CN203218796U - Operation platform for high-altitude line construction - Google Patents

Operation platform for high-altitude line construction Download PDF

Info

Publication number
CN203218796U
CN203218796U CN 201320114792 CN201320114792U CN203218796U CN 203218796 U CN203218796 U CN 203218796U CN 201320114792 CN201320114792 CN 201320114792 CN 201320114792 U CN201320114792 U CN 201320114792U CN 203218796 U CN203218796 U CN 203218796U
Authority
CN
China
Prior art keywords
guardrail
platform
support guardrail
base platform
hook
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 201320114792
Other languages
Chinese (zh)
Inventor
郑榕
郑依国
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
FUJIAN YONGAN POWER SUPPLY CO LTD
State Grid Fujian Electric Power Co Ltd
Sanming Power Supply Co of State Grid Fujian Electric Power Co Ltd
State Grid Corp of China SGCC
Original Assignee
FUJIAN YONGAN POWER SUPPLY CO LTD
State Grid Fujian Electric Power Co Ltd
Sanming Power Supply Co of State Grid Fujian Electric Power Co Ltd
State Grid Corp of China SGCC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by FUJIAN YONGAN POWER SUPPLY CO LTD, State Grid Fujian Electric Power Co Ltd, Sanming Power Supply Co of State Grid Fujian Electric Power Co Ltd, State Grid Corp of China SGCC filed Critical FUJIAN YONGAN POWER SUPPLY CO LTD
Priority to CN 201320114792 priority Critical patent/CN203218796U/en
Application granted granted Critical
Publication of CN203218796U publication Critical patent/CN203218796U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)

Abstract

本实用新型公开了一种线路高空作业操作平台,包括左支撑护栏、右支撑护栏、后支撑护栏、底座站台、绳索固定环、及挂钩,左、右及后支撑护栏分设于底座站台两侧及后侧,在底座站台上设置有绳索固定环,在后支撑护栏的上方设置有挂钩。本实用新型的线路高空作业操作平台结构简单牢固,取材、制作、使用简便,自重轻、承重力强;不受被操作的导线或瓷瓶串等的影响,在有效提升作业人员安全性的同时,减轻了操作难度和工作强度;极易推广、应用前景广泛。

Figure 201320114792

The utility model discloses a high-altitude operation operation platform for a line, which comprises a left support guardrail, a right support guardrail, a rear support guardrail, a base platform, a rope fixing ring, and a hook. On the rear side, a rope fixing ring is arranged on the base platform, and a hook is arranged on the top of the rear support guardrail. The high-altitude operation operation platform of the utility model has a simple and firm structure, easy material collection, production and use, light weight and strong bearing capacity; it is not affected by the operated wires or porcelain bottle strings, etc., while effectively improving the safety of operators, The operation difficulty and work intensity are reduced; it is very easy to popularize and has wide application prospects.

Figure 201320114792

Description

一种线路高空作业操作平台An operating platform for high-altitude operations

技术领域 technical field

本实用新型涉及一种操作平台,特别是一种线路高空作业操作平台。  The utility model relates to an operation platform, in particular to an operation platform for high-altitude operation of a line. the

背景技术 Background technique

在架空线路架设和更换耐张瓷瓶等作业中,通常使用铝合金平梯作为操作平台。这种操作平台不安全也不利于操作。首先,在线路高空作业中,必须对导线进行收紧作业,一旦出现差错会发生导线脱离横担飞出的危险。导线飞出产生的巨大拉力将使作业人员和平梯与之一同飞出,势必造成伤亡。即便作业人员没有随导线飞出,但此时其已脱离平梯,仅靠双控保险绳保护,一旦双控保险绳出现问题,也将造成伤亡。其次,坐在平梯上操作常使不上劲,增加了作业人员的操作难度和工作强度。  In operations such as erecting overhead lines and replacing strain-resistant porcelain bottles, aluminum alloy flat ladders are usually used as operating platforms. This operating platform is not safe and is not conducive to operation. First of all, in the high-altitude operation of the line, the wire must be tightened. Once an error occurs, there is a danger that the wire will break away from the cross arm and fly out. The huge pulling force generated by the flying wire will cause the operator and the ladder to fly out together with it, which will inevitably cause casualties. Even if the operator does not fly out with the wire, he has left the flat ladder at this time and is only protected by the double-control safety rope. Once the double-control safety rope fails, casualties will also be caused. Secondly, it is often difficult to operate while sitting on a flat ladder, which increases the operational difficulty and work intensity of the operator. the

