CN202948512U - Acquisition controller for gas prepayment - Google Patents

Acquisition controller for gas prepayment Download PDF

Info

Publication number
CN202948512U
CN202948512U CN 201220725706 CN201220725706U CN202948512U CN 202948512 U CN202948512 U CN 202948512U CN 201220725706 CN201220725706 CN 201220725706 CN 201220725706 U CN201220725706 U CN 201220725706U CN 202948512 U CN202948512 U CN 202948512U
Authority
CN
China
Prior art keywords
circuit
acquisition controller
combustion gas
over circuit
change
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN 201220725706
Other languages
Chinese (zh)
Inventor
郭琪
郭长鹏
冯志玉
张利磊
刘颖
曹福香
王秀娟
徐建伟
马圆圆
路磊
刘玉良
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong Start Measurement Control Equipment Co Ltd
Original Assignee
Shandong Start Measurement Control Equipment Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong Start Measurement Control Equipment Co Ltd filed Critical Shandong Start Measurement Control Equipment Co Ltd
Priority to CN 201220725706 priority Critical patent/CN202948512U/en
Application granted granted Critical
Publication of CN202948512U publication Critical patent/CN202948512U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Investigating Or Analyzing Materials By The Use Of Fluid Adsorption Or Reactions (AREA)

Abstract

The utility model discloses an acquisition controller for gas prepayment. The acquisition controller comprises a temperature sampling converting circuit, a pressure sampling converting circuit, a flow sampling converting circuit and an IC (Integrated Circuit) card read-write circuit, wherein the temperature sampling converting circuit, the pressure sampling converting circuit, the flow sampling converting circuit and the IC card read-write circuit are respectively connected with a secondary singlechip; the secondary singlechip is connected with a main singlechip; the main singlechip is connected with a memory; and the main singlechip is further connected with a power supply circuit, a liquid crystal display circuit, a button circuit and an RS485 communication circuit. The acquisition controller for gas prepayment, disclosed by the utility model, is accurate to measure, large in storage quantity and strong in historical record storage capability.

