CN202678826U - Operation stand for exchanging insulators - Google Patents

Operation stand for exchanging insulators Download PDF

Info

Publication number
CN202678826U
CN202678826U CN 201220167816 CN201220167816U CN202678826U CN 202678826 U CN202678826 U CN 202678826U CN 201220167816 CN201220167816 CN 201220167816 CN 201220167816 U CN201220167816 U CN 201220167816U CN 202678826 U CN202678826 U CN 202678826U
Authority
CN
China
Prior art keywords
utility
model
insulator
insulators
stretcher rod
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 201220167816
Other languages
Chinese (zh)
Inventor
郑义
李洪宇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Maintenance Branch of State Grid Hebei Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Maintenance Branch of State Grid Hebei Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Maintenance Branch of State Grid Hebei Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN 201220167816 priority Critical patent/CN202678826U/en
Application granted granted Critical
Publication of CN202678826U publication Critical patent/CN202678826U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Insulators (AREA)

Abstract

The utility model provides an operation stand for exchanging insulators, which is suitable to be used for exchanging insulators on a multi-voltage-level power transmission line of an electric power system. The operation stand consists of a stretcher rod capable of being hung on steel caps among ceramic bottles of the insulators, a steel cap hook is arranged at one end of the stretcher rod, and a seat plate and a pedal are arranged at the other end of the stretcher rod. The operation stand disclosed by the utility model has a simple structure and is simply and firmly fixed on an insulator chain in hooking and hanging manner by fully utilizing a mechanical principle of a tamper frame and depending on a double-chain insulator parallel arrangement structure, so that the operation posture of an operator on the insulator chain is well changed. With the operation stand disclosed by the utility model, a person can operate on the insulator chain in a labor-saving and comfortable manner, and the stability of the body of the person and the safety are improved.