实用新型内容 Utility model content

本实用新型的目的在于克服现有技术的不足,提供一种能将线路高空作业人员的安全带、双控保险绳和操作平台都挂在固定的构件上,并且能使作业人员如履平地、得心应手进行操作的线路高空作业操作平台。  The purpose of this utility model is to overcome the deficiencies of the prior art, to provide a safety belt, a double-control safety rope and an operating platform that can be hung on the fixed components of the high-altitude workers on the line, and can make the workers feel like walking on the ground, The line aerial work operation platform that is handy to operate. the

一种线路高空作业操作平台,其结构要点在于:包括左支撑护栏、右支撑护栏、后支撑护栏、底座站台、绳索固定环、及挂钩,左、右及后支撑护栏分设于底座站台两侧及后侧,在底座站台上设置有绳索固定环,在后支撑护栏的上方设置有挂钩。  An operating platform for high-altitude operations on a line, the key points of its structure are: it includes a left support guardrail, a right support guardrail, a rear support guardrail, a base platform, a rope fixing ring, and a hook. On the rear side, a rope fixing ring is arranged on the base platform, and a hook is arranged on the top of the rear support guardrail. the

本实用新型的线路高空作业操作平台,在作业时,将线路高空作业操作平台的挂钩挂在横担等固定的构件上,在绳索固定环上,扎一条绳索,拉于地面。在地面的适当位置设置地锚桩,用于固定从绳索固定环引下的绳索并收紧。操作平台挂好后,作业人员下到操作平台中,站在底座站台上,将安全带固定在操作平台上,将双控保险绳挂在固定的构件适当位置处,即可开始作业。  The line high-altitude operation platform of the utility model, when working, the hook of the line high-altitude operation platform is hung on the fixed member such as the cross arm, on the rope fixing ring, tie a rope and pull it on the ground. Ground anchor piles are set at appropriate positions on the ground to fix and tighten the ropes drawn from the rope fixing rings. After the operating platform is hung, the operator goes down to the operating platform, stands on the base platform, fixes the safety belt on the operating platform, hangs the double-control safety rope on the appropriate position of the fixed component, and then starts working. the

所述的左支撑护栏、右支撑护栏为直角三角形。  The left support guardrail and the right support guardrail are right triangles. the

所述的直角三角形较小的夹角在40°-43°之间,立边短,横边长,立边长小于或等于800mm,横边长小于或等于1000mm。  The smaller included angle of the right triangle is between 40°-43°, the vertical side is short, the horizontal side is long, the vertical side length is less than or equal to 800mm, and the horizontal side length is less than or equal to 1000mm. the

综上所述的,本实用新型相比现有技术如下优点:  In summary, the utility model has the following advantages compared with the prior art:

本实用新型的线路高空作业操作平台结构简单牢固,取材、制作、使用简便,自重轻、承重力强;不受被操作的导线或瓷瓶串等的影响,在有效提升作业人员安全性的同时,减轻了操作难度和工作强度;极易推广、应用前景广泛。 The high-altitude operation operation platform of the utility model has a simple and firm structure, easy material collection, production and use, light weight and strong bearing capacity; it is not affected by the operated wires or porcelain bottle strings, etc., while effectively improving the safety of operators, The operation difficulty and work intensity are reduced; it is very easy to popularize and has wide application prospects.

附图说明 Description of drawings

  图1是线路高空作业操作平台结构图。  Figure 1 is a structural diagram of the line aerial work operation platform. the

图2是线路高空作业操作平台现场使用示意图。  Figure 2 is a schematic diagram of on-site use of the line aerial work operation platform. the

标号说明 1左支撑护栏  2右支撑护栏  3后支撑护栏  4底座站台  5挂钩  6绳索固定环 。   Explanation of symbols 1 left support guardrail 2 right support guardrail 3 rear support guardrail 4 base platform 5 hook 6 rope fixing ring . the

具体实施方式 Detailed ways

下面结合实施例对本实用新型进行更详细的描述。  Below in conjunction with embodiment the utility model is described in more detail. the

