CN203213078U - 一种重力坝与堆石坝复合的坝型 - Google Patents

一种重力坝与堆石坝复合的坝型 Download PDF

Info

Publication number
CN203213078U
CN203213078U CN 201320163982 CN201320163982U CN203213078U CN 203213078 U CN203213078 U CN 203213078U CN 201320163982 CN201320163982 CN 201320163982 CN 201320163982 U CN201320163982 U CN 201320163982U CN 203213078 U CN203213078 U CN 203213078U
Authority
CN
China
Prior art keywords
dam
loose rock
rock
gravity
fill
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN 201320163982
Other languages
English (en)
Inventor
陈海坤
杨家修
魏勇
崔进
李刚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Guiyang Engineering Corp Ltd
Original Assignee
Hydrochina Guiyang Engineering Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hydrochina Guiyang Engineering Corp filed Critical Hydrochina Guiyang Engineering Corp
Priority to CN 201320163982 priority Critical patent/CN203213078U/zh
Application granted granted Critical
Publication of CN203213078U publication Critical patent/CN203213078U/zh
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Revetment (AREA)

Abstract

本实用新型公开了一种重力坝与堆石坝复合的坝型,它包括布置在上游的混凝土重力坝(1)和布置在下游的堆石坝(2),在所述混凝土重力坝(1)和堆石坝(2)之间的接触面上及堆石坝(2)底部设有排水体(3);在所述混凝土重力坝(1)的底部设有防渗体(5),在所述堆石坝(2)的下游坡面设有护坡结构(4)。本实用新型可有效减小坝体断面,与泄水坝段及其它建筑物的连接合理紧凑,减小工程量,减小施工干扰,节省投资及工期。

Description

一种重力坝与堆石坝复合的坝型
技术领域
本实用新型涉及一种重力坝与堆石坝复合的坝型,属于水利水电工程中的大坝技术领域。
背景技术
在水利水电工程中,通常需要拦河筑坝形成水库。大坝主要有混凝土坝及堆石坝等类型,其中堆石坝具有适应基础条件好和就地取材等优点,常用的坝型有心墙堆石坝及混凝土面板堆石坝等,这些坝体上、下游坡比多在1:1.4~1:2.5,坝体断面较大,坝脚也较长。尤其是在软基础闸坝工程(雍水高度一般不超过40m)中,作为与泄水坝段衔接的非溢流坝段时,其上游与泄水坝段衔接上需设置较长的顺河向(纵向)挡墙,下游可结合闸室段及泄洪消能区护岸,亦需设置纵向挡墙。同时,基础防渗体的施工与坝体填筑上往往存在一些干扰。总体而言,堆石坝往往体积较大,其与泄水坝段的连接不紧凑,结构上需增设较长的导墙,防渗体施工和堆石坝填筑有影响,施工组织上有一定的困难和干扰,可能导致工程量大、投资较高。
发明内容
本实用新型的目的是为克服现有堆石坝结构布置及施工组织上的缺陷,提供一种混凝土重力坝与堆石坝复合的混合坝型,该种混合坝型的体型比现有堆石坝小,与泄水坝段及其它建筑物的连接合理紧凑,节约了工程量,减小了投资,并且施工干扰大为减少,亦节省时间。
为实现本实用新型的目的,本实用新型的重力坝与堆石坝复合的坝型,它包括布置在上游的混凝土重力坝和布置在下游的堆石坝,在前述的混凝土重力坝和堆石坝之间的接触面上及堆石坝底部设有排水体;在前述的混凝土重力坝的底部设有防渗体,在前述的堆石坝的下游坡面设有护坡结构。由于这种坝型由两部分挡水结构组成,由混凝土重力坝和防渗体形成防渗体系,可以大大减少堆石坝坝体厚度,与泄水坝段及其它建筑物的连接布置合理紧凑,而且施工时混凝土重力坝可提前实施,在施工期自身保持稳定,可临时挡水度汛,加快施工进度。
进一步的,前述的防渗体设置在前述的混凝土重力坝的底部前缘平台下,并向下嵌入底部基岩内,既保证了防渗效果,又起到坝体防滑的作用,也有利于加快施工进度。
更进一步的,前述的混凝土重力坝的上游坝坡坡比为1:0~1:0.2,下游坝坡坡比为1:0.5~1:0.6,坝体断面较小,节省混凝土量,施工也更快。由于其下游设置有堆石坝,提高了坝体抵抗上游水压力的能力。
更进一步的,前述的堆石坝的下游坝坡坡比为1:2.0~1:2.5。堆石坝的上游紧贴混凝土重力坝,两者接触面上布设排水体,堆石坝的下游坝坡坡比较缓,可以提高坝体稳定性。
与现有技术相比,本实用新型采用混凝土重力坝与后部堆石坝复合而成一种混合坝型,可有效减小坝体断面,与泄水坝段及其它建筑物的连接布置合理紧凑,减小工程量,上游混凝土重力坝部分可提前实施、可临时挡水度汛、防渗体施工与坝体填筑没有影响,从而大为减小施工干扰,节省投资及工期。该种混合坝型经济可行,具有广阔的应用前景。
附图说明  
图1是本实用新型结构示意图;
附图中的标记为:1-混凝土重力坝,2-堆石坝,3-排水体,4-护坡结构,5-防渗体。
具体实施方式
下面结合附图和实施例对本实用新型作进一步的详细说明。
本实用新型重力坝与堆石坝复合的混合坝型如图1所示,它包括混凝土重力坝1、堆石坝2、排水体3、护坡结构4、防渗体5。混凝土重力坝1布置在上游,重力坝1和防渗体5作为混合坝的防渗体系,堆石坝2布置在重力坝1下游,堆石坝2与重力坝1之间的接触面上及堆石坝2底部设有排水体3,堆石坝2的下游坝面布置护坡结构4。
混凝土重力坝1可提前实施,在施工期自身保证稳定,可临时挡水度汛,其上游坝坡1:0~1:0.2,下游坝坡为1:0.5~1:0.6。防渗体5布置在混凝土重力坝1底部前缘平台下,与坝体施工几乎没有影响。混凝土重力坝1与后部堆石坝2之间的接触面上及堆石坝2底部设置排水体3。堆石坝2碾压填筑完成后,与混凝土重力坝1联合挡水。堆石坝2的下游坝坡为1:2.0~1:2.5,其表部布置护坡结构4。
当然,以上只是本实用新型的具体应用范例,本实用新型还有其它的实施方式,凡采用等同替换或等效变换形成的技术方案,均落在本实用新型所要求的保护范围之内。

