Entry side guide plate for hot continuous rolling finishing mill Download PDF

Info

Publication number
CN203304309U
CN203304309U CN2013203430479U CN201320343047U CN203304309U CN 203304309 U CN203304309 U CN 203304309U CN 2013203430479 U CN2013203430479 U CN 2013203430479U CN 201320343047 U CN201320343047 U CN 201320343047U CN 203304309 U CN203304309 U CN 203304309U
Authority
CN
China
Prior art keywords
guide plate
plate
finishing mill
cooling water
rolling finishing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2013203430479U
Other languages
Chinese (zh)
Inventor
李远东
赵敏
李国全
毛竹
陈宏涛
宋波
刘杰
李红卫
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhan Iron and Steel Co Ltd
Original Assignee
Wuhan Iron and Steel Group Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan Iron and Steel Group Corp filed Critical Wuhan Iron and Steel Group Corp
Priority to CN2013203430479U priority Critical patent/CN203304309U/en
Application granted granted Critical
Publication of CN203304309U publication Critical patent/CN203304309U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Metal Rolling (AREA)

Abstract

The utility model discloses an entry side guide plate for a hot continuous rolling finishing mill. The entry side guide plate comprises a guide plate lining plate and a guide plate transition plate, wherein a guide plate lining plate cooling water pipe with a water spray nozzle is arranged on the upper edge of the guide plate lining plate; a baffle is soldered on the lateral part of the guide plate transition plate. On the one hand, transition beam cooling water cannot be shot to the surface of strip steel when being sputtered by virtue of the baffles which are soldered on lateral parts of the guide plate transition plate at two sides of the entry side of the hot continuous rolling finishing mill, so that a local low-temperature area cannot be formed on the strip steel, and a local high spot cannot be formed after the strip steel is rolled; on the other hand, the sprayed water can be covered on the guide plate lining plate and cannot be bounced to the surface of the strip steel to form local cooling by virtue of the guide plate lining plate cooling water pipe, the guide plate lining plate temperature can be reduced, similar 'friction welding' effect is generated among destructed thermal-state metals, so that tumor generation is reduced, production is effectively performed, and the production cost is saved.

