CN203238626U - 一种分段配筋的抗拔桩 - Google Patents

一种分段配筋的抗拔桩 Download PDF

Info

Publication number
CN203238626U
CN203238626U CN 201320213115 CN201320213115U CN203238626U CN 203238626 U CN203238626 U CN 203238626U CN 201320213115 CN201320213115 CN 201320213115 CN 201320213115 U CN201320213115 U CN 201320213115U CN 203238626 U CN203238626 U CN 203238626U
Authority
CN
China
Prior art keywords
steel bars
sectionally
segmentation
uplift pile
reinforcing bar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 201320213115
Other languages
English (en)
Inventor
朱心部
黄祥海
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANDONG TONGYUAN DESIGN GROUP CO Ltd
Original Assignee
SHANDONG TONGYUAN DESIGN GROUP CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANDONG TONGYUAN DESIGN GROUP CO Ltd filed Critical SHANDONG TONGYUAN DESIGN GROUP CO Ltd
Priority to CN 201320213115 priority Critical patent/CN203238626U/zh
Application granted granted Critical
Publication of CN203238626U publication Critical patent/CN203238626U/zh
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

本实用新型公开了一种分段配筋的抗拔桩,其内部设有若干根通长钢筋,抗拔桩包括分段配置钢筋的若干段,且从上往下配置的钢筋量根据各分段内桩体的抗拔力进行依次递减。若干段的每一段内设有分段截断的钢筋,通长钢筋与分段截断的钢筋间隔配置。本实用新型的通长钢筋与分段截断的钢筋间隔配置,既保证了抗拔桩承载力及变形,又可节省大量钢筋,施工方便,减少钢筋的绑扎,加快工程进度。

Description

一种分段配筋的抗拔桩
技术领域
本实用新型涉及一种抗拔桩,具体涉及一种分段配筋的抗拔桩。属于建筑工程技术领域。
背景技术
对于地下水位较高的地区,当建筑物的自重及上部结构荷载的总和不能平衡水浮力时,需进行抗浮设计。抗拔桩是众多抗浮措施中的一种重要手段。抗拔桩属于钢筋混凝土轴心受拉构件。由于混凝土的抗拉强度较低,钢筋混凝土构件在拉力作用下易产生裂缝。当地下水对混凝土及混凝土构件中的钢筋有腐蚀性时,抗拔桩需严格控制在水浮力作用下的裂缝,一般要求裂缝宽度不大于0.2mm。为满足控制裂缝的要求,需要在抗拔桩体内配置大量的抗拉钢筋。
目前,抗拔桩内的抗拉钢筋为通长配置。当工程需要的单桩抗拔力较大时,抗拔桩的长度也较长,通常需配置大量的抗拉钢筋,造成数量较多的钢筋布筋困难、施工不便,且不经济。
发明内容
本实用新型的目的是为克服上述现有技术的不足,提供一种分段配筋的抗拔桩。
为实现上述目的,本实用新型采用下述技术方案:
一种分段配筋的抗拔桩,其内部设有若干根通长钢筋,所述抗拔桩包括分段配置钢筋的若干段,且从上往下配置的钢筋量根据各分段桩体的抗拔力依次递减。
所述若干段的每一段内设有分段截断的钢筋,所述通长钢筋与分段截断的钢筋间隔配置。
本实用新型的工作原理:
抗拔桩依靠桩侧与周围土体的摩擦力产生抗拔力,桩体各个截面的抗拔力沿桩长自上而下逐渐减小。因此,综合抗拔桩的长度以及桩侧沿桩长方向与周围土层摩擦力的分布情况,可将抗拔桩分成n段(n为大于等于2的整数)。桩体分段的抗拔力自上而下依次、逐级减小。根据每段桩体的最大抗拔力计算该段桩体所需的配筋量。桩顶段的钢筋为抗拔桩所需的最大配筋量。通长钢筋为抗拔桩分段的最末段(即第n段)所需的钢筋。通长钢筋与分段截断的钢筋间隔配置。需要说明的是,需截断的钢筋应下插到下一段桩体内不小于钢筋的锚固长度方可截断。
本实用新型的有益效果是,通长钢筋与分段截断的钢筋间隔配置,既保证了抗拔桩承载能力及变形,又可节省大量钢筋,施工方便,减少钢筋的绑扎,加快工程进度。
附图说明
图1是本实用新型的结构示意图;
图2是分段I的剖面配筋数量示意图,桩体的最大配筋量,图中钢筋数量仅为示意;
图3是分段II的剖面配筋数量示意图,图中钢筋数量仅为示意;
图4是分段III的剖面配筋数量示意图,图中钢筋数量仅为示意;
图5是分段n的剖面配筋数量示意图,桩体内通长钢筋,图中钢筋数量仅为示意;
其中1.通长钢筋,2.分段截断的钢筋,3.分段截断钢筋下插到下段桩体内钢筋长度,4.分段I,5分段II,6.分段III,7.分段n,8.总桩长。
具体实施方式
下面结合附图和实施例对本实用新型进行进一步的阐述,应该说明的是,下述说明仅是为了解释本实用新型,并不对其内容进行限定。
如图1~5所示,本实用新型是一种分段配筋的抗拔桩,其内部设有若干根通长钢筋1,抗拔桩包括分段配置钢筋的若干段,且从上往下配置的钢筋量根据各分段桩体的抗拔力依次递减。若干段的每一段内设有分段截断的钢筋2,通长钢筋1与分段截断的钢筋2间隔配置。
首先,根据抗拔桩的总桩长8及桩侧沿桩长方向与周围土层摩擦力的分布情况,将抗拔桩分成若干段(n段),如图1所示。然后根据各分段(分段I4,分段II5,分段III6,分段n7最下端桩体的抗拔力计算各分段所需的量,根据此数值配置相应的钢筋。其中分段I4的配筋量为抗拔桩各分段配筋量的最大值;分段n7的配筋量为抗拔桩各分段配筋量的最小值,该分段的配筋为抗拔桩内通长配置的钢筋,即通长钢筋1。中间各段的配筋根据分段配筋量并结合分段I4的配筋及分段n7(即通长钢筋)进行依次、间隔进行截断。每分段内,分段截断的钢筋2下插到下段桩体内钢筋长度3不小于钢筋的锚固长度。
上述虽然结合附图对本实用新型的具体实施方式进行了描述,但并非对本实用新型保护范围的限制,在本实用新型的技术方案的基础上,本领域技术人员不需要付出创造性劳动即可做出的各种修改或变形仍在本实用新型的保护范围以内。

