CN202690083U - Waterproof structure of shield tunnel duct piece - Google Patents

Waterproof structure of shield tunnel duct piece Download PDF

Info

Publication number
CN202690083U
CN202690083U CN 201220016385 CN201220016385U CN202690083U CN 202690083 U CN202690083 U CN 202690083U CN 201220016385 CN201220016385 CN 201220016385 CN 201220016385 U CN201220016385 U CN 201220016385U CN 202690083 U CN202690083 U CN 202690083U
Authority
CN
China
Prior art keywords
water blocking
blocking tape
circumferential weld
waterproof
vertical
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 201220016385
Other languages
Chinese (zh)
Inventor
周质炎
程斌
由广明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Municipal Engineering Design Insitute Group Co Ltd
Original Assignee
Shanghai Municipal Engineering Design Insitute Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Municipal Engineering Design Insitute Group Co Ltd filed Critical Shanghai Municipal Engineering Design Insitute Group Co Ltd
Priority to CN 201220016385 priority Critical patent/CN202690083U/en
Application granted granted Critical
Publication of CN202690083U publication Critical patent/CN202690083U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

The utility model relates to a waterproof structure of a shield tunnel duct piece. The waterproof structure of the shield tunnel duct piece is characterized in that two parallel circular seam waterproof tapes are arranged between the inner wall and the outer wall of the shield duct piece. When the waterproof structure of the shield tunnel duct piece is used, one way of water prevention is expanded into two ways of parallel water prevention for a shield tunnel duct piece waterproof system, and a plurality of circular seam vertical waterproof tapes perpendicular to the circular seam waterproof tapes are arranged between the two parallel circular seam waterproof tapes to form a plurality of waterproof partitions. Therefore, by means of the method, underground water is effectively prevented from entering a tunnel through vertical seams and circular seams, a leaking position can be accurately confirmed when leakage occurs on the tunnel so as to be favorable for people to take treating measures.