Claims (4)

1.一种重力坝与堆石坝复合的坝型,其特征在于:它包括布置在上游的混凝土重力坝(1)和布置在下游的堆石坝(2),在所述混凝土重力坝(1)和堆石坝(2)之间的接触面上及堆石坝(2)底部设有排水体(3);在所述混凝土重力坝(1)的底部设有防渗体(5),在所述堆石坝(2)的下游坡面设有护坡结构(4)。
2.根据权利要求1所述的重力坝与堆石坝复合的坝型,其特征在于:所述防渗体(5)设置在所述混凝土重力坝(1)的底部前缘平台下。
3.根据权利要求1所述的重力坝与堆石坝复合的坝型,其特征在于:所述混凝土重力坝(1)的上游坝坡坡比为1:0~1:0.2,下游坝坡坡比为1:0.5~1:0.6。
4.根据权利要求1所述的重力坝与堆石坝复合的坝型,其特征在于:所述堆石坝(2)的下游坝坡坡比为1:2.0~1:2.5。
CN 201320163982 2013-04-03 2013-04-03 一种重力坝与堆石坝复合的坝型 Expired - Lifetime CN203213078U (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201320163982 CN203213078U (zh) 2013-04-03 2013-04-03 一种重力坝与堆石坝复合的坝型

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201320163982 CN203213078U (zh) 2013-04-03 2013-04-03 一种重力坝与堆石坝复合的坝型

Publications (1)

Publication Number Publication Date
CN203213078U true CN203213078U (zh) 2013-09-25

Family

ID=49202626

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201320163982 Expired - Lifetime CN203213078U (zh) 2013-04-03 2013-04-03 一种重力坝与堆石坝复合的坝型

Country Status (1)

Country Link
CN (1) CN203213078U (zh)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105064288A (zh) * 2015-08-04 2015-11-18 中国电建集团华东勘测设计研究院有限公司 一种混凝土坝与土石坝的混合坝型结构及施工方法
CN107178069A (zh) * 2017-06-29 2017-09-19 中国电建集团贵阳勘测设计研究院有限公司 一种混凝土坝与堆石坝的复合坝型结构及其确定方法
CN107687159A (zh) * 2017-08-10 2018-02-13 重庆交通大学 一种拱坝‑重力坝的组合坝型及其建造方法
CN112726521A (zh) * 2020-12-25 2021-04-30 黄河勘测规划设计研究院有限公司 一种免管护加固型淤地坝及其施工方法

