The utility model content
The purpose of this utility model is at above-mentioned situation, provides the following 32.5m wind of a kind of height above sea level 5500m district 220kV transmission line of electricity list to return anchor support.
The purpose of this utility model realizes by following technical proposals:
The following 32.5m wind of a kind of height above sea level 5500m district 220kV transmission line of electricity list returns anchor support, comprise tower leg, body of the tower and tower head, described body of the tower is for once becoming sloping body of the tower, tower head is made of ground line bracket, lead cross-arm and jumper wire rack, described tower head pattern is " doing font ", described ground line bracket adopts the independent cantilevered triangular structure, the polygon leg cross-arm is triangle cross-arm pattern, middle phase conductor directly is hung on the middle wire insulation substring hanging point of body of the tower, rounded projections arranged between lead, the direct cantilever of described jumper wire rack is on the ground line bracket, and the leg that connects of described body of the tower is unshared leg.
As optimal way, the tower leg height B 1 of described anchor support is 9000mm, the lead cross-arm is 1500mm to the height B 2 of knick point, exhaling high B is 30000mm, tower head height C is 13000mm, lead cross-arm bottom is 7500mm to the height C1 of middle wire insulation substring hanging point, middle wire insulation substring hanging point is 5500mm to the height C2 of cat head, it is 8840mm that positive full root is opened A1, once becomes the wide A2 of groove and is 3140mm, and interior angle side ground wire stent length C3 is 5400mm, exterior angle side ground wire stent length C4 is 8400mm, exterior angle side lead cross-arm length C 5 is 7300mm, and interior angle side lead cross-arm length C 6 is 7300mm, and lead cross-arm hanging point space D is 460mm.
As optimal way, the tower leg height B 1 of described anchor support is 10000mm, the lead cross-arm is 1800mm to the height B 2 of knick point, exhaling high B is 30000mm, tower head height C is 13000mm, lead cross-arm bottom is 7500mm to the height C1 of middle wire insulation substring hanging point, middle wire insulation substring hanging point is 5500mm to the height C2 of cat head, it is 9544mm that positive full root is opened A1, once becomes the wide A2 of groove and is 3340mm, and interior angle side ground wire stent length C3 is 6200mm, exterior angle side ground wire stent length C4 is 8900mm, exterior angle side lead cross-arm length C 5 is 8100mm, and interior angle side lead cross-arm length C 6 is 7300mm, and lead cross-arm hanging point space D is 480mm.
As optimal way, the tower leg height B 1 of described anchor support is 10000mm, the lead cross-arm is 1800mm to the height B 2 of knick point, exhaling high B is 30000mm, tower head height C is 13000mm, lead cross-arm bottom is 7500mm to the height C1 of middle wire insulation substring hanging point, middle wire insulation substring hanging point is 5500mm to the height C2 of cat head, it is 10308mm that positive full root is opened A1, once becomes the wide A2 of groove and is 3540mm, and interior angle side ground wire stent length C3 is 7000mm, exterior angle side ground wire stent length C4 is 8900mm, exterior angle side lead cross-arm length C 5 is 8900mm, and interior angle side lead cross-arm length C 6 is 7300mm, and lead cross-arm hanging point space D is 520mm.
As optimal way, the tower leg height B 1 of described anchor support is 10000mm, the lead cross-arm is 1800mm to the height B 2 of knick point, exhaling high B is 30000mm, tower head height C is 13200mm, lead cross-arm bottom is 7700mm to the height C1 of middle wire insulation substring hanging point, middle wire insulation substring hanging point is 5500mm to the height C2 of cat head, it is 9544mm that positive full root is opened A1, once becomes the wide A2 of groove and is 3340mm, and interior angle side ground wire stent length C3 is 5900mm, exterior angle side ground wire stent length C4 is 8900mm, exterior angle side lead cross-arm length C 5 is 7800mm, and interior angle side lead cross-arm length C 6 is 7400mm, and lead cross-arm hanging point space D is 470mm.
As optimal way, described tower leg is unshared leg, namely only limits the height of one leg, and all the other tower leg height are adjusted according to the landform needs.
As optimal way, described anchor support adopts equal leg angle to build, and described equal leg angle connects by bolt each other.
The beneficial effects of the utility model are as follows:
1 arrangements of conductors mode: the mode of rounded projections arranged, good looking appearance not only, and make iron tower stressed evenly.Therefore, single time anchor support of 220kV, lead should adopt rounded projections arranged.Middle phase conductor directly is hung on body of the tower, has avoided its unbalanced tensile force to the moment of torsion that body of the tower produces, and has reduced tower weight.Clearly, the anchor support lead adopts the rounded projections arranged mode to have tangible economic advantages.
2 tower head patterns: the tower head pattern is " doing font ", and profile is light and handy, and power transmission is clear; The node requirement on machining accuracy is lower, easy for installation.
3 cross-arm patterns: the polygon leg cross-arm is triangle cross-arm pattern, and power transmission is clear, and node processing is simple, the requirement of very practical and 220kV conductor load.
4 ground wire support patterns: the ground line bracket is the triangular supports pattern, and simple structure satisfies the requirement of 220kV ground line load simultaneously fully.
