Prior art keywords
early warning
work station
analysis
line monitoring
server
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN2012206428156U
Other languages
Chinese (zh)
Inventor
田成凤
冀慧强
郭浩
赵北涛
方琼
刘美静
黄东来
宫俊
张树民
刘广振
孙莹
徐建政
随慧斌
李�荣
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Tianjin Electric Power Corp
Original Assignee
State Grid Corp of China SGCC
Tianjin Electric Power Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Tianjin Electric Power Corp filed Critical State Grid Corp of China SGCC
Priority to CN2012206428156U priority Critical patent/CN202931037U/en
Application granted granted Critical
Publication of CN202931037U publication Critical patent/CN202931037U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E60/00Enabling technologies; Technologies with a potential or indirect contribution to GHG emissions mitigation
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/16Electric power substations

Landscapes

  • Remote Monitoring And Control Of Power-Distribution Networks (AREA)

Abstract

Disclosed is a real-time analysis early warning system of intelligent transformer station operation safety. The real-time analysis early warning system of the utility model is characterized by comprising an analysis early warning server, an analysis early warning work station, a preposed work station, a switch, an isolation device, an on-line monitoring server, and a device on-line monitoring system, wherein the analysis early warning server, the analysis early warning work station, and the preposed work station are connected together via the switch; the preposed work station is connected with the on-line monitoring server via the isolation device; and the on-line monitoring server is connected with the device on-line monitoring system. According to the utility model, the real-time analysis early warning system carries out the monitoring of the operation state of various electric power devices in the intelligent transformer station, then carries out comprehensive analysis of the safety and reliability, and makes intelligent maintenance scheme, thereby realizing the early warning function, facilitating the rapid emergency disposal, and finally forming secure precaution, secure monitoring, afterword treatment, and decision-supported complete safety protection system. The real-time analysis early warning system of the utility model lays a foundation for exploring the new mode of safety centralization monitoring management.