Description

The waterproof construction of duct pieces of shield tunnel
Technical field
The utility model relates to the technical field of duct pieces of shield tunnel waterproof, and specifically duct pieces of shield tunnel prevents that underground water from passing through the method that circumferential weld (each ring between), longitudinal joint (between each piece) enter tunnel internal.
Background technology
At present, the tunnel of China's shield construction is more and more, and underground water is the principal element that affects tunnel safety, if ground water seepage, can affect the normal operation in tunnel and application life to tunnel internal.One waterproof system of the at present many employings of shield tunnel, in case lost efficacy, underground water just can leak out to tunnel internal, can not accurately determine to be unfavorable for taking treatment measures by seepage place simultaneously.
Summary of the invention
The purpose of this utility model is to provide a kind of waterproof construction of duct pieces of shield tunnel, it can prevent effectively that underground water from entering tunnel internal by longitudinal joint and circumferential weld, forms simultaneously the waterproof subregion, when percolating water occurring in the tunnel, can find fast breakthrough, be convenient to fast processing, reduce expenses.
To achieve these goals, the technical solution of the utility model is: the waterproof construction of duct pieces of shield tunnel, it mainly comprises shield duct piece, and shield duct piece is provided with inner and outer wall, it is characterized in that: be provided with the parallel circumferential weld water blocking tape of twice between the inside and outside wall of shield duct piece.
During use the utility model duct pieces of shield tunnel waterproof system by expanding to together the parallel waterproof of two pass, and the vertical water blocking tape of some circumferential welds perpendicular to the circumferential weld water blocking tape is set between the parallel circumferential weld water blocking tape of twice, form some waterproof subregions, the method can prevent effectively that underground water from entering tunnel internal by longitudinal joint and circumferential weld, simultaneously when tunnel generation seepage, can accurately determine seepage place, be beneficial to and take treatment measures.
Description of drawings
Fig. 1 is the plan view of circumferential weld water blocking tape of the present utility model.
Fig. 2 is the plan view of the vertical water blocking tape of circumferential weld of the present utility model.
The specific embodiment
Below in conjunction with drawings and Examples the utility model is further described.
The utility model mainly comprises shield duct piece, and shield duct piece is provided with inwall 1 and outer wall 2, it is characterized in that: be provided with the parallel circumferential weld water blocking tape 3 of twice between the inside and outside wall of shield duct piece.Be provided with the vertical water blocking tape 4 of several circumferential welds vertical with the circumferential weld water blocking tape between the twice circumferential weld water blocking tape, the vertical water blocking tape of circumferential weld is separated into several waterproof subregions 5 with twice circumferential weld water blocking tape, longitudinal joint water blocking tape seamless intersect vertical with the circumferential weld water blocking tape.Be provided with the vertical water blocking tape of the 3-30 bar circumferential weld vertical with the circumferential weld water blocking tape between the twice circumferential weld water blocking tape, the vertical water blocking tape of circumferential weld is separated into 3-30 waterproof subregion with twice circumferential weld water blocking tape, longitudinal joint water blocking tape width 24mm~45mm, thickness 16mm~22mm, circumferential weld water blocking tape width 24mm~45mm, thickness 16mm~22mm.Distance between the twice longitudinal joint water blocking tape is identical with distance between the twice circumferential weld water blocking tape, and the position of longitudinal joint water blocking tape is corresponding with the position of circumferential weld water blocking tape.Circumferential weld water blocking tape water blocking tape vertical with circumferential weld adopts elastic rubber gasket to make, and material is the material that ethylene propylene diene rubber, water-expansible rubber or ethylene propylene diene rubber and water-expansible rubber are composited.The longitudinal joint water blocking tape adopts elastic rubber gasket to make, and material is the material that ethylene propylene diene rubber, water-expansible rubber or ethylene propylene diene rubber and water-expansible rubber are composited.The position of the vertical waterproof of the utility model and quantity can be adjusted according to section of jurisdiction block form and assembly unit situation, but will guarantee that the position of the vertical waterproof of circumferential weld between every ring is consistent with quantity.
Embodiment 1
Be provided with 16 vertical water blocking tapes of the circumferential weld vertical with the circumferential weld water blocking tape between the parallel circumferential weld water blocking tape of twice, the vertical water blocking tape of circumferential weld is separated into 16 waterproof subregions with twice circumferential weld water blocking tape.Be provided with the parallel longitudinal joint water blocking tape of twice in the shield duct piece, longitudinal joint water blocking tape seamless intersect vertical with the circumferential weld water blocking tape.Longitudinal joint water blocking tape width 24mm, thickness 16mm, circumferential weld water blocking tape width 24mm, thickness 16mm.Distance between the twice longitudinal joint water blocking tape is identical with distance between the twice circumferential weld water blocking tape, and the position of longitudinal joint water blocking tape is corresponding with the position of circumferential weld water blocking tape.Circumferential weld water blocking tape, the vertical water blocking tape of circumferential weld and longitudinal joint water blocking tape employing elastic rubber gasket etc. are made, and material is ethylene propylene diene rubber etc., and the technical indicator of ethylene propylene diene rubber is as follows:
Figure DEST_PATH_GDA00002119387200031
Annotate: only illustrate wherein a kind of material here, also can adopt water-expansible rubber or the material that is composited is done water blocking tape.
By this waterproof construction, can prevent effectively that underground water from entering tunnel internal by longitudinal joint and circumferential weld, form simultaneously the waterproof subregion, when percolating water occurring in the tunnel, can find fast breakthrough, be convenient to fast processing, reduce expenses.

Claims (4)

