Combustion gas regulator comprehensive performance test device
Technical field
The utility model relates to a kind of test macro, particularly a kind of combustion gas regulator comprehensive performance test device.
Background technology
Gas transmission and distribution system is similar in appearance to the electric power distributing system, all adopt high pressure transmission ﹠ distribution low pressure to use, the top pressure of general long-distance transport pipes can reach 10MPa, and when arriving the terminal that the user uses at last, its pressure probably has only about 2~3kPa, gas transmission and distribution system could satisfy final request for utilization after will reducing pressure step by step through 3~5 grades.Decompression then realizes by pressure regulator.Pressure regulator, quick action emergency valve, superpressure are diffused valve and the equipment such as flange, tensimeter, filtrator, ball valve, butterfly valve of importing and exporting are formed pressure regulating box (cabinet).Combustion gas pressure regulating box (cabinet) is the important component part in the gas transmission and distribution system, little because of its compact conformation, floor area, reduce investment outlay, advantage such as easy to install applied widely.
For pressure regulating box (device), there are disadvantage in traditional, conventional test, detection mode: 1.) the checkout equipment dispersion is various, takes a lot of work inefficiency during test fee; 2.) be subjected to the restriction of human factor, measurement result is rough, poor reliability.3.) can not realize real-time monitoring, the output of data is not clear, convenient etc. yet.
Summary of the invention
The purpose of this utility model provides and a kind ofly can detect various equipment in order, and the testing efficiency height is not subjected to the restriction of human factor, and measurement result is reliable, can realize the combustion gas regulator comprehensive performance test device of the output of monitoring in real time and data.
For overcoming the deficiencies in the prior art, the technical solution of the utility model is: combustion gas regulator comprehensive performance test device, it is characterized in that: comprising: source of the gas, pressure regulator test board, pressure regulating box test board and durable test platform, source of the gas filters the back through filter and is divided into two-way by first threeway, and the first via arrives low temperature resistant tester through by-pass valve, second threeway, first flow meter, the 4th threeway, low temperature resistant test steam supply valve successively; The second the tunnel through pressure valuator, the 3rd threeway, four threeways of the 3rd flowmeter to the, the 4th threeway has temperature transmitter on another siphunculus road, be divided into the two-way branch road by the 5th threeway behind the temperature transmitter, two road branch roads, one tunnel logical pressure regulating box test board, another road leads to the pressure regulator test board.
Described pressure regulator test board and pressure regulating box test board communicate with the pressure regulation export pipeline respectively, shutdown valve, temperature transmitter, pressure unit, pressure regulating box test outlet valve are arranged to outlet on the pressure regulation outlet.
Described pressure regulator test board entrance has the pressure regulator gas admittance valve.
Between described first flow meter pipeline and the 3rd flowmeter and be connected to second flowmeter, there is shutdown valve each flowmeter both sides, each flowmeter range difference.
Temperature transmitter, pressure unit, pressure regulator test outlet valve are arranged on the described pressure regulator test board pipeline.
Form the interface of different tube diameters between described pressure regulating box test board pipeline and the pressure regulation export pipeline.
Another pass-out mouth of described second threeway connects the durable test platform, and the durable test platform connects solenoid valve.Connect durable test platform entrance the durable test gas admittance valve is arranged.
Described pressure regulating box test board connects the pressure regulating box gas admittance valve.
Described solenoid valve, temperature transmitter, pressure unit and each flowmeter are electrically connected with computer monitoring center, be serially connected with between computer monitoring center and the power supply on-the-spot start control by.
The utility model has the advantages that: source of the gas, pressure regulator test board, pressure regulating box test board and durable test platform, source of the gas filters the back through filter and is divided into two-way by first threeway, and the first via arrives low temperature resistant tester through by-pass valve, second threeway, first flow meter, the 4th threeway, low temperature resistant test steam supply valve successively; The second the tunnel through pressure valuator, the 3rd threeway, four threeways of the 3rd flowmeter to the, the 4th threeway has temperature transmitter on another siphunculus road, be divided into the two-way branch road by the 5th threeway behind the temperature transmitter, two road branch roads, one tunnel logical pressure regulating box test board, another road leads to the pressure regulator test board.So just can detect various equipment in order, the testing efficiency height is not subjected to the restriction of human factor, and measurement result is reliable, can realize monitoring in real time, the output of data.
Description of drawings
Fig. 1 is example structure synoptic diagram front view of the present utility model;
Fig. 2 is the vertical view of Fig. 1.