实施例1  Example 1

一种如图1-2所示的线路高空作业操作平台,包括左支撑护栏1、右支撑护栏2、后支撑护栏3、底座站台4、绳索固定环6、及挂钩5,左、右及后支撑护栏分设于底座站台两侧及后侧,在左支撑护栏、右支撑护栏、后支撑护栏或底座站台上设置有绳索固定环,在后支撑护栏的上方设置有挂钩。所述的左支撑护栏、右支撑护栏为直角三角形。所述的直角三角形较小的夹角在40°-43°之间,立边短,横边长,立边长小于或等于800mm,横边长小于或等于1000mm。所述的绳索固定环设置于底座站台紧邻后支撑栏的中部位置。 A line aerial work operation platform as shown in Figure 1-2, comprising a left support guardrail 1, a right support guardrail 2, a rear support guardrail 3, a base platform 4, a rope fixing ring 6, and a hook 5, left, right and rear The supporting guardrails are located on both sides and the rear side of the base platform. A rope fixing ring is arranged on the left supporting guardrail, the right supporting guardrail, the rear supporting guardrail or the base platform, and a hook is arranged above the rear supporting guardrail. The left support guardrail and the right support guardrail are right triangles. The smaller included angle of the right triangle is between 40°-43°, the vertical side is short, the horizontal side is long, the vertical side length is less than or equal to 800mm, and the horizontal side length is less than or equal to 1000mm. The rope fixing ring is arranged in the middle of the base platform adjacent to the rear support rail.

本实施例未述部分与现有技术相同。  The parts not described in this embodiment are the same as the prior art. the

Claims (3)

1. circuit work high above the ground operating platform, it is characterized in that: comprise that guardrail is supported on left side support guardrail, the right side, the back is supported guardrail, base platform, lanyard ring, reached and link up with, left and right and back is supported guardrail and is divided into base platform both sides and rear side, the base platform is provided with the lanyard ring, is provided with hook above back support guardrail.
2. circuit work high above the ground operating platform according to claim 1 is characterized in that: guardrail is supported on a described left side, right to support guardrail be right-angled triangle.
3. circuit work high above the ground operating platform according to claim 2 is characterized in that: the less angle of described right-angled triangle is between 40 °-43 °, and stile is short, and horizontal edge is long, and stile length is less than or equal to 800mm, and horizontal edge length is less than or equal to 1000mm.
CN 201320114792 2013-03-13 2013-03-13 Operation platform for high-altitude line construction Expired - Fee Related CN203218796U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201320114792 CN203218796U (en) 2013-03-13 2013-03-13 Operation platform for high-altitude line construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201320114792 CN203218796U (en) 2013-03-13 2013-03-13 Operation platform for high-altitude line construction

Publications (1)

Publication Number Publication Date
CN203218796U true CN203218796U (en) 2013-09-25

Family

ID=49208299

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201320114792 Expired - Fee Related CN203218796U (en) 2013-03-13 2013-03-13 Operation platform for high-altitude line construction

Country Status (1)

Country Link
CN (1) CN203218796U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113889916A (en) * 2021-10-15 2022-01-04 广东电网有限责任公司 Multifunctional wire tightening operation platform for distribution line

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113889916A (en) * 2021-10-15 2022-01-04 广东电网有限责任公司 Multifunctional wire tightening operation platform for distribution line

Similar Documents

Publication Publication Date Title
CN203967625U (en) A kind of overhead facility crossing frame
CN205928543U (en) Pole overhauls platform
CN203756015U (en) Aerial work platform for power transmission iron tower
CN202967920U (en) Hanging overhaul device of load switch of transformer
CN202550405U (en) Special ladder for maintenance of strain insulator
CN203598387U (en) Auxiliary device used for aloft work
CN202550348U (en) Folding multifunctional overhauling frame for overhauling isolating switch
CN201918653U (en) Protective bracket for overhaul of high-voltage disconnectors
CN114408817A (en) Protective device for circuit maintenance
CN203626222U (en) A mobile scaffolding safety device
CN204060111U (en) fall arrest device
CN209635851U (en) An arm-type high-altitude lift safety fence
CN206874212U (en) A kind of electrician is with anti-inclination insulating ladder
CN103896153A (en) Zig-zag derrick for replacing disconnecting link
CN206697838U (en) Line maintenance aerial work platform
CN211257762U (en) Safe type large arm installation protection hanging basket device
CN206053825U (en) A kind of upper font combines insulation elevator
CN205077848U (en) A multifunctional building protection net
CN203835250U (en) Safety support for well mouth
CN204609262U (en) Build mobile construction auxiliary device
CN202651689U (en) Optical cable line construction spanning frame
CN203301013U (en) Knife brake and switch maintenance frame
CN203821855U (en) Novel telescopic elevating platform with special steel structural inner barrel
CN202997372U (en) Multipurpose maintenance ladder
CN202957526U (en) Working platform of concrete pole

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20130925