Claims (2)

1.一种分段配筋的抗拔桩,其内部设有若干根通长钢筋,其特征在于,所述抗拔桩包括分段配置钢筋的若干段,且从上往下配置的钢筋量依次递减。
2.根据权利要求1所述的抗拔桩,其特征在于,所述若干段的每一段内设有分段截断的钢筋,所述通长钢筋与分段截断的钢筋间隔配置。
CN 201320213115 2013-04-24 2013-04-24 一种分段配筋的抗拔桩 Expired - Fee Related CN203238626U (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201320213115 CN203238626U (zh) 2013-04-24 2013-04-24 一种分段配筋的抗拔桩

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201320213115 CN203238626U (zh) 2013-04-24 2013-04-24 一种分段配筋的抗拔桩

Publications (1)

Publication Number Publication Date
CN203238626U true CN203238626U (zh) 2013-10-16

Family

ID=49315940

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201320213115 Expired - Fee Related CN203238626U (zh) 2013-04-24 2013-04-24 一种分段配筋的抗拔桩

Country Status (1)

Country Link
CN (1) CN203238626U (zh)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103806441A (zh) * 2014-03-12 2014-05-21 中国建筑西南勘察设计研究院有限公司 一种拉力渐变型抗拔桩
CN109024565A (zh) * 2018-08-07 2018-12-18 浙江海洋大学 一种建筑用混凝土实心桩
CN109437687A (zh) * 2018-11-30 2019-03-08 海南电网有限责任公司电力科学研究院 一种高耐久性轻质抗台风电杆及其制作方法

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103806441A (zh) * 2014-03-12 2014-05-21 中国建筑西南勘察设计研究院有限公司 一种拉力渐变型抗拔桩
CN109024565A (zh) * 2018-08-07 2018-12-18 浙江海洋大学 一种建筑用混凝土实心桩
CN109437687A (zh) * 2018-11-30 2019-03-08 海南电网有限责任公司电力科学研究院 一种高耐久性轻质抗台风电杆及其制作方法

Similar Documents

Publication Publication Date Title
CN203639942U (zh) 拱形挡土墙
CN103046561B (zh) 锚拉排桩锚碇墙复合式支挡结构
CN203238626U (zh) 一种分段配筋的抗拔桩
CN202117068U (zh) 微型桩板式复合基础
CN202830990U (zh) 橡胶止水带固定装置
CN202369931U (zh) 一种拱圈支架
CN102277875A (zh) 桩间复合支护构造
CN204626448U (zh) 一种用于高填方区的型钢混凝土扶壁式挡墙
CN202644525U (zh) 变截面预应力钢筋混凝土管桩
CN202577342U (zh) 一种t型挡土墙结构
CN202000686U (zh) 一种混凝土加固用的组合钢结构
CN203238625U (zh) 一种分段配筋的多节挤扩支盘抗拔桩
CN202298649U (zh) 一种带有纵梁的扶壁结构
CN205259173U (zh) 应用于基坑支护工程的新型抗压基桩
CN204212302U (zh) 一种空心板轻质管抗浮结构
CN204919568U (zh) 浅基坑复合支护结构
CN204662396U (zh) 一种用于高边坡的倾斜式拦污漂结构
CN204898741U (zh) 一种分段配筋的抗拔桩
CN103031841A (zh) 后张预应力矩形空心基坑支护桩
CN103015415B (zh) 后张预应力圆形基坑支护桩
CN204662493U (zh) 一种用于高填方区的钢管混凝土悬臂式挡墙
CN204435209U (zh) 一种混凝土桩支承的半刚接整体式桥台桥梁
CN202500147U (zh) 输电线路扩顶灌注桩基础
CN201762890U (zh) 钢筋混凝土墙体钢筋及模板定位条
CN202866083U (zh) 钢筋混凝土楼板结构

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20131016

Termination date: 20170424