Description

Intelligent substation security of operation real-time analysis early warning system
Technical field
The utility model belongs to transmission of electricity and power transformation field, especially a kind of intelligent substation security of operation real-time analysis early warning system.
Background technology
Intelligent transformer station is as the key equipment that is connected intelligent grid generating, transmission of electricity, power transformation, distribution, electricity consumption and scheduling six large links, bear voltage of transformation, acceptance and distribution electric energy in intelligent grid, control flow of power to the critical function of adjusting voltage, be also the focus that in intelligent grid, " flow of power, information flow, Business Stream " three streams collect simultaneously, have vital effect to building strong intelligent grid.Present stage, transformer station was after carrying out unmanned or few man on duty, although the comprehensive automation system of transformer substation with " four is distant " function has been installed, the on-line monitoring system of part visual plant also has been installed, running status that can real-time watch device, but most of or main by regularly implementing for the inspection and maintenance of transformer station's visual plant, there is no the analysis and early warning function.
Summary of the invention
The purpose of this utility model is to overcome the deficiencies in the prior art, provides a kind of reasonable in design and have an intelligent substation security of operation real-time analysis early warning system of warning function.
The utility model solves its technical problem and takes following technical scheme to realize:
A kind of intelligent substation security of operation real-time analysis early warning system, comprise analysis and early warning server, analysis and early warning work station, preposition work station, switch, xegregating unit, on-line monitoring server and equipment on-line monitoring system, analysis and early warning server, analysis and early warning work station, preposition work station link together by switch, preposition work station is connected with the on-line monitoring server by xegregating unit, and the on-line monitoring server is connected with the equipment on-line monitoring system.
And described equipment on-line monitoring system comprises multi-point type optical fiber temp measuring system, transformer detection system and environmental monitoring system.
And described analysis and early warning work station is one or more.
Advantage of the present utility model and good effect are:
The utility model is by carrying out status monitoring to the various power equipments in intelligent substation, then carry out the security reliability analysis-by-synthesis, formulate intelligent maintenance scheme, can realize the function that gives warning in advance, be convenient to quick emergency disposal, final form safety precautions, security monitoring, process and the security protection system of completing of decision support afterwards, lay the first stone for exploring safe centralization monitoring management new model.
Description of drawings
Fig. 1 is system of the present utility model connection diagram.
Embodiment
Below in conjunction with accompanying drawing, the utility model is further described.
a kind of intelligent substation security of operation real-time analysis early warning system, as shown in Figure 1, comprise the analysis and early warning server, the analysis and early warning work station, preposition work station, switch, xegregating unit, on-line monitoring server and equipment on-line monitoring system, wherein, the analysis and early warning server, the analysis and early warning work station, preposition work station links together by switch, preposition work station is connected with the on-line monitoring server by xegregating unit, the on-line monitoring server is connected with the equipment on-line monitoring system, the equipment on-line monitoring system comprises the multi-point type optical fiber temp measuring system, transformer detection system and environmental monitoring system.Multi-point type optical fiber temp measuring system, transformer detection system and environmental monitoring system gather the real time data of each power equipment in intelligent substation and it are delivered to the on-line monitoring server, the various data preparations that the on-line monitoring server will be received are sent to the analysis and early warning server by xegregating unit, each analysis and early warning work station is to the needed data of analysis and early warning server application substation equipment security reliability real-time analysis early warning, and adopts expert system and warning algorithm to carry out the security reliability real-time analysis early warning of equipment.The below describes respectively the various piece in system:
the analysis and early warning server is the nucleus equipment of system, analysis and early warning work station and preposition work station are client computer, between analysis and early warning server and analysis and early warning work station and the network communication between preposition work station and analysis and early warning server are connected with transfer of data and adopt based on the nontransparent communication mode of the network of reliable connection (being point-to-point mode), that is: the analysis and early warning work station in the mode of question-response to analysis and early warning server request data or send control command, the analysis and early warning server passes to preposition work station in point-to-point mode again, this point-to-point mode based on reliable connection, can definitely guarantee reliability and integrality that data are transmitted.Analysis and early warning work station and analysis and early warning server are followed the IEC61850 modeling rule, the substation operation data transaction are become to meet the object model of IEC61850 standard; Analysis and early warning work station and analysis and early warning server are also followed IEC61970 GID standard, and the GID open application interface is provided.The analysis and early warning work station can arrange many according to actual needs, adopt the B/S(Client/Server Architecture between analysis and early warning server and each work station) network configuration, each work station all carries out exchanges data by switch and analysis and early warning server, owing to adopting the B/S structure, guaranteed the consistency of data, and can make the system information resource realize sharing in the wide area network scope.Because the analysis and early warning work station does not have the database of oneself, the needed data of analysis and early warning work station and information all are taken from the analysis and early warning server, so every analysis and early warning work station at any time all can be opened or close down and not affect its historical data and information inquiry.Preposition work station is as a kind of client computer of specific type, the interface task of completion system and field data.
the on-line monitoring server is connected with preposition work station by xegregating unit on the one hand, on the other hand with the equipment on-line monitoring system in the multi-point type optical fiber temp measuring system, the transformer detection system is connected with environmental monitoring system, the on-line monitoring server according to and each equipment on-line monitoring system between communication protocol receive the multi-point type optical fiber temp measuring system, the temperature data that transformer detection system and environmental monitoring system gather, the transformer data, environmental data, obtain substation dynamic data and equipment state, images etc. reflect the data of substation equipment state and operating condition comprehensively and send in the analysis and early warning server in point-to-point mode by xegregating unit, processed by the analysis and early warning server.Also to adopt point-to-point mode to realize data communication function between on-line monitoring server and analysis and early warning server.
It is emphasized that; embodiment described in the utility model is illustrative; rather than determinate; therefore the utility model comprises and is not limited to the embodiment described in embodiment; every by those skilled in the art according to other execution modes that the technical solution of the utility model draws, belong to equally the scope of the utility model protection.

