CN203082915U - Heat pipe type boiler air pre-heater - Google Patents

Heat pipe type boiler air pre-heater Download PDF

Info

Publication number
CN203082915U
CN203082915U CN2013200574628U CN201320057462U CN203082915U CN 203082915 U CN203082915 U CN 203082915U CN 2013200574628 U CN2013200574628 U CN 2013200574628U CN 201320057462 U CN201320057462 U CN 201320057462U CN 203082915 U CN203082915 U CN 203082915U
Authority
CN
China
Prior art keywords
air
heat pipe
circulation part
flue gas
ash
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2013200574628U
Other languages
Chinese (zh)
Inventor
莫加全
孙兰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANGHAI HUIHANG ENERGY SAVING EQUIPMENT CO Ltd
Original Assignee
SHANGHAI HUIHANG ENERGY SAVING EQUIPMENT CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANGHAI HUIHANG ENERGY SAVING EQUIPMENT CO Ltd filed Critical SHANGHAI HUIHANG ENERGY SAVING EQUIPMENT CO Ltd
Priority to CN2013200574628U priority Critical patent/CN203082915U/en
Application granted granted Critical
Publication of CN203082915U publication Critical patent/CN203082915U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E20/00Combustion technologies with mitigation potential
    • Y02E20/34Indirect CO2mitigation, i.e. by acting on non CO2directly related matters of the process, e.g. pre-heating or heat recovery

Abstract

The utility model relates to the field of boiler flue gas waste heat recovery air pre-heaters, in particular to a heat pipe type boiler air pre-heater. An air circulation part and a flue gas circulation part are connected through a heat pipe, the heat pipe is fixed with a separation board through full-length welding, an air inlet is arranged on one side of the air circulation part, an air outlet is arranged on the other side of the air circulation part, a flue gas outlet is arranged on one side of the gas flue circulation part, a flue gas inlet is arranged on the other side of the gas flue circulation part, an ash removal door is arranged on the outer side wall of the flue gas circulation part, an ash discharging hopper is arranged below the bottom of the gas flue circulation part, and stand columns are arranged on two sides of the ash discharging hopper. The heat pipe type boiler air pre-heater is small in size, high in heat exchange efficiency, small in resistance and easy and convenient to install; the ash removal door and the ash discharging hopper are arranged, ash is removed through an automatic ash removing function of the heat pipe, ash removal difficulty is greatly reduced for operators, and the service life of the product is prolonged; and reverse operation of flue gas and air is achieved, heat exchange is promoted through temperature difference enlargement, and therefore the optimum energy-saving effect can be achieved.

