CN202945724U CN 201220144571 CN201220144571U CN202945724U CN 202945724 U CN202945724 U CN 202945724U CN 201220144571 CN201220144571 CN 201220144571 CN 201220144571 U CN201220144571 U CN 201220144571U CN 202945724 U CN202945724 U CN 202945724U
Authority
CN
China
Prior art keywords
suspension member
shaped body
sides
ceiling system
lifting surface
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN 201220144571
Other languages
Chinese (zh)
Inventor
王洪波
党连军
李昂
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing New Building Material Group Co Ltd
Original Assignee
Beijing New Building Material Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing New Building Material Group Co Ltd filed Critical Beijing New Building Material Group Co Ltd
Priority to CN 201220144571 priority Critical patent/CN202945724U/en
Application granted granted Critical
Publication of CN202945724U publication Critical patent/CN202945724U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Floor Finish (AREA)

Abstract

The utility model discloses a suspended ceiling system containing a main keel and a secondary keel, and aims to overcome the defect of tedious construction of some suspended ceiling systems of the prior art. The suspended ceiling system comprises a hanging piece, a main keel, a secondary keel and a suspension bar, wherein the hanging piece comprises a U-shaped body, a connecting part and a strengthening hole are machined on both side faces of the U-shaped body, a hoisting hole is machined on a hoisting face connecting the two side faces, and the two side faces become narrow at the parts away from the hoisting face respectively and stretch out to form two clamping parts at the tail ends respectively; the hanging piece is sleeved on the main keel and the suspension bar is fixedly connected with the main keel through the hoisting hole; the clamping part of the hanging piece bends towards the interior of the U-shaped body, the secondary keel is arranged below and perpendicular to the main keel, and the clamping part of the hanging piece is clamped between turnover parts of two vertical plates of the secondary keel. The suspended ceiling system provided by the utility model is stable in integral structure.

