CN203119358U - Bell jar type transformer lifting device - Google Patents

Bell jar type transformer lifting device Download PDF

Info

Publication number
CN203119358U
CN203119358U CN 201320057498 CN201320057498U CN203119358U CN 203119358 U CN203119358 U CN 203119358U CN 201320057498 CN201320057498 CN 201320057498 CN 201320057498 U CN201320057498 U CN 201320057498U CN 203119358 U CN203119358 U CN 203119358U
Authority
CN
China
Prior art keywords
transformer
lifting device
load voltage
type transformer
bell jar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN 201320057498
Other languages
Chinese (zh)
Inventor
王强
陈勇强
孙学锋
高鹏
孙胜涛
王世儒
王卫东
耿垒
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Zibo Power Supply Co of State Grid Shandong Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Zibo Power Supply Co of State Grid Shandong Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Zibo Power Supply Co of State Grid Shandong Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN 201320057498 priority Critical patent/CN203119358U/en
Application granted granted Critical
Publication of CN203119358U publication Critical patent/CN203119358U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Housings And Mounting Of Transformers (AREA)

Abstract

The utility model relates to a bell jar type transformer lifting device, and belongs to the field of electric power construction. The lifting device comprises a transformer, two sides of a top end of an oil tank of a transformer on-load voltage regulation switch are provided with mounting flanges, and gaps are arranged between the mounting flanges and a top of a transformer housing. The bell jar type transformer lifting device overcomes drawbacks of the prior art, and is used for shortening the construction period of replacing the on-load voltage regulation switch and improving replacement efficiency.

Description

Bell-jar transformer lifting device
Technical field
The utility model relates to a kind of bell-jar transformer lifting device, belongs to the power construction field.
Background technology
Along with the fast development of electrical network, higher to the operational reliability requirement of transformer.Move transformer more than 15 years in the transformer station, its on-load voltage regulating switch pressure regulation time number average is more than 20000 times, and reasons such as dynamic and static contact burning and mechanical part wearing and tearing cause ratio of defects to improve year by year, influence the transformer safe and reliable operation.Add the homemade on-load voltage regulating switch manufacturing process in top, the parts quality problems can't reach its designed life.This will badly influence the reliability service of transformer.Now the replacing on-load voltage regulation technology of Zhi Hanging is to carry out when the transformer overhaul, and long in time limit, workload is big.The higher area of air-borne dust content threatens to long-time exposed transformer core and coil cleanliness factor, influences the operational reliability of transformer.How to change on-load voltage regulating switch fast and be the difficult problem that present power construction system runs into.
The utility model content
According to above deficiency of the prior art, the technical problems to be solved in the utility model is: a kind of bell-jar transformer lifting device that can overcome above-mentioned defective is provided, is used for shortening the construction period of changing on-load voltage regulating switch.
The lifting device that the utility model provides comprises transformer, and there is mounting flange the both sides on the fuel tank top of on-load tap-changer of transformer, and the space is arranged at mounting flange and transformer case top.
The outer casing underpart of described transformer has manhole.
Described on-load tap-changer of transformer is sleeved in the protective jacket, and the bore of described protective jacket is stretched out by the gap at mounting flange and transformer case top.
Bell-jar transformer lifting device provided by the utility model is rationally effective, does not need 220kV or 110kV power transformer carried out large repairs to hang cover work, can finish the bell-jar on-load voltage regulating switch and remove, and new case top formula on-load voltage regulating switch is installed.Present technique is optimized 15 original standard operation flow processs to simplify 6 flow processs.Use this technology, the duration that can change on-load voltage regulating switch shortens 60%, and takies situation the same period that significantly reduces personnel, reduces special vehicle and uses, and reduces the use of all kinds of goods and materials in a large number, and financial resources use manpower and material resources sparingly.Reduce the transformer body exposed time at the scene, and transformer is moved in advance, improved electric network reliability.This replacing technology is to guarantee that no metal dust enters under the prerequisite of transformer inside, use specific purpose tool to separate the on-load voltage regulating switch mounting flange bigger than transformer tank top flange port diameter, make it less than the top flange mouth, the mode that tap changer is hung out with crane is finished the dismounting of bell-jar on-load voltage regulating switch then, installs the case top formula on-load voltage regulating switch that new employing does not have the mounting flange design then.
Description of drawings
Fig. 1 is the utility model structural representation;
Among the figure: 1, on-load voltage regulating switch; 2, mounting flange; 3, transformer case; 4, space; 5,
Protective jacket; 6, manhole.
Embodiment
Below in conjunction with accompanying drawing embodiment of the present utility model is described further:
Specific embodiment:
At first to the power transformer processing of draining the oil, open manhole then, transformer inside is ventilated.After meeting condition of work, the staff enters transformer inside by manhole, behind dismounting on-load voltage regulating switch lead-in wire and the top cover, flange separate, dedicated protective jacket is sent into from manhole, be inserted in from the bottom with Switch main body integral body, the bore place of protective jacket is stretched out by transformer tank top flange port.Used singly to advance the formula cast-cutting saw mounting flange of bell-jar on-load voltage regulating switch is separated by the staff then, by crane its integral body is hung out then.New case top formula is installed then to be had at tap changer.After installment work is finished, transformer is carried out vacuum oil, work such as venting.After high voltage test was qualified, transformer resumed operation.
Effect:
By to two 110kV transformers, the replacing of three 220kV on-loads tap-changer of transformer, new technology is quoted well.Transformer after the replacing is stable.New technology is simple to operate, workload reduces, realize that first transformer does not fall cover and changes more changing jobs of bell-jar on-load voltage regulating switch, initiative adopts patterning method to carry out more changing jobs of on-load voltage regulating switch at home, finishes more the changing jobs of on-load voltage regulating switch of power transformer first in 5 days.
Project name Standard operation The new technology actual value
The operation duration 14 days 5 days
Personnel attrition 15 people 6 people
Resource consumption 160 kinds 37 kinds
Energy resource consumption 6 3
The effect contrast table
Performance analysis:
Though enforcement complexity, technical equipment, level of skill are had relatively high expectations, The application of new technique can be changed on-load voltage regulating switch work for the transformer of a 220kV save 2,260,000 yuan.New technology has reduced resources consumption, energy resource consumption, manually expended and has significantly improved operating speed.My company has employed new technology comprehensively and has carried out operation at present.
Figure BDA00002803121600031
Bell-jar transformer lifting device as shown in Figure 1 comprises transformer, and there is mounting flange 2 both sides on the fuel tank top of on-load tap-changer of transformer 1, and mounting flange 2 has space 4 with transformer case 3 tops.Transformer case 3 bottoms have manhole 6.
On-load tap-changer of transformer 1 is sleeved in the protective jacket 5, and the bore of protective jacket 5 is stretched out by 4 places, space at mounting flange 2 and transformer case 3 tops.
By protective jacket reasonably is set, and for protective jacket 5 provides the installation site, during use mounting flange 2 excision backs just can conveniently be hung out on-load voltage regulating switch 1 by lifting protective jacket 5, be convenient for changing, keep in repair, increase work efficiency.