Description

A kind of tubular boiler air preheater
Technical field:
The utility model relates to residual heat from boiler fume and reclaims the air preheater field, is specifically related to a kind of tubular boiler air preheater.
Background technology:
Existing boiler adopts tubular air preheater more, and the main heat transfer component of tubular air preheater is a thin-wall steel tube.Tubular air preheater is cube more, and steel pipe is vertically staggered each other, and two ends are welded on the lower perforated plate.Tubular air preheater is equipped with sagging plate in bobbin carriage, flue gas up and down by preheater, then laterally by preheater, is finished the heat conduction along steel pipe.The shortcoming of tubular air preheater is that volume is big, stifled easily ash in the steel pipe, be not easy to cleaning and wear and tear easily in the gas approach place.
The utility model content:
The purpose of this utility model provides a kind of tubular boiler air preheater, its volume is little, the heat exchange efficiency height, resistance is little, installation is simple and convenient, be provided with shoot door and ash dropping hopper, utilize the automatic ash removing function of heat pipe to carry out deashing, significantly reduce operative employee's deashing difficulty, increased the long service life of product, with flue gas and air antikinesis, by enlarging the temperature difference, promote heat exchange, so that reach optimum energy-saving effect.
In order to solve the existing problem of background technology, the utility model is by the following technical solutions: it comprises the circulation of air part A, flue gas circulation part B, column 1, shoot door 2, exhanst gas outlet 3, gas approach 4, dividing plate 5, heat pipe 6, air intlet 7, air outlet slit 8 and ash dropping hopper 9, the circulation of air part A is connected by heat pipe 6 with flue gas circulation part B, heat pipe 6 and dividing plate 5 are fixed by full weld, one side of circulation of air part A is provided with air intlet 7, opposite side is provided with air outlet slit 8, the side of flue gas circulation part B is provided with exhanst gas outlet 3, opposite side is provided with gas approach 4, flue gas circulation part B lateral wall is provided with shoot door 2, below, flue gas circulation part B bottom is provided with ash dropping hopper 9, and the both sides of ash dropping hopper 9 are provided with column 1.
Two parts up and down of described heat pipe 6 all have fin 6-1, increase heat exchange area, improve heat exchange efficiency.
The equipment end portion was connected with boiler flue when the utility model was installed, flue gas enters to wash away after heat pipe 6 heat releases via gas approach 4 and is discharged by exhanst gas outlet 3, the equipment upper part then is connected with the air blast air channel, air blast is entered by air intlet 7, blast boiler furnace by air outlet slit 8 discharges again after washing away heat pipe 6 heat absorptions, improve boiler and mend the wind-warm syndrome degree.
The utlity model has following beneficial effect: its volume is little, the heat exchange efficiency height, resistance is little, installation is simple and convenient, be provided with shoot door and ash dropping hopper, utilize the automatic ash removing function of heat pipe to carry out deashing, significantly reduce operative employee's deashing difficulty, increased the long service life of product, with flue gas and air antikinesis, by enlarging the temperature difference, promote heat exchange, so that reach optimum energy-saving effect.
Description of drawings:
Fig. 1 is a structural representation of the present utility model;
Fig. 2 is the plan structure schematic diagram of Fig. 1;
Fig. 3 is the arrangement schematic diagram of heat pipe;
Fig. 4 is the syndeton schematic diagram of heat pipe and fin in the utility model.
The specific embodiment:
With reference to Fig. 1-4, this specific embodiment is taked following technical scheme: it comprises the circulation of air part A, flue gas circulation part B, column 1, shoot door 2, exhanst gas outlet 3, gas approach 4, dividing plate 5, heat pipe 6, air intlet 7, air outlet slit 8 and ash dropping hopper 9, the circulation of air part A is connected by heat pipe 6 with flue gas circulation part B, heat pipe 6 and dividing plate 5 are fixed by full weld, one side of circulation of air part A is provided with air intlet 7, opposite side is provided with air outlet slit 8, the side of flue gas circulation part B is provided with exhanst gas outlet 3, opposite side is provided with gas approach 4, flue gas circulation part B lateral wall is provided with shoot door 2, below, flue gas circulation part B bottom is provided with ash dropping hopper 9, and the both sides of ash dropping hopper 9 are provided with column 1.
Two parts up and down of described heat pipe 6 all have fin 6-1, increase heat exchange area, improve heat exchange efficiency.
The equipment end portion was connected with boiler flue when this specific embodiment was installed, flue gas enters to wash away after heat pipe 6 heat releases via gas approach 4 and is discharged by exhanst gas outlet 3, the equipment upper part then is connected with the air blast air channel, air blast is entered by air intlet 7, blast boiler furnace by air outlet slit 8 discharges again after washing away heat pipe 6 heat absorptions, improve boiler and mend the wind-warm syndrome degree.
This specific embodiment has following beneficial effect: its volume is little, the heat exchange efficiency height, resistance is little, installation is simple and convenient, be provided with shoot door and ash dropping hopper, utilize the automatic ash removing function of heat pipe to carry out deashing, significantly reduce operative employee's deashing difficulty, increased the long service life of product, with flue gas and air antikinesis, by enlarging the temperature difference, promote heat exchange, so that reach optimum energy-saving effect.