1. the waterproof construction of duct pieces of shield tunnel, it mainly comprises shield duct piece, shield duct piece is provided with inner and outer wall, it is characterized in that: be provided with the parallel circumferential weld water blocking tape of twice between the inside and outside wall of shield duct piece.
2. the waterproof construction of duct pieces of shield tunnel as claimed in claim 1, it is characterized in that: be provided with the vertical water blocking tape of several circumferential welds vertical with the circumferential weld water blocking tape between the twice circumferential weld water blocking tape, the vertical water blocking tape of circumferential weld is separated into several waterproof subregions with twice circumferential weld water blocking tape, longitudinal joint water blocking tape seamless intersect vertical with the circumferential weld water blocking tape.
3. the waterproof construction of duct pieces of shield tunnel as claimed in claim 2, it is characterized in that: be provided with the vertical water blocking tape of the 3-30 bar circumferential weld vertical with the circumferential weld water blocking tape between the twice circumferential weld water blocking tape, and twice circumferential weld water blocking tape is separated into 3-30 waterproof subregion, longitudinal joint water blocking tape width 24mm ~ 45mm, thickness 16mm ~ 22mm, circumferential weld water blocking tape width 24mm ~ 45mm, thickness 16mm ~ 22mm.
4. the waterproof construction of duct pieces of shield tunnel as claimed in claim 2 is characterized in that: the distance between the twice longitudinal joint water blocking tape is identical with distance between the twice circumferential weld water blocking tape, and the position of longitudinal joint water blocking tape is corresponding with the position of circumferential weld water blocking tape.
CN 201220016385 2012-01-13 2012-01-13 Waterproof structure of shield tunnel duct piece Expired - Fee Related CN202690083U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201220016385 CN202690083U (en) 2012-01-13 2012-01-13 Waterproof structure of shield tunnel duct piece

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201220016385 CN202690083U (en) 2012-01-13 2012-01-13 Waterproof structure of shield tunnel duct piece

Publications (1)

Publication Number Publication Date
CN202690083U true CN202690083U (en) 2013-01-23

Family

ID=47545713

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201220016385 Expired - Fee Related CN202690083U (en) 2012-01-13 2012-01-13 Waterproof structure of shield tunnel duct piece

Country Status (1)

Country Link
CN (1) CN202690083U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104018857A (en) * 2014-03-26 2014-09-03 福州市规划设计研究院 Splicing paving method of waterproof plates in tunnel and splicing paving structure of waterproof plates in tunnel
CN110006348A (en) * 2019-03-19 2019-07-12 天津大学前沿技术研究院有限公司 A kind of early warning type Shield-bored tunnels segments' joints waterproofing performance intelligent monitoring method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104018857A (en) * 2014-03-26 2014-09-03 福州市规划设计研究院 Splicing paving method of waterproof plates in tunnel and splicing paving structure of waterproof plates in tunnel
CN104018857B (en) * 2014-03-26 2016-01-13 福州市规划设计研究院 A kind of splicing laying method of anchor bar of waterproof plate in tunnels and structure thereof
CN110006348A (en) * 2019-03-19 2019-07-12 天津大学前沿技术研究院有限公司 A kind of early warning type Shield-bored tunnels segments' joints waterproofing performance intelligent monitoring method

Similar Documents

Publication Publication Date Title
CN103206230A (en) Waterproof structure of shield tunnel segment
CN202690083U (en) Waterproof structure of shield tunnel duct piece
CN207213352U (en) A kind of borehole wall of drainage inspection well and the draw bail of water pipe
CN204959824U (en) Structure is flowed in lap guard of underground continuous wall gasbag formula
CN206158767U (en) Shield tunnel pipe sheet joint waterproof elastic sealing pad
CN210739677U (en) Prevent municipal natural gas line of leakage
CN204262063U (en) Cold roller-way backwater waterproof construction in a kind of
CN103742167B (en) Possesses the Structural Test of Tunnel Segments of difference waterproof ability
CN207295853U (en) A kind of fire-fighting safety fire hydrant
CN207891741U (en) A kind of bridge cable protecting pipe of resistance to intensive ultraviolet
CN203656395U (en) PP pipe joint
CN205715634U (en) Self sealss fixing ring
CN203049715U (en) Integrated stainless steel water channel
CN204238953U (en) A kind of fixed structure of tunnel
CN203643583U (en) Battery leakage detecting device
CN203613521U (en) Gate with sealing structure
CN203628129U (en) Plastic tube joint provided with copper inserts
CN210599386U (en) Oil head oil seal spacer ring of water injection pump
CN202359871U (en) Soft shielding door of shielding tent
CN206488056U (en) A kind of petroleum pipeline monitors receiver
CN205579022U (en) Blind plate
CN207246656U (en) Smoke controlling air hose fast blockage structure
CN206931951U (en) A kind of pre-assembled cable tube
CN203702673U (en) Water intake self-flushing structure for double-shell multistage centrifugal pump
CN206173923U (en) Rescue equipment on water

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20130123

Termination date: 20210113

CF01 Termination of patent right due to non-payment of annual fee