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105064288A (zh) * 2015-08-04 2015-11-18 中国电建集团华东勘测设计研究院有限公司 一种混凝土坝与土石坝的混合坝型结构及施工方法
CN107178069A (zh) * 2017-06-29 2017-09-19 中国电建集团贵阳勘测设计研究院有限公司 一种混凝土坝与堆石坝的复合坝型结构及其确定方法
CN107178069B (zh) * 2017-06-29 2019-05-14 中国电建集团贵阳勘测设计研究院有限公司 一种混凝土坝与堆石坝的复合坝型结构及其确定方法
CN107687159A (zh) * 2017-08-10 2018-02-13 重庆交通大学 一种拱坝‑重力坝的组合坝型及其建造方法
CN112726521A (zh) * 2020-12-25 2021-04-30 黄河勘测规划设计研究院有限公司 一种免管护加固型淤地坝及其施工方法

Similar Documents

Publication Publication Date Title
CN204023501U (zh) 一种用于土石坝的除险加固防渗处理结构
CN203213078U (zh) 一种重力坝与堆石坝复合的坝型
CN203222773U (zh) 带种植槽直立式挡墙
CN201778306U (zh) 河岸多级阶梯式增氧消能护坡结构
CN204199246U (zh) 一种碾压堆石混凝土重力坝结构
CN205000309U (zh) 一种适用于低水头溢流坝的过鱼装置
CN205604272U (zh) 一种挡水围堰
CN202450501U (zh) 消力池砖砌排水结构
CN203795388U (zh) 土坝+重力坝混合坝型的布置结构
CN104099909B (zh) 基于泄洪隧洞的泄洪发电同步组合消能工
CN204023523U (zh) 一种坝体内闸阀室结构
CN202730719U (zh) 一种堆石坝量水堰
CN203113359U (zh) 土石围堰结构
CN103938585A (zh) 土坝+重力坝混合坝型的布置结构
CN104695455A (zh) 大流量高水头防冲刷、防渗过水围堰结构及其施工方法
CN204385687U (zh) 无翼墙水闸布置形式
CN105019466A (zh) 一种土石围堰防渗体系的构筑方法及结构
CN212714833U (zh) 一种水闸结构
CN210151667U (zh) 一种用于城市河道的防渗结构
CN210439235U (zh) 一种具备过鱼功能的底格栏栅式小型水坝
CN203729280U (zh) 一种低水头导流洞封堵下闸挡水结构
CN211228408U (zh) 一种景观式溢洪道结构
CN210262945U (zh) 一种胶凝砂砾石支墩坝结构
CN202187356U (zh) 一种装配栅板式护坡结构
CN104047273A (zh) 水电站消能防冲墙及其施工方法

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee

Owner name: CHINA POWER GROUP GUIYANG INVESTIGATION DESIGN + R

Free format text: FORMER NAME: HYDROCHINA GUIYANG ENGINEERING CORPORATION, LTD.

Owner name: HYDROCHINA GUIYANG ENGINEERING CORPORATION, LTD.

Free format text: FORMER NAME: GUIYANG PROSPECTION + DESIGN INST, CHINA HYDRAULIC POWER CONSULTARY GROUP

CP01 Change in the name or title of a patent holder

Address after: 550081 No. 16 Xing Qian Road, Jinyang New District, Guizhou, Guiyang

Patentee after: POWERCHINA GUIYANG ENGINEERING Corp.,Ltd.

Address before: 550081 No. 16 Xing Qian Road, Jinyang New District, Guizhou, Guiyang

Patentee before: HydroChina Guiyang Engineering Corp.

Address after: 550081 No. 16 Xing Qian Road, Jinyang New District, Guizhou, Guiyang

Patentee after: POWERCHINA GUIYANG ENGINEERING CORPORATION LIMITED

Address before: 550081 No. 16 Xing Qian Road, Jinyang New District, Guizhou, Guiyang

Patentee before: POWERCHINA GUIYANG ENGINEERING Corp.,Ltd.

CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20130925