Claims (2)

1. tubular boiler air preheater, it is characterized in that it comprises circulation of air part (A), flue gas circulation part (B), column (1), shoot door (2), exhanst gas outlet (3), gas approach (4), dividing plate (5), heat pipe (6), air intlet (7), air outlet slit (8) and ash dropping hopper (9), circulation of air part (A) is connected by heat pipe (6) with flue gas circulation part (B), heat pipe (6) is fixed by full weld with dividing plate (5), one side of circulation of air part (A) is provided with air intlet (7), opposite side is provided with air outlet slit (8), one side of flue gas circulation part (B) is provided with exhanst gas outlet (3), opposite side is provided with gas approach (4), flue gas circulation part (B) lateral wall is provided with shoot door (2), below, flue gas circulation part (B) bottom is provided with ash dropping hopper (9), and the both sides of ash dropping hopper (9) are provided with column (1).
2. according to the described a kind of tubular boiler air preheater of claim 1, it is characterized in that two parts up and down of described heat pipe (6) all have fin (6-1).
CN2013200574628U 2013-02-01 2013-02-01 Heat pipe type boiler air pre-heater Expired - Fee Related CN203082915U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2013200574628U CN203082915U (en) 2013-02-01 2013-02-01 Heat pipe type boiler air pre-heater

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2013200574628U CN203082915U (en) 2013-02-01 2013-02-01 Heat pipe type boiler air pre-heater

Publications (1)

Publication Number Publication Date
CN203082915U true CN203082915U (en) 2013-07-24

Family

ID=48828748

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2013200574628U Expired - Fee Related CN203082915U (en) 2013-02-01 2013-02-01 Heat pipe type boiler air pre-heater

Country Status (1)

Country Link
CN (1) CN203082915U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106123012A (en) * 2016-06-30 2016-11-16 禹州市神运机械有限公司 A kind of vertical heat pipe air preheater
CN107327869A (en) * 2017-07-04 2017-11-07 江苏东方成套设备制造集团有限公司 A kind of heat pipe preheater

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106123012A (en) * 2016-06-30 2016-11-16 禹州市神运机械有限公司 A kind of vertical heat pipe air preheater
CN107327869A (en) * 2017-07-04 2017-11-07 江苏东方成套设备制造集团有限公司 A kind of heat pipe preheater

Similar Documents

Publication Publication Date Title
CN204313292U (en) A kind of waste heat of boiler tail gas is collected and treating apparatus
CN103697730A (en) Fast cooler of high-temperature flue gas
CN203082915U (en) Heat pipe type boiler air pre-heater
CN104315896A (en) Detachable heat exchanger for blast furnace slag flushing water
CN203657531U (en) Spiral condenser
CN203571819U (en) Condensation type extractor hood
CN203489229U (en) Waste heat boiler with multiple vertical modules
CN203923249U (en) Novel pair of air port buffer-type converter secondary flue gas capturing device
CN203784971U (en) Boiler soot blower for grease machining
CN103471073B (en) There is the waste heat boiler of multiple vertical type module
CN203258666U (en) Liquid drop recovery device of hanging type chimney
CN203240597U (en) Suspension type chimney comprising horizontal expansion joints
CN203162917U (en) Heat pipe type boiler economizer
CN204345692U (en) A kind of purifier of Gas Pipe
CN202192076U (en) Device for melting, carrying out heat preservation on and filtering paste waste
CN204268929U (en) A kind of detachable heat exchanger for blast furnace slag quenching water
CN207570384U (en) A kind of gas station waste-heat recovery device
CN207351237U (en) A kind of novel condensing unit
CN202253695U (en) Movable smoke hood for waste heat boiler
CN103977638A (en) Self-dedusting economizer
CN203842411U (en) Self-dust-removing energy saving device
CN204514075U (en) A kind of mechanical cooler for argon oxygen decarburization refining stove dust pelletizing system
CN203687074U (en) System for utilizing waste heat generated during welding wire production
CN216336686U (en) Industrial boiler dust removal desulfurization waste water recovery device
CN202692422U (en) Novel coal saving device of coal-fired boiler

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
DD01 Delivery of document by public notice

Addressee: Shanghai Huihang Energy Saving Equipment Co., Ltd.

Document name: Notification of Termination of Patent Right

CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20130724