Description

Hot-rolling finishing mill group inlet side-guiding-board
Technical field
The utility model relates to the hot-rolling finishing mill group, relates in particular to a kind of hot-rolling finishing mill group inlet side-guiding-board.
Background technology
Hot-rolling finishing mill group inlet side-guiding-board is the indispensable part of hot-rolling finishing mill group, and it plays and guarantees band steel head threading centering, rectifies a deviation in the operation of rolling, while throwing steel, prevents the effect of whipping, and its importance is self-evident.
There are two defects in the coil of strip that uses existing hot-rolling finishing mill group to produce always, that is: cold rolling stalk seal and foreign matter are rolled into defect.
Cold rolling stalk prints defect, be that the transition beam cooling water bounce-back of hot-rolling finishing mill group is splashed to belt steel surface and easily makes belt steel surface topical hypothermia, after rolling, form local high spot on cross section, be seen as in appearance hot rolling reel length direction bright band, this is in cold rolling stalk seal defect because producing after work hardening later;
Foreign matter is rolled into defect, be that the reason that the guide plate dross produces is that band steel and guide plate come in contact, collide, between thermal state metal, produce the effect of similar " friction welding (FW) ", metal adhesive is on guide plate, and dross easily falls into belt steel surface after producing and is rolled into belt steel surface and forms foreign matter and be rolled into defect.
While producing continuity quality defect, must take quality to shut down, therefore very big to cost impact, and, with the reel of this type of defect, need to after bringing back to life, can give down, lumber recovery, inventory cost and logistics cost are affected greatly.
Summary of the invention
The purpose of this utility model is exactly for above-mentioned defect, and a kind of hot-rolling finishing mill group inlet side-guiding-board is provided, and has overcome cold rolling stalk seal defect of the prior art and foreign matter and has been rolled into defect, has improved finished product rate, has guaranteed the production direct motion.
For achieving the above object, the hot-rolling finishing mill group inlet side-guiding-board that the utility model is designed, comprise guide plate liner plate and guide plate rebound, the Shang Yanchu of described guide plate liner plate is provided with the guide plate liner plate cooling water pipe with water spout, and the sidepiece of described guide plate rebound is welded with baffle plate.
Further, described guide plate liner plate cooling water pipe is fixed on the gland of described guide plate liner plate top.
Further, be provided with a plurality of water spouts on described guide plate liner plate cooling water pipe, water spout passes gland covers on the guide plate liner plate water of water spout ejection.
The utility model has the advantage of: on the one hand by the baffle plate of two flipper guide rebound sidepiece welding at hot-rolling finishing mill group entrance side, while guaranteeing the sputter of transition beam cooling water, can not be bound to belt steel surface, thereby guarantee that the band steel can not form the topical hypothermia district, can not form local high spot after rolling; The Shang Yanchu of guide plate liner plate is provided with the guide plate liner plate cooling water pipe with water spout on the other hand, the water sprayed is covered on the guide plate liner plate but is unlikely to rebound to belt steel surface to form Local cooling, reduce guide plate liner plate temperature, between broken ring thermal state metal, produce the effect of similar " friction welding (FW) ", thereby reduced the dross generation, reduced the flame cutting times, effectively direct motion production, saved production cost; Therefore overcome that cold rolling stalk in existing production technology prints defect and foreign matter is rolled into defect, improved lumber recovery, guaranteed the unobstructed of the continuity of production process and logistics.
The accompanying drawing explanation
Fig. 1 is front view of the present utility model;
Fig. 2 is top view of the present utility model;
Fig. 3 is axonometric drawing of the present utility model.
In figure, each parts label is as follows: guide plate 1, guide plate liner plate 1.1, guide plate rebound 1.2, gland 2, guide plate liner plate cooling water pipe 3, baffle plate 4, transition beam 5, water spout 6.
The specific embodiment
The utility model is described in further detail below in conjunction with the drawings and specific embodiments.
As shown in Figure 1, 2, 3, the guide plate 1 of hot-rolling finishing mill group entrance side comprises the guide plate liner plate 1.2 of vertical direction and the guide plate rebound 1.2 of horizontal direction.
Therefore in order to prevent that transition beam 5 cooling waters are splashed to belt steel surface, the sidepiece at the guide plate rebound 1.2 of both sides respectively is welded with baffle plate 4.By spacing and the scope of calculating the transition beam cooling water, determine the baffle dimensions scope, while guaranteeing the sputter of transition beam cooling water, can not be bound to belt steel surface, guarantee that the band steel can not form the topical hypothermia district, can not form local high spot, thereby improve the quality of product after rolling.
Simultaneously, the Shang Yanchu of guide plate liner plate 1.1 is provided with the guide plate liner plate cooling water pipe 3 with water spout 6, guide plate liner plate cooling water pipe 3 is fixed on the gland 2 of guide plate liner plate 1.1 tops, a plurality of water spouts 6 on guide plate liner plate cooling water pipe 3 pass gland 2 covers on guide plate liner plate 1.1 water of water spout 6 ejections, and by pressure and the angle calculation of cooling water, water spout quantity reasonable in design and water spout model, make the injection water covering of the fan just cover the guide plate liner plate but be unlikely to rebound to belt steel surface and form Local cooling, can reduce like this guide plate liner plate temperature, between broken ring thermal state metal, produce the effect of similar " friction welding (FW) ", thereby reduced the dross generation, reduced the flame cutting times, effectively direct motion production, saved production cost.
It is below the design of concrete finish rolling inlet side-guiding-board
1, as transition beam 5 cooling waters, there are 4,21 group, and the pressure of every water is 5bar, two maximum distance water column length are about 400mm, guide plate rebound 1.2 sidepieces in both sides respectively weld a baffle plate 4, according to this scheme, can effectively stop the transition beam cooling water and not affect the cooling effect of transition beam, can use function normal by assurance equipment.If needing the effective area that cooling water covers is 0.0192 ㎡, can be by the wide 40mm that is designed to of baffle plate, longly be designed to 480mm, therefore, the effective area that covers of cooling water as required, design the size of baffle plate.
While 2, being with at present the steel steady production, by the guide plate aperture, set, band steel and guide plate liner plate are 35mm apart from minimum, suppose to adopt the water of 5bar pressure, should effectively play guide plate liner plate cooling effect and be unlikely to again to make the cooling water belt steel surface that rebounds, according to above-mentioned cooling water pipe pressure, if the area diameter that water spout 6 covers is about 60mm, 22 water spouts 6 need be set on guide plate liner plate cooling water pipe 3, can cover the effective area of above-mentioned guide plate liner plate, number and model that the effective area difference that therefore can cover is as required regulated water spout.On the other hand, do not hamper the operation of band steel in order to make the water spout of transforming, transform along place so be chosen on the guide plate liner plate.