Description

A kind of ceiling system that comprises main joist and secondary joist
Technical field
The utility model relates to a kind of ceiling system that comprises main joist and secondary joist.
Background technology
In present ceiling system, have and adopt main joist to hang the application of secondary joist by suspension member.In this application mode, secondary joist is suspended on main joist by two suspension members that are buckled in main joist both sides.These two suspension members are separately independently, are symmetricly set on main joist both sides.When construction and installation, installation personnel need to be installed simultaneously in the main joist both sides this a pair of suspension member, hangs secondary joist if only in main joist one side, a suspension member is installed because of carelessness or other reasons, and easily the installation of secondary joist is not reliable and stable especially.And all need to install two suspension members at every turn, and construction is comparatively loaded down with trivial details again, and efficient is lower.
The utility model content
Technical problem to be solved in the utility model be overcome in present part ceiling system secondary joist by two suspension members be suspended on main joist that construction is loaded down with trivial details, inefficiency and may the relatively poor defective of existence and stability.
In order to solve the problems of the technologies described above, the utility model provides a kind of ceiling system that comprises main joist and secondary joist, comprises suspension member (10), main joist (91), secondary joist (92) and suspension rod (93), wherein:
Suspension member (10) comprises U-shaped body (1), all be processed with snapping section (2) and reinforced hole (3) on two sides (11) of U-shaped body (1), connect on the lifting surface (12) of two sides (11) and be processed with hole for hoist, each leisure of two sides (11) narrows down and respectively stretches out endways an Access Division (4) to both sides away from the part of lifting surface (12); Suspension member (10) is enclosed within on main joist (91), and suspension rod (93) passes hole for hoist and is fixedly connected with main joist (91); Snapping section (2) on suspension member (10) is toward the internal bend of U-shaped body (1), perpendicular to main joist (91), secondary joist (92) is installed from the below of main joist (91), the Access Division (4) of suspension member (10) is stuck between folding portion (82) on (92) two risers of secondary joist (81).
Wherein, the snapping section (2) on two sides (11) of the U-shaped body (1) of suspension member (10) is oppositely arranged.
Wherein, the reinforced hole (3) on two sides (11) of the U-shaped body (1) of suspension member (10) is oppositely arranged.
Wherein, the snapping section (2) of suspension member (10) comprises rectangle, semicircle, half elliptic or triangle.
Wherein, the snapping section (2) of suspension member (10) forms from the cutting of the side (11) of U-shaped body (1), near lifting surface (12) one side be connected on side (11) or lifting surface (12).
Wherein, the Access Division (4) of suspension member (10) is in smoothing junction away from the end of lifting surface (12) by curve 5 and side (11).
Wherein, respectively be provided with a snapping section (2) on two sides (11) of the U-shaped body (1) of suspension member (10); On each side (11), snapping section (2) is positioned between the lifting surface (12) of reinforced hole (3) and U-shaped body (1).
Wherein, respectively be provided with two snapping sections (2) on two sides (11) of the U-shaped body (1) of suspension member (10), the reinforced hole (3) on each side (11) is positioned between two snapping sections (2) or the below.
Wherein, each side (11) of the U-shaped body (1) of suspension member (10), the top of (4) is gap (6) in the Access Division.
Wherein, the gap (6) of suspension member (10) is parallel to lifting surface (12) near the first side (61) of lifting surface (12) one sides, Second Edge (62) perk away from lifting surface (12) one sides, gap (6) connects the 3rd limit (63) of first side (61) and Second Edge (62), is straight line or curve.
Compared with prior art, the integrally-built stability of the ceiling system of the utility model embodiment is stronger.Embodiment of the present utility model replaces order the first two suspension member by a suspension member, guaranteeing can also not make installation personnel to construct efficiently and easily because carelessness waits outside the cause influence installation quality, has improved efficiency of construction.
Description of drawings
Fig. 1 is the structural representation of the suspension member used in the utility model.
Fig. 2 is the structural representation of the another kind of suspension member used in the utility model.
Fig. 3 is the partial structurtes schematic diagram of the ceiling system of the utility model embodiment.
The specific embodiment
For making the purpose of this utility model, technical scheme and advantage clearer, hereinafter in connection with accompanying drawing, embodiment of the present utility model is elaborated.Need to prove, in the situation that do not conflict, the embodiment in the application and the feature in embodiment be any combination mutually.
Fig. 1 is the structural representation of the utility model embodiment suspension member used.As shown in Figure 1, this suspension member mainly comprises U-shaped body 1, snapping section 2, reinforced hole 3 and Access Division 4.As shown in Figure 1, on two sides 11 of U-shaped body 1, all be processed with snapping section 2 and reinforced hole 3.In implementation as shown in Figure 1, the snapping section 2 on two sides 11 is oppositely arranged, and the reinforced hole 3 on two sides 11 also is oppositely arranged.Connect the width of the lifting surface 12 of two sides 11 on U-shaped body 1, more than or equal to the width of main joist, U-shaped body 1 like this can be enclosed within on main joist.Suspension member as shown in Figure 1, snapping section 2 is rectangle, its side 11 cuttings from U-shaped body 1 form, can be towards the inside of U-shaped body 1 and bend towards the lifting surface 12 of U-shaped body 1, wherein snapping section 2 is connected on the side 11 or lifting surface 12 of U-shaped body 1 near one side of the lifting surface 12 of U-shaped bodies 1, cuts open from the side of U-shaped body 1 away from one side and the both sides of the lifting surface 12 of U-shaped body 1.Suspension member as shown in Figure 1, the snapping section 2 on each side 11 is between the lifting surface 12 of reinforced hole 3 and U-shaped body 1.
In suspension member as shown in Figure 1, on the lifting surface 12 of U-shaped body 1, also be processed with the hole for hoist (not shown in figure 1).
Suspension member as shown in Figure 1,1 two sides, 11 each leisures of U-shaped body narrow down away from the part of lifting surface 12, and respectively stretch out an Access Division 4 to both sides endways.Access Division 4 is in smoothing junction away from the end of lifting surface 12 by curve 5 and side 11.
In suspension member as shown in Figure 1, each side 11 of U-shaped body 1 is gap 6 above Access Division 4.Gap 6 is parallel to lifting surface 12 near the first side 61 of lifting surface 12 1 sides, the slight perk of Second Edge 62 away from lifting surface 12 1 sides, gap 6 connects the 3rd limit 63 of first side 61 and Second Edge 62, can be straight line, can be also curve, comprise the curve that the curve by several sections different curvature is formed by connecting.
As shown in Figure 2, in the another kind of suspension member that the utility model adopts, all comprise two snapping sections 2 on each side 11 of U-shaped body 1, these two snapping sections 2 lay respectively at the both sides of side 11 separately.Reinforced hole 3 on side 11 is between two snapping sections 2.In the suspension member of other implementations, reinforced hole 3 also can be positioned at the below of two snapping sections 2.
As shown in Figure 3, the suspension member of the utility model embodiment, with the keel fit applications time, suspension member 10 is enclosed within on main joist 91, and the hole for hoist that suspension rod 93 passes on it is fixedly connected with main joist 91.With the internal bend of the snapping section on suspension member 10 toward U-shaped body 1, further guarantee can not produce significantly between suspension member 10 and main joist 91 and relatively move.From the below of main joist 91 perpendicular to main joist 91, secondary joists 92 are installed, wherein the Access Division 4 of suspension member 10 is stuck between folding portion 82 on 92 two risers 81 of secondary joist.Gap 6 on 1 two sides 11 of U-shaped body is away from the slight perk of Second Edge 62 of lifting surface 12 1 sides, makes Access Division 4 can firmly be stuck between folding portion 82 on 92 two risers 81 of secondary joist.
Snapping section 2 on 1 two sides 11 of the U-shaped body of suspension member 10 lays respectively between the lifting surface 12 of reinforced hole 3 on side 11 separately and U-shaped body 1.After suspension member 10 is enclosed within on main joist, can by two snapping section 2 inside to U-shaped body 1 are bent, guarantee can not relatively move between main joist and suspension member 10.And by insert rigid body in reinforced hole 3, strengthen the bonding strength between main joist and suspension member 10.
The snapping section 2 of suspension member illustrated in figures 1 and 2 is rectangle, in other embodiment of the present utility model, the snapping section 2 that forms from 1 cutting of U-shaped body can be also half elliptic, semicircle, triangle or other irregular shapes, as long as its part is connected on U-shaped body 1 and can be towards the inside of U-shaped body 1 and bend towards the lifting surface 12 of U-shaped body 1.
Although the disclosed embodiment of the utility model as above, the embodiment that described content just adopts for the ease of understanding the utility model is not to limit the utility model.Those of skill in the art under any the utility model; under the prerequisite that does not break away from the disclosed spirit and scope of the utility model; can do any modification and variation what implement in form and on details; but scope of patent protection of the present utility model still must be as the criterion with the scope that appending claims was defined.