Description

Combustion gas pre-payment acquisition controller
Technical field
The utility model relates to the gas metering technical field, specifically, relates to a kind of combustion gas pre-payment acquisition controller.
Background technology
At present, the gas meter, flow meter that good multi-user uses is all to adopt prepayment mode, need to use acquisition controller charging meter combustion gas integrated flux, but the gas flow that acquisition controller is originally measured is all the gas flow under operating mode, larger with the gas flow deviation under the mark condition, measure inaccurate, and memory space is little, can not satisfy the needs that record IC-card remaining sum, the historical use traffic of non-volatile recording combustion gas, integrated flux, outrange warning etc., also need paper using history of printing record, use inconvenience.
The utility model content
Technical problem to be solved in the utility model is: a kind of accurate measurement, combustion gas pre-payment acquisition controller that the storing history ability is strong are provided.
for solving the problems of the technologies described above, the technical solution of the utility model is: a kind of combustion gas pre-payment acquisition controller, comprise the temperature sampling change-over circuit, the force samples change-over circuit, traffic sampling change-over circuit and IC-card read/write circuit, described temperature sampling change-over circuit, described force samples change-over circuit, described traffic sampling change-over circuit and described IC-card read/write circuit are connected respectively to secondary single-chip microcomputer, described secondary single-chip microcomputer is connected to host scm, described host scm is connected with storer, described host scm also is connected with power circuit, liquid crystal display circuit, key circuit and RS485 telecommunication circuit.
Preferably, the quantity of described storer is two.
Preferably, described host scm also is connected with the GPRS/GSM telecommunication circuit.
After having adopted technique scheme, the beneficial effects of the utility model are:
Because this combustion gas pre-payment acquisition controller comprises temperature sampling change-over circuit, force samples change-over circuit, traffic sampling change-over circuit and IC-card read/write circuit, described temperature sampling change-over circuit, described force samples change-over circuit, described traffic sampling change-over circuit and described IC-card read/write circuit are connected respectively to secondary single-chip microcomputer, described secondary single-chip microcomputer is connected to host scm, described host scm is connected with storer, and described host scm also is connected with power circuit, liquid crystal display circuit, key circuit and RS485 telecommunication circuit.This combustion gas pre-payment acquisition controller in use, temperature, the pressure flow signal of combustion gas are sent to secondary single-chip microcomputer, pass through again the processing of secondary single-chip microcomputer, convert the operating mode flow to mark condition flow, eliminated the deviation of combustion gas operating mode flow with mark condition flow, made the gas flow signal of measurement more accurate.And calculate combustion gas accumulation use traffic, the IC-card information that records with the IC-card read/write circuit is relatively determined the situation that time that the user need to pay dues and user pay dues.And these information are delivered to host scm, then by host scm, it are delivered to storer and store.
Because the quantity of storer is two, increase memory capacity, can satisfy the needs that record IC-card remaining sum, the historical use traffic of non-volatile recording combustion gas, integrated flux, outrange warning etc., no longer needed paper using history of printing record, realized being easy to use without the paper memory storage.
Because described secondary single-chip microcomputer also is connected with the GPRS/GSM telecommunication circuit, make this combustion gas pre-payment acquisition controller have radio communication function.
Description of drawings
Below in conjunction with drawings and Examples, the utility model is further illustrated.
Fig. 1 is the theory diagram of the utility model combustion gas pre-payment acquisition controller;
Fig. 2 is the electronic circuitry of the utility model combustion gas pre-payment acquisition controller;
In figure: 1, secondary single-chip microcomputer; 2, host scm; 3, temperature sampling change-over circuit; 4, force samples change-over circuit; 5, traffic sampling change-over circuit; 6, IC-card read/write circuit; 7, power circuit; 8, liquid crystal display circuit; 9, key circuit; 10, RS485 telecommunication circuit; 11, GPRS/GSM telecommunication circuit; 12, storer.
Embodiment
As shown in Fig. 1 and Fig. 2 are common, combustion gas pre-payment acquisition controller of the present utility model, comprise temperature sampling change-over circuit 3, force samples change-over circuit 4, traffic sampling change-over circuit 5 and IC-card read/write circuit 6, temperature sampling change-over circuit 3, force samples change-over circuit 4, traffic sampling change-over circuit 5 and IC-card read/write circuit 6 are connected respectively to secondary single-chip microcomputer 1, secondary single-chip microcomputer 1 is connected to host scm 2, host scm 2 is connected with storer 12, and host scm 2 also is connected with power circuit 7, liquid crystal display circuit 8, key circuit 9 and RS485 telecommunication circuit 10.In Fig. 2, ZU1 is host scm, U6 is secondary single-chip microcomputer, U2 and U3 are storer, and this combustion gas pre-payment acquisition controller is sent to secondary single-chip microcomputer 1 with temperature, the pressure flow signal of combustion gas in use, pass through again the processing of secondary single-chip microcomputer 1, convert the operating mode flow to mark condition flow, eliminated the deviation of combustion gas operating mode flow with mark condition flow, make the gas flow signal of measurement more accurate.And calculate combustion gas accumulation use traffic, the IC-card information that records with IC-card read/write circuit 6 is relatively determined the situation that time that the user need to pay dues and user pay dues.And these information are delivered to host scm 2, then by host scm 2, it are delivered to storer 12 and store.
The quantity of storer 12 is two, increase memory capacity, can satisfy the needs that record IC-card remaining sum, the historical use traffic of non-volatile recording combustion gas, integrated flux, outrange warning etc., no longer needed paper using history of printing record, realized being easy to use without the paper memory storage.
Host scm 2 also is connected with GPRS/GSM telecommunication circuit 11, makes this combustion gas pre-payment acquisition controller have radio communication function.
The above is only giving an example of the utility model preferred forms.Should be pointed out that for the person of ordinary skill of the art, under the prerequisite that does not break away from the utility model spirit and principle, can also make some distortion and improvement.Protection domain of the present utility model is as the criterion with the content of claim, and any equivalent transformation that carries out based on technology enlightenment of the present utility model is also within protection domain of the present utility model.