Claims (3)

1. intelligent substation security of operation real-time analysis early warning system, it is characterized in that: comprise analysis and early warning server, analysis and early warning work station, preposition work station, switch, xegregating unit, on-line monitoring server and equipment on-line monitoring system, analysis and early warning server, analysis and early warning work station, preposition work station link together by switch, preposition work station is connected with the on-line monitoring server by xegregating unit, and the on-line monitoring server is connected with the equipment on-line monitoring system.
2. intelligent substation security of operation real-time analysis early warning system according to claim 1 is characterized in that: described equipment on-line monitoring system comprises multi-point type optical fiber temp measuring system, transformer detection system and environmental monitoring system.
3. intelligent substation security of operation real-time analysis early warning system according to claim 1 is characterized in that: described analysis and early warning work station is one or more.
CN2012206428156U 2012-11-28 2012-11-28 Real-time analysis early warning system of intelligent transformer station operation safety Expired - Lifetime CN202931037U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012206428156U CN202931037U (en) 2012-11-28 2012-11-28 Real-time analysis early warning system of intelligent transformer station operation safety

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012206428156U CN202931037U (en) 2012-11-28 2012-11-28 Real-time analysis early warning system of intelligent transformer station operation safety

Publications (1)

Publication Number Publication Date
CN202931037U true CN202931037U (en) 2013-05-08

Family

ID=48220947

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012206428156U Expired - Lifetime CN202931037U (en) 2012-11-28 2012-11-28 Real-time analysis early warning system of intelligent transformer station operation safety

Country Status (1)

Country Link
CN (1) CN202931037U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US11315083B2 (en) * 2016-12-28 2022-04-26 Hyosung Heavy Industries Corporation Asset management method for substation
US11507074B2 (en) 2017-04-28 2022-11-22 Hyosung Heavy Industries Corporation Method for asset management of substation

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US11315083B2 (en) * 2016-12-28 2022-04-26 Hyosung Heavy Industries Corporation Asset management method for substation
US11507074B2 (en) 2017-04-28 2022-11-22 Hyosung Heavy Industries Corporation Method for asset management of substation

Similar Documents

Publication Publication Date Title
CN111131480A (en) Cloud edge cooperative service system for smart power plant
CN106532935B (en) For carrying out the method and its system of secondary system of intelligent substation fault diagnosis
Jamil et al. Condition-based maintenance decision making support system (DSS) of hydropower plant
CN102263436B (en) On-line monitoring system for energy-saving scheduling and real-time coal consumption of power grid
CN110084946A (en) A kind of system and method that five-defence block is used for based on wearable device
CN104504483B (en) Method for realizing province and local integration of anti-misoperation tickets
CN105262227A (en) Fool-proof lockout system
CN202363972U (en) Remote operation and maintenance platform of substation secondary system
CN202931037U (en) Real-time analysis early warning system of intelligent transformer station operation safety
CN107832857A (en) A kind of low-voltage network system of smart city
CN202840679U (en) Intelligent analyzing and decision-making system for transformation operating accidents and abnormity
Peng et al. Design and development of intelligent operation and maintenance training system for substation based on augmented reality
Xiao et al. The influence of green development idea on power supply reliability and power quality of distribution network
Fu et al. An edge computing framework for digital grid
CN103872778A (en) Wind power control center device arranged in redundant mode
Bian et al. Research on the realization and application of intelligent iot platform for electrical equipment under industrial internet
CN106655127A (en) Urgent repair command system for distribution network
CN105262218A (en) Smart grid electric power information safety monitoring system and method
CN107301606A (en) A kind of energy management monitoring system
CN202183638U (en) Remote distribution control system based on internet of things
Wang et al. On Unmanned Electric Power System and Its Development Strategy
CN105305623A (en) Distributed generation information management and control system
CN204408026U (en) A kind of substation secondary device monitor and analysis system
CN209015215U (en) A kind of visualization power transmission and transforming equipment supervisory systems
CN203788051U (en) Wind power control center device with redundancy setting

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20130508