Claims (3)

1. hot-rolling finishing mill group inlet side-guiding-board, comprise guide plate liner plate (1.1) and guide plate rebound (1.2), it is characterized in that: the Shang Yanchu of described guide plate liner plate (1.1) is provided with the guide plate liner plate cooling water pipe (3) with water spout (6), and the sidepiece of described guide plate rebound (1.2) is welded with baffle plate (4).
2. hot-rolling finishing mill group inlet side-guiding-board according to claim 1 is characterized in that: described guide plate liner plate cooling water pipe (3) is fixed on the gland (2) of described guide plate liner plate (1.1) top.
3. hot-rolling finishing mill group inlet side-guiding-board according to claim 1 and 2, it is characterized in that: on described guide plate liner plate cooling water pipe (3), be provided with a plurality of water spouts (6), described water spout (6) passes gland (2), thereby the water of water spout (6) ejection is covered on guide plate liner plate (1.1).
CN2013203430479U 2013-06-17 2013-06-17 Entry side guide plate for hot continuous rolling finishing mill Expired - Fee Related CN203304309U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2013203430479U CN203304309U (en) 2013-06-17 2013-06-17 Entry side guide plate for hot continuous rolling finishing mill

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2013203430479U CN203304309U (en) 2013-06-17 2013-06-17 Entry side guide plate for hot continuous rolling finishing mill

Publications (1)

Publication Number Publication Date
CN203304309U true CN203304309U (en) 2013-11-27

Family

ID=49610544

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2013203430479U Expired - Fee Related CN203304309U (en) 2013-06-17 2013-06-17 Entry side guide plate for hot continuous rolling finishing mill

Country Status (1)

Country Link
CN (1) CN203304309U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109290378A (en) * 2017-07-25 2019-02-01 宝山钢铁股份有限公司 A kind of iron scale dust guiding device

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109290378A (en) * 2017-07-25 2019-02-01 宝山钢铁股份有限公司 A kind of iron scale dust guiding device

Similar Documents

Publication Publication Date Title
CN102430733B (en) Secondary cooling water amplitude-cutting control method of slab continuous casting machine
CN104226689B (en) Roller cooling device and cooling method
CN103831412B (en) Production method for controlling straight crack defect of surface edge of medium-thick plate
CN203304309U (en) Entry side guide plate for hot continuous rolling finishing mill
CN206028337U (en) A export guide fittings for heating up tandem mill
CN102343367B (en) Control method for lowering head and tail undercooled sections of steel plate in pressure jet cooling process
CN102756000A (en) Jet flow cooling method and device in narrow slit water jacket passage of steel plate
CN201020475Y (en) Auxiliary cooling pipe for tandem mill device
CN204182697U (en) A kind of water under high pressure header device
CN108144967A (en) A kind of emulsion spray device for being used to cooling down and lubricating copper wires roll for hot-rolling
CN204503764U (en) Water cooling device for roller
CN206240947U (en) A kind of Strip control cooling super-intensive cooler
JP4420130B2 (en) T-section steel
JP5015034B2 (en) Cooling device and method for hot-rolled steel strip excellent in uniform cooling and plate feed stability
CN108114994B (en) The device and method of iron sheet ash indentation are reduced when a kind of hot tandem production strip
CN202123288U (en) Hot sawing machine with spray system
CN105750333B (en) A kind of cooling device of roll
CN105921535B (en) A kind of Strip control cooling super-intensive cooler
CN204074709U (en) Roll cooling device
CN201664694U (en) Cooling device for rolling ring of high-speed wire rod mill
CN101829680A (en) Method for lubricating and cooling finish rolling side guide plate
CN203916767U (en) There is the coal pulverizer of Comprehensive Preventing mill tube wall
CN203470245U (en) Nozzle with adjustable height
CN204639428U (en) A kind of plumb joint lens protecting device
CN106955983B (en) Device for reducing warping of slab

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20170720

Address after: 430083, Hubei Wuhan Qingshan District Factory No. 2 Gate joint stock company organs

Patentee after: Wuhan iron and Steel Company Limited

Address before: 430080 Wuchang, Hubei Friendship Road, No. A, block, floor 999, 15

Patentee before: Wuhan Iron & Steel (Group) Corp.

TR01 Transfer of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20131127

Termination date: 20200617