Claims (3)

1.一种钟罩式变压器提升装置,包括变压器,其特征是,所述的变压器有载调压开关的油箱顶端的两侧有安装法兰,安装法兰与变压器外壳顶部有空隙。1. A bell type transformer hoisting device, comprising a transformer, is characterized in that, there are mounting flanges on both sides of the oil tank top of the transformer on-load tap changer, and there is a gap between the mounting flange and the top of the transformer shell. 2.根据权利要求1所述的钟罩式变压器提升装置,其特征是,所述的变压器的外壳下部开有人孔。2. The bell type transformer lifting device according to claim 1, characterized in that, a manhole is opened in the lower part of the casing of the transformer. 3.根据权利要求1所述的钟罩式变压器提升装置,其特征是,所述的变压器有载调压开关套装在防护套内,所述的防护套的口径由安装法兰和变压器外壳顶部的空隙处伸出。3. The bell-type transformer lifting device according to claim 1, characterized in that, the transformer on-load tap changer is set in a protective cover, and the diameter of the protective cover is determined by the mounting flange and the top of the transformer shell. protrude from the gap.
CN 201320057498 2013-01-31 2013-01-31 Bell jar type transformer lifting device Expired - Lifetime CN203119358U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201320057498 CN203119358U (en) 2013-01-31 2013-01-31 Bell jar type transformer lifting device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201320057498 CN203119358U (en) 2013-01-31 2013-01-31 Bell jar type transformer lifting device

Publications (1)

Publication Number Publication Date
CN203119358U true CN203119358U (en) 2013-08-07

Family

ID=48899676

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201320057498 Expired - Lifetime CN203119358U (en) 2013-01-31 2013-01-31 Bell jar type transformer lifting device

Country Status (1)

Country Link
CN (1) CN203119358U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103066514A (en) * 2013-01-31 2013-04-24 山东电力集团公司淄博供电公司 Method and device for lifting immersion bell type transformer

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103066514A (en) * 2013-01-31 2013-04-24 山东电力集团公司淄博供电公司 Method and device for lifting immersion bell type transformer
CN103066514B (en) * 2013-01-31 2016-08-24 国网山东省电力公司淄博供电公司 Bell-jar transformer method for improving and lifting device

Similar Documents

Publication Publication Date Title
CN203119358U (en) Bell jar type transformer lifting device
CN103996985A (en) Method for overhauling oil leakage existing on middle portion and lower portion of large transformer by means of pressure intensity balance
CN204447598U (en) A kind of filter core fixed mechanism of vertical filter
CN204242797U (en) An on-load capacity regulating power transformer
CN204189707U (en) A kind of new type of relay
CN103066514B (en) Bell-jar transformer method for improving and lifting device
CN106989960A (en) A kind of transformer insulation oil sampling apparatus
CN203491044U (en) Dry-type electric transformer
CN203426998U (en) Novel safety tool storage case
CN212485065U (en) Intelligent protection device for dry-type transformer
CN204170528U (en) A kind of industrial waste-gas purifier
CN212934358U (en) Photovoltaic transformer
CN203026318U (en) Sealing device for secondary terminal of voltage transformer
CN202004342U (en) Box-type substation
CN204904968U (en) Automatic control by temperature change cooling system of transformer
CN204516546U (en) A kind of transformer air relief cock with U-shaped pipe
CN206774352U (en) A kind of weather resistant transformer
CN203536828U (en) Novel box type transformer substation
CN205080995U (en) Novel oil -immersed transformer
CN204144020U (en) A kind of oil-filled transformer
CN204834269U (en) Box -type substation oil tank for wind power generation
CN204651146U (en) A kind of winding inner tube structure of low pressure winding
CN203205188U (en) Half-sealing-type transformer
CN204480862U (en) A kind of oil-immersed type transformer
CN202405685U (en) Visual display system for line power flow and transformer power

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
AV01 Patent right actively abandoned

Granted publication date: 20130807

Effective date of abandoning: 20160824

C25 Abandonment of patent right or utility model to avoid double patenting