Claims (10)

1. a ceiling system that comprises main joist and secondary joist, is characterized in that, comprises suspension member (10), main joist (91), secondary joist (92) and suspension rod (93), wherein:
Suspension member (10) comprises U-shaped body (1), all be processed with snapping section (2) and reinforced hole (3) on two sides (11) of U-shaped body (1), connect on the lifting surface (12) of two sides (11) and be processed with hole for hoist, each leisure of two sides (11) narrows down and respectively stretches out endways an Access Division (4) to both sides away from the part of lifting surface (12); Suspension member (10) is enclosed within on main joist (91), and suspension rod (93) passes hole for hoist and is fixedly connected with main joist (91); Snapping section (2) on suspension member (10) is toward the internal bend of U-shaped body (1), perpendicular to main joist (91), secondary joist (92) is installed from the below of main joist (91), the Access Division (4) of suspension member (10) is stuck between folding portion (82) on (92) two risers of secondary joist (81).
2. ceiling system according to claim 1 is characterized in that:
Snapping section (2) on two sides (11) of the U-shaped body (1) of suspension member (10) is oppositely arranged.
3. ceiling system according to claim 1 is characterized in that:
Reinforced hole (3) on two sides (11) of the U-shaped body (1) of suspension member (10) is oppositely arranged.
4. ceiling system according to claim 1 is characterized in that:
The snapping section (2) of suspension member (10) comprises rectangle, semicircle, half elliptic or triangle.
5. ceiling system according to claim 1 is characterized in that:
The snapping section (2) of suspension member (10) forms from the cutting of the side (11) of U-shaped body (1), near lifting surface (12) one side be connected on side (11) or lifting surface (12).
6. ceiling system according to claim 1 is characterized in that:
The Access Division (4) of suspension member (10) is in smoothing junction away from the end of lifting surface (12) by curve (5) and side (11).
7. ceiling system according to claim 1 is characterized in that:
Respectively be provided with a snapping section (2) on two sides (11) of the U-shaped body (1) of suspension member (10); On each side (11), snapping section (2) is positioned between the lifting surface (12) of reinforced hole (3) and U-shaped body (1).
8. ceiling system according to claim 1 is characterized in that:
Respectively be provided with two snapping sections (2) on two sides (11) of the U-shaped body (1) of suspension member (10), the reinforced hole (3) on each side (11) is positioned between two snapping sections (2) or the below.
9. ceiling system according to claim 1 is characterized in that:
Each side (11) of the U-shaped body (1) of suspension member (10), the top of (4) is gap (6) in the Access Division.
10. ceiling system according to claim 9 is characterized in that:
The gap (6) of suspension member (10) is parallel to lifting surface (12) near the first side (61) of lifting surface (12) one sides, Second Edge (62) perk away from lifting surface (12) one sides, gap (6) connects the 3rd limit (63) of first side (61) and Second Edge (62), is straight line or curve.
CN 201220144571 2012-04-09 2012-04-09 Suspended ceiling system containing main keel and secondary keel Expired - Lifetime CN202945724U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201220144571 CN202945724U (en) 2012-04-09 2012-04-09 Suspended ceiling system containing main keel and secondary keel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201220144571 CN202945724U (en) 2012-04-09 2012-04-09 Suspended ceiling system containing main keel and secondary keel