Description

A kind of replacing insulator operating platform frame
Technical field
The utility model relates to a kind of replacing insulator operating platform frame.
Background technology
In September, 2010, the building up of peaceful east-Shandong ± 660kV super high voltage direct current electricity transmission line, created on present China and even the world's direct current construction history three large: sectional area of wire is maximum, insulator sheet number at most, wire spacing is the widest.Although the development work of check man's utensil draws to an end at present, repair method and scheme are still waiting further perfect.Particularly change the work of strain insulator monolithic insulator,, monolithic insulator heavier etc. large because of its insulator string spacing causes work difficulty to strengthen, usually the operating personnel rides and sits insulator string and get final product work on the 500kV circuit, still ± the 660kV DC line on just dying.Insulator disk track 380mm, apart from 650mm, the operating personnel can't sit at all in the above between string.When entering wire by insulator, can only adopt and creep or the method for " stride two short by three " is carried out, operating personnel's health stable very poor, rising does not sell at all carries out other operation.Because the insulator tonnage is large, weight is also just large, the jig that changes monolithic is also heavy especially, just can carry out this work so the operating personnel only possesses good work posture, wastes time and energy.
The utility model content
Technical problem to be solved in the utility model provides a kind of electric power system multi-voltage grade transmission line that is applicable to easy to use and good stability and changes the insulator operating platform frame.
The utility model adopts following technical scheme:
The utility model can be hung on by one that the stretcher rod on the steel cap consists of between the porcelain insulator bottle, and an end of described stretcher rod is provided with steel cap hook, and the other end of stretcher rod is provided with seat board and pedal.
Good effect of the present utility model is as follows:
The utility model simple structure, take full advantage of and ram the principle that booster is learned, the structure that relies on two insulator strings to be arranged in parallel adopts hook, extension mode not only simply but also firmly the utility model to be fixed on the insulator string, thereby has well changed the work posture of operating personnel on insulator string.The utility model operating platform frame of making according to GB GB/T18037-2000 " high-altitude operations tool specification requirement and design guide rule ", by mechanical test, satisfies the work high above the ground specification requirement.The utility model operating platform frame is long to be 1.2m, and wide is 0.3m, and weight is 5.8kg, and the maximum capacity load is 350 kg, can satisfy the load of an operation personnel own wt fully.
After using the utility model operating platform frame, can't improvement of operation be the operation of power-saving on insulator string from personnel, further strengthen the stability of personnel's healths, safety system be improved.Through overtesting, the utility model operating platform frame at strain insulator dress, tear open conveniently, the operating personnel is free and relaxed during transfer position between insulator and paralell, when the utility model paralell operates, good stability, convenient operation has guaranteed operating personnel's personal safety.In addition, the utility model operation horizontal stand can also be applied to the setting of personnel's inconvenience erect-position on the steel tower, and purposes is very extensive.
The utility model operating platform frame is novel in design, and volume is small and exquisite, is beneficial to vehicle transport.The utility model adopts high strength linepipe, and weight is light, transmit on the tower when not only being convenient to work high above the ground, and when working truck can not arrive on high mountain, personnel carries convenient.Install simply, save the work high above the ground time, alleviate operating personnel's labour intensity.The utility model seat board height 450mm is equal to routine office work seat height, comfort for sitting posture, and be provided with foot pedal, personnel can stand up in operating process, are convenient to the operation of different angles.Anti-skidding backrest has avoided personnel when overexerting, and health is slippage backward.
At present, the UHV transmission line of China is in the starting stage, electric pressure improve constantly the main feature that becomes power grid construction with emerging in an endless stream of new equipment, new material.The application of large-tonnage insulator in the DC line forces us must constantly improve the upkeep operation methods.The utility model change insulator with the solution of the birth success of operating platform frame this electric pressure transmission line can't operation on insulator string a difficult problem.Even how the wire pitch of circuit is adjusted in the future, we still can utilize the design principle of the utility model paralell, and the manufacturing dimension of adjusting operation frame is made corresponding " operating platform frame ".Thus, the utility model paralell is widely used, and has higher promotional value.
The utility model operating platform frame is simple in structure, and materials are few, and low cost of manufacture is economical and practical.Adopt the utility model that the operation that can't carry out is finished smoothly, zero low resistance insulator of discovery in service can in time be changed, sound assurance the stable operation of electrical network, the tremendous economic of having avoided causing owing to equipment fault is lost.The cleaning of rope is transmitted in insulation, guarantees to have saved under the safe prerequisite fund that rope is transmitted in insulation of buying.
Description of drawings
Accompanying drawing 1 is the utility model structural representation.
Accompanying drawing 2 uses state diagram for the utility model.
In the accompanying drawings: 1 stretcher rod, 2 steel caps hook, 3 seat boards, 4 pedals, 5 porcelain vases, 6 steel caps.
Embodiment
As shown in Figure 1, the utility model can be hung on by one that the stretcher rod on the steel cap 1 consists of between the porcelain insulator bottle, and an end of described stretcher rod 1 is provided with steel cap hook 2, and the other end of stretcher rod 1 is provided with seat board 3 and pedal 4.
As shown in Figure 2, when using the utility model, the utility model is fixed on steel cap 6 places of 5 in the parallel porcelain insulator bottle of two strings, two string porcelain vase 5 of strain tower are and are horizontally disposed with, at first stretcher rod 1 of the present utility model is hung on the steel cap 6 of 5 of a string porcelain vase wherein, steel cap hook 2 is hooked on the steel cap 6 of 5 of another string porcelain vase, the operator just can be sitting on the seat board 3 like this, and both feet are placed on pedal 4 enterprising line operates.
The utility model operating platform frame simple structure, the structure that relies on two insulator strings to be arranged in parallel, adopt hook, extension mode not only simply but also firmly the utility model to be fixed on the insulator string, thereby well changed the work posture of operating personnel on insulator string.The utility model operating platform frame of making according to GB GB/T18037-2000 " high-altitude operations tool specification requirement and design guide rule ", by mechanical test, satisfies the work high above the ground specification requirement.The utility model is long to be 1.2m, and wide is 0.3m; Weight is 5.8kg, and the maximum capacity load is 350 kg, can satisfy the load of an operation personnel own wt fully.
After using the utility model operating platform frame, can't improvement of operation be the operation of power-saving on insulator string from personnel, further strengthen the stability of personnel's healths, safety system be improved.Through overtesting, the utility model operating platform frame at strain insulator dress, tear open conveniently, the operating personnel is free and relaxed during transfer position between insulator and paralell, when the utility model paralell operates, good stability, convenient operation has guaranteed operating personnel's personal safety.In addition, the utility model operation horizontal stand can also be applied to the setting of personnel's inconvenience erect-position on the steel tower, and purposes is very extensive.
The utility model operating platform frame is novel in design, and volume is small and exquisite, is beneficial to vehicle transport.The utility model adopts high strength linepipe, and weight is light, transmit on the tower when not only being convenient to work high above the ground, and when working truck can not arrive on high mountain, personnel carries convenient.Install simply, save the work high above the ground time, alleviate operating personnel's labour intensity.The utility model seat board height 450mm is equal to routine office work seat height, comfort for sitting posture, and be provided with foot pedal, personnel can stand up in operating process, are convenient to the operation of different angles.Anti-skidding backrest has avoided personnel when overexerting, and health is slippage backward.
At present, the UHV transmission line of China is in the starting stage, electric pressure improve constantly the main feature that becomes power grid construction with emerging in an endless stream of new equipment, new material.The application of large-tonnage insulator in the DC line forces us must constantly improve the upkeep operation methods.The utility model change insulator with the solution of the birth success of operating platform frame this electric pressure transmission line can't operation on insulator string a difficult problem.Even how the wire pitch of circuit is adjusted in the future, we still can utilize the design principle of the utility model paralell, and the manufacturing dimension of adjusting operation frame is made corresponding " operating platform frame ".Thus, the utility model paralell is widely used, and has higher promotional value.
The utility model operating platform frame is simple in structure, and materials are few, and low cost of manufacture is economical and practical.Adopt the utility model that the operation that can't carry out is finished smoothly, zero low resistance insulator of discovery in service can in time be changed, sound assurance the stable operation of electrical network, the tremendous economic of having avoided causing owing to equipment fault is lost.The cleaning of rope is transmitted in insulation, guarantees to have saved under the safe prerequisite fund that rope is transmitted in insulation of buying.