Claims (3)

1. combustion gas pre-payment acquisition controller, it is characterized in that: comprise temperature sampling change-over circuit, force samples change-over circuit, traffic sampling change-over circuit and IC-card read/write circuit, described temperature sampling change-over circuit, described force samples change-over circuit, described traffic sampling change-over circuit and described IC-card read/write circuit are connected respectively to secondary single-chip microcomputer, described secondary single-chip microcomputer is connected to host scm, described host scm is connected with storer, and described host scm also is connected with power circuit, liquid crystal display circuit, key circuit and RS485 telecommunication circuit.
2. combustion gas pre-payment acquisition controller as claimed in claim 1, it is characterized in that: the quantity of described storer is two.
3. combustion gas pre-payment acquisition controller as claimed in claim 1 or 2, it is characterized in that: described host scm also is connected with the GPRS/GSM telecommunication circuit.
CN 201220725706 2012-12-25 2012-12-25 Acquisition controller for gas prepayment Expired - Lifetime CN202948512U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201220725706 CN202948512U (en) 2012-12-25 2012-12-25 Acquisition controller for gas prepayment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201220725706 CN202948512U (en) 2012-12-25 2012-12-25 Acquisition controller for gas prepayment

Publications (1)

Publication Number Publication Date
CN202948512U true CN202948512U (en) 2013-05-22

Family

ID=48424205

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201220725706 Expired - Lifetime CN202948512U (en) 2012-12-25 2012-12-25 Acquisition controller for gas prepayment

Country Status (1)

Country Link
CN (1) CN202948512U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104199470A (en) * 2014-08-08 2014-12-10 潍坊奥博仪表科技发展有限公司 Energy flow supply control method, controller and control system
CN108597122A (en) * 2018-04-23 2018-09-28 重庆人文科技学院 A kind of prepayment diaphragm gas number reading method
CN110400423A (en) * 2019-07-31 2019-11-01 杭州鸿鹄电子有限公司 A kind of multi-functional flowmeter of integral type Internet of Things and control method

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104199470A (en) * 2014-08-08 2014-12-10 潍坊奥博仪表科技发展有限公司 Energy flow supply control method, controller and control system
CN104199470B (en) * 2014-08-08 2017-02-15 潍坊奥博仪表科技发展有限公司 Steam/hot water IC card prepaid intelligent controller
CN108597122A (en) * 2018-04-23 2018-09-28 重庆人文科技学院 A kind of prepayment diaphragm gas number reading method
CN108597122B (en) * 2018-04-23 2020-08-18 重庆人文科技学院 Prepaid gas reading method
CN110400423A (en) * 2019-07-31 2019-11-01 杭州鸿鹄电子有限公司 A kind of multi-functional flowmeter of integral type Internet of Things and control method

Similar Documents

Publication Publication Date Title
CN203931006U (en) A kind of non-contact IC card water meter
CN102081118B (en) Real-time metering two-way communication intelligent ammeter
CN203588377U (en) IC (Integrated Circuit) card intelligent gas meter with GPRS (General Packet Radio Service) remote transmission function
CN202948512U (en) Acquisition controller for gas prepayment
CN103985197A (en) Prepaid intelligent water meter system
CN104677467A (en) Novel high-precision intelligent gas meter
CN204270400U (en) A kind of intellectual water meter electronic module
CN201562317U (en) Three-phase three-wire CPU card intelligent electric energy meter
CN203024813U (en) Oil consumption metering and displaying device
CN202434049U (en) Water meter data acquirer
CN204924523U (en) Air compressor machine energy consumption evaluation system
CN105279855A (en) Intelligent gas meter with NFC radio frequency CPU card
CN201508593U (en) IC card prepaid gas meter
CN204143550U (en) NFC radio frequency CPU card intelligent gas meter
CN206115584U (en) Plug -in card formula has water gauge of ladder water cost system
CN103150828A (en) Local carrier single-phase fee-controlled intelligent electric energy meter
CN203101503U (en) Multifunctional electric energy meter based on high-precision metering
CN201549018U (en) Single-phase electronic CPU card prepaid electric energy meter
CN201477674U (en) Multi-rate prepayment electric meter
CN103150827A (en) Local single-phase fee-controlled intelligent electric energy meter
CN203733219U (en) Direct-reading teletransmission valve control water meter
CN202339602U (en) Local single-phase cost control smart electric energy meter
CN203366435U (en) Ultrasonic intelligent water meter
CN202339600U (en) Local-carrier single-phase cost-control intelligent watt-hour meter
CN202563598U (en) Non-contact IC (Integrated Circuit) card type mechanical film type gas meter and control system thereof

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term

Granted publication date: 20130522

CX01 Expiry of patent term