Publications (1)

Publication Number Publication Date
CN202945724U true CN202945724U (en) 2013-05-22

Family

ID=48421432

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201220144571 Expired - Lifetime CN202945724U (en) 2012-04-09 2012-04-09 Suspended ceiling system containing main keel and secondary keel

Country Status (1)

Country Link
CN (1) CN202945724U (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103758271A (en) * 2014-01-27 2014-04-30 王佳佳 Neck type ceiling connecting part and ceiling structure
CN104074301A (en) * 2014-07-08 2014-10-01 无锡唯景木业有限公司 Ceiling installing structure
CN104878868A (en) * 2015-05-28 2015-09-02 广州市广京装饰材料有限公司 Ceiling keel structure and mounting method
CN106245840A (en) * 2016-09-29 2016-12-21 范柏联 A kind of overlap stable ceiling joist
CN107152115A (en) * 2016-03-03 2017-09-12 北新集团建材股份有限公司 Mineral wool board sector ceiling suspension system
CN110805196A (en) * 2019-08-09 2020-02-18 浙江亚厦装饰股份有限公司 Suspension rod-free ceiling structure
CN113356462A (en) * 2021-06-21 2021-09-07 北新集团建材股份有限公司 Hanging component and ceiling assembling method

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103758271A (en) * 2014-01-27 2014-04-30 王佳佳 Neck type ceiling connecting part and ceiling structure
CN104074301A (en) * 2014-07-08 2014-10-01 无锡唯景木业有限公司 Ceiling installing structure
CN104878868A (en) * 2015-05-28 2015-09-02 广州市广京装饰材料有限公司 Ceiling keel structure and mounting method
CN107152115A (en) * 2016-03-03 2017-09-12 北新集团建材股份有限公司 Mineral wool board sector ceiling suspension system
CN107152115B (en) * 2016-03-03 2023-06-09 北新集团建材股份有限公司 Sector suspended ceiling system of mineral wool board
CN106245840A (en) * 2016-09-29 2016-12-21 范柏联 A kind of overlap stable ceiling joist
CN110805196A (en) * 2019-08-09 2020-02-18 浙江亚厦装饰股份有限公司 Suspension rod-free ceiling structure
CN113356462A (en) * 2021-06-21 2021-09-07 北新集团建材股份有限公司 Hanging component and ceiling assembling method

Similar Documents

Publication Publication Date Title
CN202945724U (en) Suspended ceiling system containing main keel and secondary keel
CN203617637U (en) Cable ladder plane connecting piece
CN104860189A (en) Adjustable sheet material lifting hook
CN202595996U (en) Pedant
CN103924284A (en) Placement device for anodic oxidation aluminum product
CN204714326U (en) A kind of adjustable sheet material suspension hook
CN203947648U (en) A kind of Skeleton hanging part structure
CN205348810U (en) Can dismantle unit glass curtain wall's stone tongs and lifting device
CN205088943U (en) Scaffold support system's top fossil fragments connection structure
CN204152033U (en) The partition post that intensity is high and easy for installation
CN202248470U (en) Ceiling skeleton connection structure
CN203701361U (en) Installation structure of ceramic plate curtain wall
CN203113791U (en) Concrete pump truck and fifth arm support thereof
CN203878776U (en) Corner connecting piece
CN204554194U (en) A kind of reinforced bend pipe
CN203878231U (en) Placement device for anodization aluminum products
CN203821682U (en) Keel hanger structure
CN208577341U (en) A kind of multiple spot load-bearing suspender
CN103701065A (en) Mounting rack for replacing tension-resistant cross arms
CN204038854U (en) A kind of lifting hook for cable tray suspension bracket
CN204059712U (en) T-shaped keel buckling and hanging system
CN202426198U (en) Clothes hanger structure stable in hanging
CN208830710U (en) Main side bar
CN202750351U (en) Pole-used optical network terminal communication box
CN201486131U (en) Concrete pouring template provided with wood frames

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20130522