conditioning device

Similar Documents

Publication Publication Date Title
CN102927715B (en) Multiple-on-line heat pump air-conditioning system and method for controlling multiple-on-line heat pump air-conditioning system
CN203533802U (en) Air-conditioning system
CN201306902Y (en) Air conditioner with heat-recovery type heat pump and refrigerator integrated machine
CN106196684B (en) The multi-functional multi-connected air conditioning system of three control of one kind and its control method
CN103225851B (en) A kind of multi-gang air conditioner working in coordination with defrosting
CN104964371B (en) Combined air-conditioning system
CN102734885B (en) Serial air conditioner and temperature regulating box all-in-one machine and operation control method thereof
CN103591732B (en) Air conditioning system
CN105180304B (en) Air-conditioner outdoor unit, multifuctional air conditioning system and its method of work
CN104515217B (en) Energy accumulation air conditioner and control method
CN105135737B (en) Combined air-conditioning system
CN104154673A (en) Refrigeration method and system for three-pipe heat recovery varied refrigerant volume air-conditioning system
CN106595004B (en) air conditioner control method and device and air conditioner
CN106524339A (en) Air conditioning energy saving system and method and air conditioner
CN103225936A (en) Air conditioning system with defrosting device and defrosting method thereof
CN110779233A (en) Air source heat pump air conditioner floor heating hot water unit
CN105258276A (en) Air conditioner system and control method thereof
CN203404908U (en) Air conditioner system
CN204027081U (en) Air-condition heat exchanger, air conditioner heat exchange system and air-conditioner
CN206695426U (en) Air-conditioning system
CN206235054U (en) A kind of multi-functional multi-connected air conditioning system of three control
US20140144176A1 (en) Air Conditioner Exhaust Recycling
CN204254925U (en) Heat-exchange system and there is its air-conditioner
CN202902496U (en) Multiple on-line heat pump air-conditioning system
WO2022183839A1 (en) Easy-to-press multi-purpose cooling/heating machine system

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20140122

Termination date: 20170816