Claims (1)

1. change the insulator operating platform frame for one kind, it is characterized in that it can be hung on the stretcher rod on the steel cap (1) formation between the porcelain insulator bottle by one, one end of described stretcher rod (1) is provided with steel cap hook (2), and the other end of stretcher rod (1) is provided with seat board (3) and pedal (4).
CN 201220167816 2012-04-19 2012-04-19 Operation stand for exchanging insulators Expired - Fee Related CN202678826U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201220167816 CN202678826U (en) 2012-04-19 2012-04-19 Operation stand for exchanging insulators

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201220167816 CN202678826U (en) 2012-04-19 2012-04-19 Operation stand for exchanging insulators

Publications (1)

Publication Number Publication Date
CN202678826U true CN202678826U (en) 2013-01-16

Family

ID=47499702

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201220167816 Expired - Fee Related CN202678826U (en) 2012-04-19 2012-04-19 Operation stand for exchanging insulators

Country Status (1)

Country Link
CN (1) CN202678826U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102611040A (en) * 2012-04-19 2012-07-25 河北省电力公司超高压输变电分公司 Operation stand for exchanging insulators

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102611040A (en) * 2012-04-19 2012-07-25 河北省电力公司超高压输变电分公司 Operation stand for exchanging insulators

Similar Documents

Publication Publication Date Title
CN205029247U (en) Folding maintenance ladder of overhead transmission line multipurpose
CN202785338U (en) Large plate girder overturning seat
CN202140007U (en) Portable safety ladder
CN202678826U (en) Operation stand for exchanging insulators
CN201990380U (en) Special lifting tool for spools of ultra large rope forming machine
CN203066839U (en) Insulated extension ladder
CN202678827U (en) Seat frame for replacing insulators
CN102611040A (en) Operation stand for exchanging insulators
CN201934006U (en) Power overhaul working ladder
CN204643644U (en) A kind of novel building small-sized crane
CN203813313U (en) Mobile workbench for check and repair of strain insulator string
CN204720888U (en) Portable power distribution less important work platform
CN203264089U (en) Portable transformer anti-drop rod
CN201705193U (en) Dedicated flexible ladder used for replacing insulators
CN203787859U (en) Portable derrick applied to transmission line overhauling
CN202926197U (en) Auxiliary hooking device for safety belt of steel tube tower
CN201882845U (en) Portable special jack for cable cover plate
CN203419729U (en) Lifting chair
CN103618248A (en) Direct current high-tension transmission line maintenance method and special safety hanging seat
CN205901172U (en) Nearly pole of transmission line overhauls corridor hanger device
CN201643562U (en) mechanical pole climbing device
CN203306988U (en) High-place operation auxiliary transfer car
CN205011276U (en) Rubber tired crane suitable for building trade
CN204103358U (en) Equipotential replacing insulator specific purpose tool
CN203728505U (en) Hoisting-bulldozing dual-purpose construction trolley

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20130116

Termination date: 20180419

CF01 Termination of patent right due to non-payment of annual fee