Number in the figure is respectively: 1-filtrator, 2-pressure valuator, 3-by-pass valve, 4-flowmeter, 5-pressure regulating box gas admittance valve, 6-computer monitoring center, 7-durable test gas admittance valve, 8-solenoid valve, 9-temperature transmitter, 10-pressure unit, 11-pressure regulator gas admittance valve, 12-pressure regulator test outlet valve, 13-pressure regulating box test outlet valve, 14-shutdown valve, 15-low temperature resistant tester, 16-on-the-spot control knob, the 17-low temperature resistant test steam supply valve of starting.
Embodiment
Below in conjunction with drawings and Examples the utility model is described in further detail.
As shown in Figure 1 and Figure 2, combustion gas regulator comprehensive performance test device, it is characterized in that: comprising: source of the gas, pressure regulator test board, pressure regulating box test board and durable test platform, source of the gas filters the back through filter 1 and is divided into two-way by first threeway, and the first via arrives low temperature resistant tester 15 through by-pass valve 3, second threeway, first flow meter 4, the 4th threeway, low temperature resistant test steam supply valve 17 successively; The second the tunnel through pressure valuator 2, the 3rd threeway, four threeways of the 3rd flowmeter to the, the 4th threeway has temperature transmitter 9 on another siphunculus road, temperature transmitter 9 backs are divided into the two-way branch road by the 5th threeway, two road branch roads, one tunnel logical pressure regulating box test board, and another road leads to the pressure regulator test board.
Pressure regulator test board and pressure regulating box test board communicate with the pressure regulation export pipeline respectively, shutdown valve 14, temperature transmitter 9, pressure unit 10, pressure regulating box test outlet valve 13 are arranged to outlet on the pressure regulation outlet.
Pressure regulator test board entrance has pressure regulator gas admittance valve 11.
Between first flow meter 4 pipelines and the 3rd flowmeter and be connected to second flowmeter, there is shutdown valve each flowmeter both sides, each flowmeter range difference.
Temperature transmitter 9, pressure unit 10, pressure regulator test outlet valve 12 are arranged on the pressure regulator test board pipeline.
Form the interface of different tube diameters between pressure regulating box test board pipeline and the pressure regulation export pipeline.
Another pass-out mouth of second threeway connects the durable test platform, and the durable test platform connects solenoid valve 8.Connect durable test platform entrance durable test gas admittance valve 7 is arranged.
The pressure regulating box test board connects pressure regulating box gas admittance valve 5.
Solenoid valve 8, temperature transmitter 9, pressure unit 10 and each flowmeter are electrically connected with computer monitoring center 6, are serially connected with the on-the-spot control knob 16 that starts between computer monitoring center 6 and the power supply.
The pressure feed system at first connects source of the gas, and by-pass valve 3 is in closed condition.From import inflation pressurization, by pressure valuator 2 pressure is set to required test pressure, open computer monitoring center, system enters test mode.
Pressure regulator durable test: the pressure regulator of setup test is connected between durable test gas admittance valve 7 and the durable test platform, open durable test gas admittance valve 7, start the durable test solenoid valve, pressure regulator is just under the control of chronotron, solenoid valve does not stop opening and closing, thereby realizes the long duration test of pressure regulator epithelium.
Pressure regulator static characteristic test: the pressure regulator of setup test is connected between pressure regulator gas admittance valve 11 and the pressure regulator test board, turn-on flow rate meter 4 front and back valves, open pressure regulator gas admittance valve 11, set test voltage regulator operation pressure, open shutdown valve 14 and pressure regulating box test outlet valve 13, manually boot field control button 16.Slowly at the uniform velocity open pressure regulator test outlet valve 12, slowly at the uniform velocity close then, stop field control button 16 at last.Computing machine is collected all data by pressure unit 10, temperature transmitter 9 and flowmeter 4, and is depicted as flow curve figure and test report, printout.
Pressure regulating box static characteristic test: the pressure regulating box of setup test is connected on the pressure regulating box test board at corresponding center, turn-on flow rate meter 4 front and back valves, open pressure regulating box gas admittance valve 5, set test pressure regulating box working pressure, close shutdown valve 14 and pressure regulating box test outlet valve 13, manually boot field control button 16.Slowly at the uniform velocity open pressure regulating box test outlet valve 13, slowly at the uniform velocity close then, stop field control button 16 at last.Computing machine is collected all data by pressure unit 10, temperature transmitter 9 and flowmeter 4, and is depicted as flow curve figure and test report, printout.The low temperature resistant test of pressure regulator: with the regulator of setup test, place in the cryogenic box, the equipment air inlet is connected to low temperature resistant test steam supply valve 17 and opens, adjust the pressure regulator top hole pressure and record the closing presure value, close the low temperature chamber door, set temperature drop to-20 ℃, and keep 1h, record pressure regulator closing presure value, the relatively change value of pressure before and after the temperature difference.
The parts that present embodiment is not described in detail and structure belong to well-known components and common structure or the conventional means of the industry, here not narration one by one.