5 jumper wire rack patterns: cantilever with ground wire common land line bracket, has been avoided increasing because of the tower weight that structure requires to produce on the ground line bracket, can effectively control the tower head height again.
6 bodies of the tower connect leg: all connect leg and all adopt unshared leg, make the unequal leg of iron tower more can satisfy the landform requirement in the precipitous mountain area of periphery, Lhasa, reduce engineering evolution amount, satisfy the requirement that environmental protection water in Tibet region is protected.
7 rational size design make the anchor support can normal operation under the special environment in Tibet region, neither produce the danger of discharge, control cost to greatest extent again, satisfy special applications requirement under 32.5m/s wind district and complicated weather and orographic condition simultaneously.
The specific embodiment
Below in conjunction with specific embodiments and the drawings the utility model is further described.
As shown in Figure 1, the following 32.5m wind of a kind of height above sea level 5500m district 220kV transmission line of electricity list returns anchor support, comprise tower leg 1, body of the tower 2 and tower head 3, described body of the tower 2 is for once becoming sloping body of the tower, tower head is by ground line bracket 32, lead cross-arm 31 and jumper wire rack 33 constitute, described tower head pattern is " doing font ", described ground line bracket adopts the independent cantilevered triangular structure, the polygon leg cross-arm is triangle cross-arm pattern, middle phase conductor directly is hung on the middle wire insulation substring hanging point 4 of body of the tower, rounded projections arranged between lead, the direct cantilever of described jumper wire rack are on the ground line bracket, and the leg that connects of described body of the tower is unshared leg.
The variation of size can have following several scheme:
Scheme one: the tower leg height B 1 of described anchor support is 9000mm, the lead cross-arm is 1500mm to the height B 2 of knick point, exhaling high B is 30000mm, tower head height C is 13000mm, lead cross-arm bottom is 7500mm to the height C1 of middle wire insulation substring hanging point, middle wire insulation substring hanging point is 5500mm to the height C2 of cat head, it is 8840mm that positive full root is opened A1, once become the wide A2 of groove and be 3140mm, interior angle side ground wire stent length C3 is 5400mm, and exterior angle side ground wire stent length C4 is 8400mm, and exterior angle side lead cross-arm length C 5 is 7300mm, interior angle side lead cross-arm length C 6 is 7300mm, and lead cross-arm hanging point space D is 460mm.
Scheme two: the tower leg height B 1 of described anchor support is 10000mm, the lead cross-arm is 1800mm to the height B 2 of knick point 5, exhaling high B is 30000mm, tower head height C is 13000mm, lead cross-arm bottom is 7500mm to the height C1 of middle wire insulation substring hanging point 4, middle wire insulation substring hanging point 4 is 5500mm to the height C2 of cat head, it is 9544mm that positive full root is opened A1, once become the wide A2 of groove and be 3340mm, interior angle side ground wire stent length C3 is 6200mm, and exterior angle side ground wire stent length C4 is 8900mm, and exterior angle side lead cross-arm length C 5 is 8100mm, interior angle side lead cross-arm length C 6 is 7300mm, and lead cross-arm hanging point space D is 480mm.
Scheme three: the tower leg height B 1 of described anchor support is 10000mm, the lead cross-arm is 1800mm to the height B 2 of knick point 5, exhaling high B is 30000mm, tower head height C is 13000mm, lead cross-arm bottom is 7500mm to the height C1 of middle wire insulation substring hanging point 4, middle wire insulation substring hanging point 4 is 5500mm to the height C2 of cat head, it is 10308mm that positive full root is opened A1, once become the wide A2 of groove and be 3540mm, interior angle side ground wire stent length C3 is 7000mm, and exterior angle side ground wire stent length C4 is 8900mm, and exterior angle side lead cross-arm length C 5 is 8900mm, interior angle side lead cross-arm length C 6 is 7300mm, and lead cross-arm hanging point space D is 520mm.
Scheme four: the tower leg height B 1 of described anchor support is 10000mm, the lead cross-arm is 1800mm to the height B 2 of knick point 5, exhaling high B is 30000mm, tower head height C is 13200mm, lead cross-arm bottom is 7700mm to the height C1 of middle wire insulation substring hanging point 4, middle wire insulation substring hanging point 4 is 5500mm to the height C2 of cat head, it is 9544mm that positive full root is opened A1, once become the wide A2 of groove and be 3340mm, interior angle side ground wire stent length C3 is 5900mm, and exterior angle side ground wire stent length C4 is 8900mm, and exterior angle side lead cross-arm length C 5 is 7800mm, interior angle side lead cross-arm length C 6 is 7400mm, and lead cross-arm hanging point space D is 470mm.
Described tower leg is unshared leg, namely only limits the height of one leg, and all the other tower leg height are adjusted according to the landform needs.
Described anchor support adopts equal leg angle to build, and described equal leg angle connects by bolt each other.
The above only is preferred embodiment of the present utility model; not in order to limit the utility model; all any modifications of within spirit of the present utility model and principle, doing, be equal to and replace and improvement etc., all should be included within the protection domain of the present utility model.